System Fuels, Inc. v. United States 0

110 Fed. Cl. 583, 2013 U.S. Claims LEXIS 309
CourtUnited States Court of Federal Claims
DecidedApril 23, 2013
Docket03-2623C
StatusPublished
Cited by2 cases

This text of 110 Fed. Cl. 583 (System Fuels, Inc. v. United States 0) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
System Fuels, Inc. v. United States 0, 110 Fed. Cl. 583, 2013 U.S. Claims LEXIS 309 (uscfc 2013).

Opinion

Post-trial decision in a remanded case involving the Standai’d Contract for pickup of spent nuclear fuel; application of the 1987 industry-wide acceptance rate; causation; costs of mitigation for partial breach; avoided costs

OPINION AND ORDER

LETTOW, Judge.

The Department of Energy (“DOE”) has failed to fulfill its contractual obligation to collect and dispose of spent nuclear fuel (“SNF”) and high-level radioactive waste (“HLW ”) generated at the two-unit Arkansas Nuclear One (“ANO”) power plant located at Russellville, Arkansas. Plaintiffs, System Fuels, Inc. and Entergy Arkansas, Inc. (collectively “System Fuels,” or “plaintiffs”), own the units and seek damages for the government’s breach of contract. The court previously granted System Fuels summary judgment on liability for a partial breach of contract, see System Fuels, Inc. v. United States, 65 Fed.Cl. 163, 177 (2005) (“System Fuels I”), and the court determined damages in a subsequent post-trial decision, see System Fuels, Inc. v. United States, 79 Fed.Cl. 37 (2007) (“System Fuels III”), 1 recons, denied, 79 Fed.Cl. 182 (2007) (“System Fuels IV”), aff'd in part, rev’d in part, System Fuels, Inc. v. United States, 457 Fed.Appx. 930 (Fed.Cir.2012) (“System Fuels V”).

The court’s decision awarded $48,651,728 in damages, using an industry-wide acceptance rate of 3,000 MTU per year (“the 3000 MTU rate” or “3000 rate”) to calculate the amount of spent nuclear fuel which would have been removed by DOE, had it performed on the contract. See System Fuels III, 79 Fed.Cl. at 55, 74. 2 On appeal, the Federal Circuit affirmed in part but determined that the 3000 MTU rate was not the appropriate rate; rather, the court should have applied the acceptance rate identified in DOE’s 1987 Annual Capacity Report (“the 1987 rate”). System Fuels V, 457 Fed.Appx. at 934. 3 The case was remanded to this court for analysis of causation and damages employing the 1987 rate.

*587 The remand trial occurred over seven days in October and November of 2012. The bulk of the damages awarded in the original trial were not contested at the remand trial, as neither party contended that they were affected by the rate change. See DX 538 at 9 (Report of Robert Peterson, an expert testifying on behalf of the government) (noting $34,051,573 of uncontested damages). The parties focused during the remand trial on four specific areas of plaintiffs’ mitigation of defendant’s partial breach where damages might have been altered. Post-trial briefing has now concluded and closing argument was held on March 18, 2013. The case is ready for disposition.

FACTS 4

A. The Nuclear Waste Policy Act

During the normal course of operation, nuclear reactors produce radioactive waste in the form of SNF and HLW. To “avoid the inefficient and potentially unsafe prospect of allowing individual utilities to recycle or dispose of their own [SNF],” Congress enacted the Nuclear Waste Policy Act of 1982, Pub. L. No. 97-425, 96 Stat. 2201 (Jan. 7, 1983) (“NWPA”) (codified as amended at 42 U.S.C. §§ 10101-10270). The NWPA authorizes “the siting, construction, and operation of repositories” for storing SNF, and the subsequent use of those repositories for an indeterminate period. 42 U.S.C. § § 10131(a)(4), (b)(1), 10221(a).

Under the NWPA, DOE entered into a “Standard Contract for Disposal of Spent Nuclear Fuel and/or High-Level Radioactive Waste” (“the Standard Contract” or “contract”) with individual operators of nuclear plants. See, e.g., DX 1 (Pis.’ Standard Contract). 5 The terms of the Standard Contract called for payment of two fees by the utility: first, a one-time fee based on energy generated and sold before April 7, 1983, and, second, a continuing fee based on the amount of energy produced after that date. Id., Art. VIII. In exchange, DOE committed to removing SNF and HLW from the signatory plant operators starting no later than January 31, 1998. Id., Art. II. The precise dates and amounts of the SNF pickups are not specified in the Standard Contract, which simply states that DOE must claim the materials “as expeditiously as possible,” and assures that DOE would issue annual acceptance priority rankings for SNF pickup starting on April 1, 1991. Id. at 1, Art. IV.B.5(a).

System Fuels entered into a Standard Contract with DOE on June 30, 1983. DX 1 (Pis.’ Standard Contract). System Fuels has fully performed its obligations under the contract to date, and has been making payments on the one-time fee under the Standard Contract’s payments-with-interest option. As of the expiration of the claim period in this case, June 30, 2006, the expected one-time fee totaled roughly $165 million. System Fuels V, 457 Fed.Appx. at 932. System Fuels has also maintained full payment of the continuing fee, at a rate of approximately $13 to $15 million per year (reaching a total of nearly $269 million as of the expiration of the claim period). Id. In contrast, as of the date of the remand trial, DOE has yet to perform a single pickup of SNF or HLW from ANO. 2012 Tr. 51:22 to 52:5 (Test, of Kenneth B. Metcalfe, an expert testifying on behalf of plaintiff). 6 Thus, all SNF or HLW which should have been taken and stored by DOE under the Standard Contract instead remains the burden of System Fuels.

B. The ANO facility

The Arkansas Nuclear One power plant owned and operated by plaintiffs consists of two units, the first a Babcock & Wilcox reactor (“Unit 1”) and the second a Combustion *588 Engineering reactor (“Unit 2”). Specifically, this remand trial focused on four particular-areas of expense which System Fuels contends were incurred to mitigate the government’s partial breach: Boraflex degradation mitigation, use of dry storage casks, replacement of the L-3 loading crane, and replacement of the water transfer system. The evidence presented at the remand trial addressed causation and certain “avoided costs” associated with these four areas.

1. Boraflex.

Each unit at ANO is designed to operate with 177 nuclear assemblies in its core. 2012 Tr. 175:8-11 (Test, of Christopher Walker, Senior Engineer, ANO). These units must be periodically refueled, which involves offloading spent fuel into a spent fuel pool and bringing in fresh fuel to the reactors to replace spent fuel that is not reloaded. 7

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
110 Fed. Cl. 583, 2013 U.S. Claims LEXIS 309, Counsel Stack Legal Research, https://law.counselstack.com/opinion/system-fuels-inc-v-united-states-0-uscfc-2013.