Pacific Gas & Electric Co. v. United States

668 F.3d 1346, 2012 WL 540055, 2012 U.S. App. LEXIS 3384
CourtCourt of Appeals for the Federal Circuit
DecidedFebruary 21, 2012
Docket2010-5123
StatusPublished
Cited by18 cases

This text of 668 F.3d 1346 (Pacific Gas & Electric Co. v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pacific Gas & Electric Co. v. United States, 668 F.3d 1346, 2012 WL 540055, 2012 U.S. App. LEXIS 3384 (Fed. Cir. 2012).

Opinion

RADER, Chief Judge.

In this spent nuclear fuel case, the United States Court of Federal Claims entered *1349 a damages judgment in favor of PlaintiffAppellee Pacific Gas & Electric Company (“PG & E”). Because the new judgment accounts for the proper causation times and principles, this court affirms the trial court’s decision.

I.

This court heard this case earlier and will not repeat the complete factual background. Pac. Gas & Elec. Co. v. United States, 536 F.3d 1282, 1284-87 (Fed.Cir. 2008). This case, like its predecessor, “involves the damages calculation” for the Government’s partial breach of the Standard Contract. Id. at 1284. In the earlier 2008 appeal, the trial court had relied upon the 1991 Annual Capacity Report (“ACR”) and the “duty of good faith and fair dealing.” This court determined that 1991 ACR was an incorrect acceptance rate. Id. at 1284. Instead, this court, at a time after the trial court’s ruling, had set the 1987 ACR as the appropriate acceptance rate for a causation analysis under the Standard Contract. Id. at 1291-92. On remand, the trial court had “the opportunity to calculate the damages owed to PG & E for [the Department of Energy’s (“DOE”) ] partial breach of the Standard Contract.” Id. at 1292.

On remand, the trial court “focuse[d] on whether the costs claimed as damages by PG & E were incurred as a direct and reasonably foreseeable result of defendant’s partial breach of the [Standard Contract].” Pac. Gas & Elec. Co. v. United States, 92 Fed.Cl. 175, 179 (2010). Plaintiffs claimed the following six categories of damages:

(1) costs incurred related to the evaluation of storage options and the licensing and construction of an independent spent fuel storage installation (ISFSI) and temporary racks at its Diablo Canyon power plant; (2) costs incurred for maintaining its Humboldt Bay power plant in custodial [safe storage (“SAFSTOR”) ] status after 1998; (3) costs incurred in the licensing and construction of an ISFSI at its Humboldt Bay plant; (4) incremental costs of removing the ventilation stack at its Humboldt Bay plant while spent fuel continued to be stored in the spent fuel pool; (5) evaluation of Private Fuel Storage (PFS) off-site storage options for both plants; and (6) internal and external legal costs related to the activities contained in the other categories.

Id. at 180. The Government did not dispute the amount of damages in each category, but continued to dispute PG & E’s entitlement to those damages. Id. Indeed the Government “acknowledge^] that PG & E [was] entitled to recover approximately $82 million of its approximately $92 million in damages claims on remand.” Id. Specifically, under the 1987 ACR, the Government acknowledged that “PG & E [was] entitled to recover on remand the following costs: (1) Humboldt Bay SAFSTOR costs from 2000-2004, in the amount of $38,678,000; (2) Humboldt Bay ISFSI costs in the amount of $7,945,000; (3) Diablo Canyon ISFSI costs in the amount of $31,734,000; (4) Diablo Canyon temporary rack costs in the amount of $2,663,807; and (5) Diablo Canyon Storage Options study costs in the amount of $1,451,091.” Id. The trial court found that PG & E would not have incurred these reasonably foreseeable costs but for the Government’s breach. Id. at 182. The trial court also found that the record supported these amounts with reasonable certainty. Id.

On remand, the trial court focused on the disputed costs, i.e., Humboldt Bay SAFSTOR costs in 1999, Humboldt Bay ISFSI costs for Greater Than Class C waste (“GTCC”), evaluation of PFS off-site storage, costs associated with stack removal, as well as internal and external legal costs. Id. at 182-203. With respect to the 1999 costs at Humboldt Bay, the trial *1350 court determined that the Government’s partial breach caused PG & E to incur $4,744,000 in SAFSTOR costs. Id. at 183-86. The trial court then offset this amount by the amount PG & E would have paid to exchange its 1999 allocation for an allocation right in the 1998 priority queue. After this offset, the trial court awarded $4,044,000 for the Humboldt Bay SAFSTOR costs in 1999. Id. at 188-89.

Concerning the Humboldt Bay ISFSI costs for GTCC, the trial court, consistent with this court’s decision in Yankee Atomic Electric Co. v. United States, 536 F.3d 1268 (Fed.Cir.2008), awarded PG & E the full amount of damages, totaling $9,534,000 which included $1,589,000 for the costs associated with storing the GTCC. Id. at 193. The trial court specifically found that it was “more likely than not” that DOE would have collected the GTCC when it collected the spent nuclear fuel (“SNF”). Id. Regarding the PFS, the trial court determined: “Based on a preponderance of the credible evidence ... the costs plaintiff incurred for the evaluation of the off-site storage options were both caused by the government’s partial breach of the Standard Contract and foreseeable as the natural and probable result of the government’s partial breach.” Id. at 196-97. Thus, PG & E received an award of $889,517 in damages. Id.

The trial court upheld its previous denial of the stack removal costs because the “more persuasive testimony” supported the finding that PG & E would have removed the ventilation stacks for safety reasons. Id. at 197-98. Therefore, the application of the 1987 ACR did not impact this earlier finding. Id. Finally, the trial court determined that the mandate from this court and the statute of limitations barred the claim for internal and external legal costs because this claim could have been presented at the initial trial but PG & E waited to present this claim for the first time on remand. Id. at 199-202.

After totaling the damages award, the trial court set the amount for PG & E at $89,004,415. Id. at 204. The Government timely filed its appeal of the trial court’s decision. On appeal, the Government contends that the earlier mandate barred the trial court’s award of damages for the PFS and the Humboldt Bay SAFSTOR 1999 costs based on an exchanges model. As such, the Government appeals $4,933,517 of the trial court’s damages award. This court has jurisdiction under 28 U.S.C. § 1295(a)(3).

II.

This court reviews an interpretation of its own mandate without deference. Laitram Corp. v. NEC Corp., 115 F.3d 947, 950-51 (Fed.Cir.1997).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jones v. United States
Federal Circuit, 2026
Meridian Engineering Company v. United States
885 F.3d 1351 (Federal Circuit, 2018)
Banks v. United States
Federal Circuit, 2017
Sacramento Municipal Utility District v. United States
120 Fed. Cl. 270 (Federal Claims, 2015)
Kellogg Brown & Root Services, Inc. v. United States
728 F.3d 1348 (Federal Circuit, 2013)
St. John v. Peterson
2013 SD 67 (South Dakota Supreme Court, 2013)
System Fuels, Inc. v. United States 0
110 Fed. Cl. 583 (Federal Claims, 2013)
Dairyland Power Cooperative v. United States
106 Fed. Cl. 102 (Federal Claims, 2012)
Yankee Atomic Electric Co. v. United States
679 F.3d 1354 (Federal Circuit, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
668 F.3d 1346, 2012 WL 540055, 2012 U.S. App. LEXIS 3384, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pacific-gas-electric-co-v-united-states-cafc-2012.