Yankee Atomic Electric Co. v. United States

679 F.3d 1354
CourtCourt of Appeals for the Federal Circuit
DecidedMay 18, 2012
Docket2011-5020, 2011-5021, 2011-5022, 2011-5027, 2011-5028, 2011-5029
StatusPublished
Cited by17 cases

This text of 679 F.3d 1354 (Yankee Atomic Electric Co. v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Yankee Atomic Electric Co. v. United States, 679 F.3d 1354 (Fed. Cir. 2012).

Opinion

RADER, Chief Judge.

This consolidated appeal is the latest manifestation of the numerous contract disputes arising from the Government’s failure to accept and dispose of radioactive waste from the nation’s nuclear utilities. Specifically, the appeal flows from this court’s decision in Yankee Atomic Electric Co. v. United States, 536 F.3d 1268 (Fed.Cir.2008), which reversed the United States Court of Federal Claims’ initial *1357 damages determination, and remanded for a calculation of damages according to the rate at which the Government was contractually obligated to accept the utilities’ waste.

Yankee Atomic Electric Company (Yankee Atomic), Maine Yankee Atomic Power Company (Maine Yankee), and Connecticut Yankee Atomic Power Company (Connecticut Yankee) (collectively, the Yankees) originally brought this action seeking damages to compensate for the cost of storing spent nuclear fuel (SNF) and high-level radioactive waste (HLW) beyond the time that the Government promised by contract to begin storing that waste in a permanent and secure repository. On remand, the trial court correctly calculated damages for dry storage construction costs, deferred costs of loading waste to the Department of Energy (DOE), and reracking costs. However, the trial court erred in denying Yankee Atomic’s claim for a portion of its wet pool storage costs and Nuclear Regulatory Commission (NRC) fees. Unlike Consolidated Edison Co. of N.Y. v. United States, 676 F.3d 1331 (Fed.Cir.2012), this case does not include a claim for NRC fees that allegedly increased due to DOE’s breach. Rather, the plaintiff here claims that no NRC fees would have been incurred by the inactive plant if the SNF had been removed in a timely manner pursuant to the Standard Contract. See Yankee Atomic Power Co. v. United States, 94 Fed.Cl. 678, 725 (2010).

Therefore, this court affirms-in-part and reverses-in-part the trial court’s damages award as recited below.

I.

This court has ofteii addressed the Standard Contract between the Government and nuclear utilities, and the Government’s liability for a partial breach. See Me. Yankee Atomic Power Co. v. United States, 225 F.3d 1336, 1337-40 (Fed.Cir.2000); Yankee Atomic Elec. Co. v. United States, 73 Fed.Cl. 249, 250-259 (2006) (Yankee I). However, the history of this case is necessary on this appeal from an earlier remand decision.

Starting in August 2004, the trial court held a seven-week trial on damages. Yankee I, 73 Fed.Cl. at 251. Yankee Atomic received as damages $32,863,366 to compensate for the cost of building dry storage (i.e., an independent spent fuel storage installation (ISFSI)); Connecticut Yankee received $8,350,893 for reracking its wet pool to increase storage capacity and $25,803,986 for ISFSI construction; and Maine Yankee received $10,069,018 for reracking costs and $65,705,536 for ISFSI construction expenses. Id. at 326. During the Yankee I trial, the Government argued that Greater Than Class C radioactive waste (GTCC) was not covered by the Standard Contract. According to the Government, the Yankees would have been required to build dry storage for GTCC in the non-breach world, thus incurring ISFSI costs (in whole or in part). Id. at 312-15. The trial court rejected this argument. Id.

On appeal, this court accepted the trial court’s “findings on foreseeability, reasonable certainty and the use of the substantial causal factor standard” for causation purposes, as well as the determination that an award of Nuclear Waste Fund fees should be denied as premature. Yankee Atomic Elec. Co. v. United States, 536 F.3d 1268, 1272-4 (Fed.Cir.2008) (Yankee II). However, this court noted that the trial court made its causation analysis “without formally interpreting the Standard Contract” and did not fulfill its “obligation” to “apply [the 1987 annual capacity report] rate in determining the substantial cause of the Yankees’ costs.” Id. at 1274. For that reason, this court remanded for *1358 application of the 1987 annual capacity report (ACR) rate to the damages claimed by the parties. The 1987 ACR set forth the projected annual waste receiving capacity for DOE and the annual acceptance ranking relating to DOE contracts for the disposal of SNF and/or HLW. Pac. Gas & Elec. Co. v. United States, 73 Fed.Cl. 333, 399-400 (2006).

On remand, the trial court accepted the fuel exchange model presented by the Yankees’ expert, and concluded that the Yankees would not have built dry storage; Maine Yankee and Connecticut Yankee also, according to the trial court, would not have reracked their storage pools under the 1987 ACR rate. Yankee Atomic Power Co. v. United States, 94 Fed.Cl. 678, 685-86 (2010) (Yankee III). The trial court found that, using fuel exchanges, the Yankees would have emptied their wet storage facilities in the non-breach world within the first ten years of DOE’s performance. Id. at 688-93.

The trial court also addressed certain “matters beyond the remand and mandate.” Id. at 717-19. Each side claimed the other presented issues beyond the scope of the remand. Id. at 719-20. The Yankees claimed that the Government’s argument to include GTCC pickup in the 1987 ACR queue was “of new cloth” and beyond the scope of the mandate. Id. at 719, 721. The Government responded that the Yankees’ claims for the cost of transferring SNF from their wet pools to DOE (including crane upgrades) were beyond the scope of the mandate. Id. at 720, 726. The Government also objected to Yankee Atomic’s claim for the costs to operate and maintain (O & M) its wet pool for 2000 and 2001, as well as its NRC fees.

The trial court found that the Government’s argument to include GTCC into the 1987 ACR queue was not raised during the Yankee I trial and was thus barred. Id. at 722. However, the trial court noted that even if the issue was not barred, “removal of GTCC by the date of at least the last SNF removal” would likely have occurred. Id. at 723. Moreover “the GTCC generated from shut-down reactors was statistically insignificant and would not have had an appreciable affect [sic] on the SNF queue.” Id. at 724. Finally “costs associated with dry storage and reracking would not have been incurred due to the presence of GTCC.” Id. at 725.

Another remand issue involved the costs of future loading to DOE and crane upgrades. The Yankees had voluntarily deducted these costs from the damages in Yankee I under the belief these costs were avoided costs and thus not recoverable.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Shell Oil Company v. United States
123 Fed. Cl. 707 (Federal Claims, 2015)
Sacramento Municipal Utility District v. United States
120 Fed. Cl. 270 (Federal Claims, 2015)
Sacramento Municipal Utility District v. United States
566 F. App'x 985 (Federal Circuit, 2014)
Gallagher v. San Diego Unified Port District
14 F. Supp. 3d 1380 (S.D. California, 2014)
Carolina Power & Light Co. v. United States
115 Fed. Cl. 57 (Federal Claims, 2014)
Yankee Atomic Electric Company v. United States
113 Fed. Cl. 323 (Federal Claims, 2013)
Fresenius USA, Inc. v. Baxter International, Inc.
721 F.3d 1330 (Federal Circuit, 2013)
Parra v. Bashas', Inc.
291 F.R.D. 360 (D. Arizona, 2013)
System Fuels, Inc. v. United States 0
110 Fed. Cl. 583 (Federal Claims, 2013)
Portland General Electric Co. v. United States
107 Fed. Cl. 633 (Federal Claims, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
679 F.3d 1354, Counsel Stack Legal Research, https://law.counselstack.com/opinion/yankee-atomic-electric-co-v-united-states-cafc-2012.