System Fuels, Inc. v. United States

79 Fed. Cl. 182, 2007 U.S. Claims LEXIS 357, 2007 WL 3378057
United States Court of Federal Claims·Decided November 9, 2007·No. No. 03-2623C·Published·Cited by 21 cases

Opinion

OPINION AND ORDER

LETTOW, Judge.

The government has moved for reconsideration of the post-trial judgment entered October 16, 2007 in this contract case involving spent nuclear fuel (“SNF”). Judgment was entered on the basis of the court’s decision rendered on that same day. See System Fuels, Inc. v. United States, 79 Fed.Cl. 87, 2007 WL 3033659 (Oct. 16, 2007) (“System Fuels III”). The government’s motion raises two issues that merit discussion. One involves an issue of causation associated with the nature and extent of the Department of Energy’s contractual obligation to pick up SNF from plaintiffs’ two-unit nuclear power plant. The other concerns the standards employed by the court in concluding that modifications to water transfer systems at the spent fuel pools in plaintiffs’ power plant were part of plaintiffs’ mitigation of, and caused by, defendant’s partial breach of contract.

BACKGROUND FACTS

On June 30, 1983, the Department of Energy (“DOE”) and plaintiffs (collectively, “System Fuels”) entered into a so-called Standard Contract for Disposal of Spent Nuclear Fuel and/or High-Level Radioactive Waste. DX 1 (DOE Contract DE CRO 183NE44363) (“System Fuels Standard Contract”).1 In essence, that contract calls for DOE to collect and dispose of SNF generated by System Fuels’ two-unit Arkansas Nuclear One (“ANO”) power plant at Russell-ville, Arkansas, in exchange for payment of a one-time fee and continuing fees based upon the amount of electricity produced at the plant via nuclear means. Id. DOE’s collection of SNF for disposal was due to begin on January 31, 1998, but thus far DOE has failed to perform. System Fuels III, 79 Fed.Cl. at 40-41, 2007 WL 3033659, at *1-2. System Fuels, however, has fulfilled its obligations, duly paying the continuing fees contemplated by the Standard Contract and invoking a contractual option to defer payment of the one-time fee, accruing interest on that [184]*184deferral as the Contract provides. Id. at 41-43, 2007 WL 3033659, at *3-4.

System Fuels brought this suit for partial breach of the Standard Contract, and in due course this court granted System Fuels summary judgment on liability. System Fuels, Inc. v. United States, 65 Fed.Cl. 163, 177 (2005) (“System Fuels I”). The complaint was thereafter amended such that the period covered by this partial breach case extends through June 30, 2006. See System Fuels, Inc. v. United States, 73 Fed.Cl. 206, 212 (2006) (“System Fuels II”). Following a seventeen-day trial on damages in February, March, and April 2007, System Fuels was awarded $48,651,728 in damages. System Fuels III, 79 Fed.Cl. at 40, 68, 2007 WL 3033659, at *1, 38.

Standard for Decision

The government’s motion for reconsideration of the final judgment in System Fuels’ favor was timely filed. See Rule 59(b) of the Rules of the Court of Federal Claims (“RCFC”) (“[A] motion for a new trial, or for amendment or reconsideration of a judgment, shall be filed no later than 10 days after the entry of the judgment.”); see also RCFC 59(e) (“Any motion to alter or amend a judgment shall be filed no later than 10 days after entry of the judgment.”). In essence, the government would have the court “open the judgment” and “amend findings of fact and conclusions of law or make new findings and conclusions, and direct the entry of a new judgment.” RCFC 59(a)(1).

A motion for reconsideration constitutes a request for extraordinary relief in a matter that has been closed. See Caldwell v. United States, 391 F.3d 1226, 1235 (Fed. Cir.2004) (referring to a required showing of “extraordinary circumstances which justify relief,” quoting Fru-Con Constr. Corp. v. United States, 44 Fed.Cl. 298, 300 (1999), affd, 250 F.3d 762 (Fed.Cir.2000) (table)); see also Four Rivers Invs., Inc. v. United States, 78 Fed.Cl. 662, 664 (2007); Amber Resources Co. v. United States, 78 Fed.Cl. 508, 514 (2007). A court may grant such a motion when the movant shows “(1) that an intervening change in the controlling law has occurred; (2) that previously unavailable evidence is now available; or (3) that the motion is necessary to prevent manifest injustice.” Amber Resources, 78 Fed.Cl. at 514 (quoting Stockton E. Water Dist. v. United States, 76 Fed.Cl. 497, 499 (2007)); see also Bannum, Inc. v. United States, 59 Fed.Cl. 241, 243 (2003) (same). “To prevail on such a motion, ‘the movant must point to a manifest error of law or mistake of fact’ and must do more than ‘merely reassert[] arguments which were previously made and were carefully considered by the court.’ ” Bannum, 59 Fed.Cl. at 243 (quoting Henderson County Drainage Dist. No. 3 v. United States, 55 Fed.Cl. 334, 337 (2003)).

DISCUSSION

A. Causation Determined By Reference to the Capacity of A Monitored Retrievable Storage Facility Or A Repository

The principal thrust of the government’s motion is aimed at the court’s rejection of the government’s contentions respecting causation. See Def.’s Mot. for Reconsideration (“Def.’s Mot.”) at 2-5. The parties’ dispute over causation had its genesis in the fact that the Standard Contract did not establish a specific rate or schedule for the collection of SNF by DOE from contracting utilities. Rather, the Contract set out a process by which DOE would identify and then collect SNF from the utilities. See System Fuels III, 79 Fed.Cl. at 40-41, 2007 WL 3033659, at *2 (citing Southern Nuclear Operating Co. v. United States, 77 Fed.Cl. 396, 410 (2007); Tennessee Valley Auth. v. United States, 60 Fed.Cl. 665, 668 (2004)).2 System Fu[185]*185els relied on that contractual process to establish the baseline for DOE’s collection obligations under the Contract and to seek expectancy damages guided by that baseline. See Indiana Michigan Power Co. v. United States, 422 F.3d 1369, 1373 (Fed. Cir.2005) (“The [expectancy] remedy for breach of contract is damages sufficient to place the injured party in as good a position as it would have been had the breaching party performed.”). At trial, to describe the non-breach world for the causation aspect of this damages calculus, DOE relied on projected shipments of SNF to a monitored retrievable storage facility (“MRS”) for a period of at least ten years, commencing in 1998, without reference to a repository. Def.’s Mot. at 2-5. The court concluded, however, that such a description had a statutorily impermissible predicate and thus could not be applied in determining causation. See System Fuels III, 79 Fed.Cl. at 53-54, 2007 WL 3033659, at *18-19. On reconsideration, the government specifically challenges “the court’s finding that DOE sought a MRS that was ‘independent’ of a federal repository.” Def.’s Mot. at 2 (capitals omitted). However, the court made no such finding, and, indeed, it took care not to make a finding of that nature. The government has miscast the bases for the court’s rulings on causation.

In the Nuclear Waste Policy Act of 1982, Pub.L. No. 97-425, 96 Stat. 2201 (Jan. 7, 1983) (“NWPA”) (codified as amended at 42 U.S.C. §§

System Fuels, Inc. v. United States, 79 Fed. Cl. 182, 2007 U.S. Claims LEXIS 357, 2007 WL 3378057 (uscfc 2007).

79 Fed. Cl. 182 (System Fuels, Inc. v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Beberman v. United States
133 Fed. Cl. 138 (Federal Claims, 2017)
System Fuels, Inc. v. United States 0
110 Fed. Cl. 583 (Federal Claims, 2013)
Boston Edison Co. v. United States
106 Fed. Cl. 330 (Federal Claims, 2012)
Petro-Hunt, L.L.C. v. United States
105 Fed. Cl. 132 (Federal Claims, 2012)
Estate of Hage v. United States
90 Fed. Cl. 388 (Federal Claims, 2009)
Stovall v. United States
86 Fed. Cl. 770 (Federal Claims, 2009)
Alli v. United States
86 Fed. Cl. 33 (Federal Claims, 2009)
PCL Construction Services, Inc. v. United States
84 Fed. Cl. 408 (Federal Claims, 2008)