Town of North Bonneville v. United States

11 Cl. Ct. 694, 1987 U.S. Claims LEXIS 34
CourtUnited States Court of Claims
DecidedFebruary 20, 1987
DocketNo. 564-80C
StatusPublished
Cited by5 cases

This text of 11 Cl. Ct. 694 (Town of North Bonneville v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Town of North Bonneville v. United States, 11 Cl. Ct. 694, 1987 U.S. Claims LEXIS 34 (cc 1987).

Opinion

OPINION

HARKINS, Senior Judge:

Plaintiff, Town of North Bonneville (Town), filed its petition in the United States Court of Claims on October 20,1980, to claim damages for breach of contractual arrangements alleged to have been made during the course of relocation of the Town that was necessitated by construction of a second powerhouse at Bonneville Dam.1 Plaintiffs petition alleged six breaches of contract and claimed damages of $14,550,-000. Defendant filed an answer on March 12, 1981, a first amended answer on April 8, 1981, and a counterclaim on November 19, 1982. Defendant’s counterclaim included a comprehensive restatement of facts; it listed four causes of action and claims that totaled $13,400,000. The case was transferred to the United States Claims Court on October 1, 1982, pursuant to section 403(d) of the Federal Courts Improvement Act of 1982.2

Some of the liability issues were decided in plaintiff’s favor on cross-motions for summary judgment in a Memorandum of Decision, filed May 11, 1984.3 At that time, it was determined that a Memorandum of Agreement dated May 23,1975, and a Contract for Relocation, dated August 19, 1975, were included in the class of contracts subject to the jurisdiction conferred on this court in 28 U.S.C. § 1491(a)(1) (1982). It also was determined that defendant’s repudiation, by October 13, 1976, of the provisions of those agreements relative to conveyance of certain parcels of land for the optimum town on the ground that the Town lacked authority to so contract, was without arguable foundation after a December 18, 1980, decision of the Supreme Court of Washington, and a February 17, 1981, decision by the Ninth Circuit adverse to defendant.4 After the January 1, 1984, termination date for the United States to retain an interest in real property acquired for the new town site, the refusal of the Corps to convey was found to be a breach of the Relocation Contract. Damages, if any, for such breach were left for subsequent proceedings.

After the May 11, 1984, ruling on cross-motions for summary judgment, numerous liability issues remained on plaintiff’s claims, and defendant’s counterclaim raised significantly different liability issues. Further, the parties’ concepts of the principles appropriate in this case for allocation of damages differed widely. Pretrial preparation, because of the parties inability to agree as to the basic factual structure of the relocation commitments, was difficult, and for the most part was unsatisfactory as a procedure to isolate and clarify disputed contentions of fact and law. Each party procured the services of a number of expert consultants and obtained reports that focused preselected facts on the topic [696]*696or subject assigned for investigation. In pretrial, counsel were able to stipulate as to only 11 facts. Plaintiff, on 35 pages, identified more than 330 separate factual issues to be tried; defendant, on 36 pages, identified more than 200 separate factual issues to be tried.

During the period June 4 through June 28, 1985, 19 days of trial were held. Plaintiff’s remaining liability issues and all of its damages issues were heard first. Liability issues and damages issues on defendant’s counterclaim were heard following plaintiff’s presentation. During the trial counsel were able to enlarge the stipulation to 98 facts.5

In posttrial briefing, plaintiff requested 178 findings of fact, on 71 pages; defendant requested 328 findings of fact, on 54 pages, and both parties substantially restated their claims. Plaintiff now seeks damages for five categories of claims in total amount of $28,436,238.32. Under its counterclaim, defendant now seeks damages in five categories of claims that total $4,874,639.45.

The legal issues in this case arise in an unusual context. Although the claims essentially are for breach of contract, the contracting parties are governmental organizations and the Town’s relocation is collateral to the United States’ assertion of the sovereign power of eminent domain under the Bonneville Project Act.6 Special legislation was obtained to supplement the authority of the Corps of Engineers to assist relocation of the Town in connection with construction of a second powerhouse at Bonneville Dam.7 This special legislation (referred to as Section 83 or the McCormack legislation) specifically authorized the Secretary of the Army to relocate the Town of North Bonneville, Washington, to a new town site. As part of such relocation, the Secretary of the Army, acting through the Chief of Engineers, was authorized to cooperate in the planning of a new town with Federal and non-Federal interests, to acquire land necessary for the new town, and to convey title to that land to individuals, businesses, and other entities, including the Town. The special legislation authorized relocation of municipal facilities that were additional to, or constructed to higher standards than, those permitted under the substitute facilities rule applicable to eminent domain proceedings, provided appropriate non-Federal interests furnished binding contractual commitments to cover the additional costs.

The breach of contract issues also are exceptional because of the negotiating stance available to representatives of the parties because of their governmental interests. This public body relationship resulted in procedures atypical in government contracts, and produced a series of written instruments that embodied a sequence of understandings that were dependant upon prior actions. Changes due to future developments were implicit, agreements were expected to be amended and further agreements were expected to be reached at a later date.

FACTS

Background information on the parties and the relocation project is provided in the May 11, 1984, Memorandum of Decision on the cross-motions for summary judgment.8 The findings of fact set forth separately in [697]*697a subsequent section of this opinion include in Part I a chronology in detail of the facts involved in the parties’ dealings to August 24, 1976, during the planning and design stages of relocation. Part II of the findings includes selected facts applicable to damages claims during the construction phase. Except as appropriate for continuity, information in the findings of fact is not repeated in other sections of this opinion.

Bonneville Dam, on the Columbia River, was completed in 1943. The northern half of the spillway is located in the State of Washington; the southern half of the spillway, the first powerhouse, and other facilities, are located on the Oregon side of the river. The Town of North Bonneville developed with the construction of the Bonneville Dam, and until 1975 its center was located adjacent to the dam on the Washington side of the river.

The Corps of Engineers constructed Bonneville Dam, and operates and maintains its facilities. In 1965, the Bonneville Power Administration, which markets electrical power generated by the dam, requested the Corps of Engineers to construct a second powerhouse. The site ultimately selected was on the Washington side.

In this case, defendant acted through the Corps’ Portland District office, supervised by the District Engineer, who also acted in the capacity of contracting officer for the second powerhouse project.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
11 Cl. Ct. 694, 1987 U.S. Claims LEXIS 34, Counsel Stack Legal Research, https://law.counselstack.com/opinion/town-of-north-bonneville-v-united-states-cc-1987.