L.W. Matteson, Inc. v. United States

61 Fed. Cl. 296, 2004 U.S. Claims LEXIS 175, 2004 WL 1662264
CourtUnited States Court of Federal Claims
DecidedJuly 20, 2004
DocketNo. 01-542C
StatusPublished
Cited by13 cases

This text of 61 Fed. Cl. 296 (L.W. Matteson, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
L.W. Matteson, Inc. v. United States, 61 Fed. Cl. 296, 2004 U.S. Claims LEXIS 175, 2004 WL 1662264 (uscfc 2004).

Opinion

OPINION AND ORDER

BLOCK, Judge.

I. Introduction

This case involves a breach of a fixed-price dredging contract that required the dredging, transporting, and depositing of material from two stockpile areas located near Alma, Wisconsin. Before this court is the government’s motion for summary judgment pursuant to Rule 56 of the Rules of the Court of Federal Claims (“RCFC”).

The two parties to the contract are plaintiff, L.W. Matteson, Inc. (“Matteson”), an experienced government contractor and established hydraulic dredging company, and the U.S. Army Corps of Engineers (“the Corps”). The contract required Matteson to deposit fill material in two separate areas, one of which was specified and, thus, mandatory. After filling the mandatory site, the contract provided that Matteson could transport the remaining fill material either to one of the Corps’ previously-selected areas or to private property that Matteson selected. Before Matteson could use the private site, however, the Corps needed to approve the site and the requisite permits needed to be [300]*300obtained. The contract also required the Corps to perform an environmental assessment if Matteson chose private property as a filling site.

In essence, the overarching issue in this case is one of contract interpretation, which requires the court to determine which of the parties bore the burdens and consequent risks of obtaining and complying with permitting requirements. While both sides agree the contract contains clauses that obligate the contractor to comply with all federal, state, and local laws (including, of course, regulatory requirements), Matteson contends the contract also contains other provisions that conflict with and supersede these clauses. These other provisions, Matteson asserts, resulted in the obligation of the Corps to inform Matteson not only of the existence of the Wabasha County Shoreline Protection Act (“SPA”), but also the vociferous local opposition in the County to any dredging. Matteson argues that the Corps’ failure to fulfill these obligations caused Matteson to lose a considerable amount of money while performing the contract because it could not use its proposed site on private property for disposing dredged material.

Before this court are Matteson’s multiple claims for relief based on various theories. Their resolutions, however, are all linked to the singular issue of which party under the contract bore the burden of compliance. As the court fully explains below, because the contract is unambiguous in this regard and the burden of compliance clearly fell on Matteson, the court grants summary judgment in favor of the government.

II. Background

The facts of this case derive from the parties’ pleadings and proposed findings of uncontroverted facts (“PFUF”).

A. The Grand Encampment Excavation Solicitation.

On July 10, 1996, the Corps issued an invitation for bids for a fixed-price contract to perform the following work:

[furnish] all plant, labor, material, and equipment necessary to excavate and transport existing dredged material from two stockpile/borrow areas: (1) the Alma Marina in Alma, Wisconsin; and (2) an island in the Mississippi River located upstream from Alma, Wisconsin. Such removed existing dredged material is to be disposed of in various potential on-land placement sites located in Buffalo County [Wisconsin].

Pl.’s First Am. Compl. ¶ 1; Def.’s PFUF ¶ 7 (citing Def.’s App. at 15).

The Corps referred to this project as the “Grand Encampment Excavation,” (“GEE”) and incorporated various Federal Acquisition Regulation (“FAR”) sections into the solicitation.1 The solicitation also identified sections tailored to the GEE project that addressed topics such as available lands for the contractor’s use, contractor-selected disposal areas, construction restrictions and compliance with federal, state, and local environmental protection laws and regulations. Def.’s PFUF ¶ 3 (citing Def.’s App. at 148-51, 166).

The solicitation required the contractor to dispose dredged material in the “Buffalo County No. 1 Placement Site.” Def.’s App. at 151-52. After filling the mandatory site, however, the contractor could, if necessary, make use of any one of five other sites the Corps previously selected, or any of the contractor’s own selected disposal areas. Id. at 149. The solicitation stated plainly, however, that any contractor-selected disposal areas would be subject to the Contracting Officer’s approval and may require an environmental assessment. Id.

The following provisions give rise to the controversy in this case. One provision required potential contractors to submit an Environmental Protection Plan (“EPP”) that outlined the particular contractor’s method for reducing pollution, protecting natural resources while performing contracted work, and “[procedures to be implemented to pro[301]*301vide the required environmental protection and to comply with the applicable laws and regulations.” Id. at 165. Another held contractors responsible for their subcontractors’ compliance with the overall EPP, as well as federal, state, and local environmental laws and regulations. Id. at 166.

Yet another provision expressly placed contractors on notice that they could not rely on the Corps to advise them of any noncompliance with local environmental regulations.2 Another important provision of the solicitation explicitly warned all contractors that, “[n]ot withstanding [sic] the requirements of this section and not withstanding [sic] approval by the Contracting Officer of the Contractor’s Environmental Protection Plan, nothing herein shall be construed as relieving the Contractor of all applicable Federal, State, and local environmental protection laws and regulations.” Id. Very important to this case, furthermore, is the provision of the solicitation that obligated the contractor, without additional expenses to the government, to obtain all necessary permits and to comply with any federal, state, local laws, codes, and regulations applicable to the performance of the work. Id. at 88.

Finally, and perhaps the critical provision, the “Placement Site Paragraph” of the contract — Paragraph 7.3, Section 01000 — provides that the contractor may dispose of dredged material on private property upon approval by the Corps. The Placement Site Paragraph, furthermore, notified the contractor that choosing an optional final disposal area may require the Corps to prepare an environmental assessment. Id. at 149. This environmental assessment, in turn, may result in additional requirements to offset any environmental impact from the use of the private disposal area. Id.

B. L.W. Matteson, Inc.

L.W. Matteson, Inc. (“Matteson”), an experienced government contractor and established hydraulic dredging company, contacted the Corps during the bid period and inquired as to whether the contract permitted hydraulic dredging. The Corps responded affirmatively to Matteson’s inquiry, and encouraged Matteson to submit a bid incorporating hydraulic dredging. Pl.’s First Am. Compl. at ¶¶ 4-7. While crafting its bid, however, Matteson determined that the Corps’ five proposed disposal sites were incompatible with hydraulic dredging. Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Yee v. United States
Federal Circuit, 2019
Bell/Heery v. United States
106 Fed. Cl. 300 (Federal Claims, 2012)
Federated Mutual Insurance v. Williams Trull Co.
838 F. Supp. 2d 370 (M.D. North Carolina, 2011)
St. Christopher Associates, L.P. v. United States
75 Fed. Cl. 1 (Federal Claims, 2006)
Precision Pine & Timber, Inc. v. United States
75 Fed. Cl. 80 (Federal Claims, 2006)
Rodriguez v. United States
69 Fed. Cl. 487 (Federal Claims, 2006)
Renda Marine, Inc. v. United States
66 Fed. Cl. 639 (Federal Claims, 2005)
Statesman II Apartments, Inc. v. United States
66 Fed. Cl. 608 (Federal Claims, 2005)
Record Steel & Construction, Inc. v. United States
62 Fed. Cl. 508 (Federal Claims, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
61 Fed. Cl. 296, 2004 U.S. Claims LEXIS 175, 2004 WL 1662264, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lw-matteson-inc-v-united-states-uscfc-2004.