Asphalt Roads & Materials Co. v. Commonwealth

512 S.E.2d 804, 257 Va. 452, 1999 Va. LEXIS 49
CourtSupreme Court of Virginia
DecidedFebruary 26, 1999
DocketRecord 980805
StatusPublished
Cited by12 cases

This text of 512 S.E.2d 804 (Asphalt Roads & Materials Co. v. Commonwealth) is published on Counsel Stack Legal Research, covering Supreme Court of Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Asphalt Roads & Materials Co. v. Commonwealth, 512 S.E.2d 804, 257 Va. 452, 1999 Va. LEXIS 49 (Va. 1999).

Opinions

SENIOR JUSTICE WHITING

delivered the opinion of the Court.

[454]*454The dispositive issue in this appeal is whether a provision in a construction contract allows extra compensation to a contractor for certain additional work on a highway project.

In June 1992, Asphalt Roads and Materials Company, Incorporated (Asphalt Roads) contracted with the Virginia Department of Transportation (VDOT), an agency of the Commonwealth, to widen a section of Landstown Road in Virginia Beach. The contract incorporated by reference VDOT’s “January 1991 Road and Bridge Specifications” and any amendatory and supplemental specifications. Section references herein will be to the “1991 Road and Bridge Specifications,” as amended and supplemented.

Asphalt Roads subcontracted with Kevcor Corporation (Kevcor) to install the utility pipes in conformance with the terms of Asphalt Roads’ contract with VDOT. The contract required the contractor to remove and replace any soil that was unsuitable for use as backfill under the utility pipes.1 The contract drawings indicated that there were 940 cubic yards of such soil. However, during excavation, Kevcor discovered that there were many more than 940 cubic yards of unsuitable soil and VDOT’s inspector required that Kevcor remove and replace that extra unsuitable soil with “borrow,” which is defined by § 101.02 as “[sjuitable material from sources outside the roadway.”

Asphalt Roads, on behalf of Kevcor (collectively the contractor), claimed additional compensation for the excess unsuitable material that was discovered, removed, and replaced with borrow. Agreeing that the contractor was entitled to a part of its claim, VDOT paid for the removal of some of the material as an “unforeseen condition” covered by § 104.02.2 VDOT also paid for some of the backfill under § 303.06(d) (quoted later herein). VDOT declined to pay the balance of the claim for a number of reasons, some of which are involved in this appeal.

After exhausting the administrative remedies provided by Code §33.1-386, the contractor sued VDOT in the Circuit Court of the City of Virginia Beach under the provisions of Code § 33.1-387. At [455]*455issue was the contractor’s right of recovery and, if it had such a right, how much borrow had been required and how much unsuitable material had to be removed and disposed of.

The circuit court resolved these factual disputes by holding that the contractor was entitled to payment for an additional 8,657 cubic yards of backfill and 8,807 cubic yards of unsuitable material. The court adopted VDOT’s contention that compensation for the backfill should be awarded at the contract-stated unit price of $6.18 for select borrow and awarded the contractor $53,500.26 on that claim.3 With regard to the disposal of unsuitable material, the court adopted the contractor’s contention that compensation should be in the amount of $11.16 per cubic yard, the unit price stated in the contract for the disposal of similar materials, and awarded the contractor $98,286.12 for that claim.

On VDOT’s appeal, the Court of Appeals reversed the portion of the judgment awarding the additional compensation, affirmed a part of the judgment, and remanded the case for further proceedings on issues not material here. We awarded the contractor an appeal limited to the hereinafter described issues.4

Here, the dispute is whether the Court of Appeals properly denied the contractor’s described claim for extra compensation for excavating, removing, and replacing unsuitable material under and around the utility pipes. Among other things, the contractor contended that §§ 104.03 and 303.06 applied, not only to allow the claim, but also to fix the amount of the contractor’s compensation.5 The Court of Appeals adopted VDOT’s contention that §§ 302.04 and 520.06 were [456]*456the controlling sections and that they did not provide for extra compensation.

For the reasons which follow, we do not think that §§ 302.04 and 520.06 control or conflict with the sections relied upon by the contractor to sustain its claim. As pertinent, §§ 302.04 and 520.06, both entitled “Measurement and Payment,” provide generally that excavating, backfilling, disposing of unsuitable material, and restoring existing surfaces, are included in the contract unit price for pipe. However, neither deals specifically with the problems at hand, as do the sections relied upon by the contractor.

First, we decide whether the contractor is entitled to compensation for the backfill that had to be obtained from offsite sources to replace the unsuitable material. VDOT argues that §§ 302.04 and 520.06 preclude the payment of additional sums for obtaining borrow to replace the excess unsuitable soil removed by the contractor. For the following reason, we find no merit in this contention.

Section 303.06, also entitled “Measurement and Payment,” provides, in subsection (d) that:

Furnishing and placing backfill material, including backfill for undercut, will be included in the price for excavation . . . unless . . . suitable material is not available within the construction limits. . . . When suitable material is not available within the construction limits, the material furnished and placed by the Contractor will be paid for in accordance with Section 109.05.

Section 303.06 is specific in providing that when suitable backfill is not available on the job site, the contractor will be compensated for the backfill provided from off-site sources. Hence, we hold that § 303.06 authorizes additional compensation to the contractor for having provided the additional backfill material. Accordingly, the trial court did not err in allowing additional compensation for that claim.

Next, we consider whether the contractor is entitled to additional compensation for removing and disposing of the excess unsuitable material. The contractor claims that it is entitled to such compensation under § 104.03, the differing site conditions clause. That section provides, in pertinent part, that

[djuring the progress of the work, if subsurface or latent physical conditions are encountered at the site differing materially from those indicated in the contract,

[457]*457then upon notification to VDOT and its determination that the conditions are materially different, “an adjustment, excluding anticipated profit, will be made and the contract modified” to compensate the contractor for the contractor’s increased cost.

The purpose of the differing site conditions clause and similar clauses, described in a number of cases as the “changed conditions clause,” has been stated in several cases. The North Carolina Court of Appeals, for example, has stated that its purpose is “[t]o encourage low, competent bids,” Ray D. Lowder, Inc., v. North Carolina State Highway Comm’n, 217 S.E.2d 682, 696, (N.C. Ct. App.) cert. denied, 218 S.E.2d 467 (N.C. 1975).

Similarly, the Court of Claims stated that the purpose of the clause was:

[T]o take at least some of the gamble on subsurface conditions out of bidding.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bradford T. Cellucci v. Commonwealth of Virginia
Court of Appeals of Virginia, 2023
Fielder's Choice Enterprise, Inc. v. Augusta County
92 Va. Cir. 66 (Augusta County Circuit Court, 2015)
Faulconer Construction Co. v. Branch & Associates, Inc.
85 Va. Cir. 85 (Rockbridge County Circuit Court, 2012)
Condominium Services, Inc. v. FOA
709 S.E.2d 163 (Supreme Court of Virginia, 2011)
Com. v. AMEC CIVIL, LLC
699 S.E.2d 499 (Supreme Court of Virginia, 2010)
Commonwealth of Virginia, etc. v. AMEC Civil, LLC
677 S.E.2d 633 (Court of Appeals of Virginia, 2009)
AMEC Civil, LLC v. Commonwealth of Virginia, etc.
Court of Appeals of Virginia, 2009
Dan Nelson Construction, Inc. v. Nodland & Dickson
2000 ND 61 (North Dakota Supreme Court, 2000)
Asphalt Roads & Materials Co. v. Commonwealth
512 S.E.2d 804 (Supreme Court of Virginia, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
512 S.E.2d 804, 257 Va. 452, 1999 Va. LEXIS 49, Counsel Stack Legal Research, https://law.counselstack.com/opinion/asphalt-roads-materials-co-v-commonwealth-va-1999.