Schutt Construction Co. v. United States

353 F.2d 1018, 173 Ct. Cl. 836, 1965 U.S. Ct. Cl. LEXIS 239
CourtUnited States Court of Claims
DecidedDecember 17, 1965
DocketCong. No. 3-59
StatusPublished
Cited by14 cases

This text of 353 F.2d 1018 (Schutt Construction Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Schutt Construction Co. v. United States, 353 F.2d 1018, 173 Ct. Cl. 836, 1965 U.S. Ct. Cl. LEXIS 239 (cc 1965).

Opinion

Jones, Senior Judge,

delivered the opinion of the court:

The primary issue in this case is whether, under the facts here involved, an excavating contractor is equitably entitled to reimbursement for a 15 percent overrun in the amount of trees and brush cleared under a lump-sum contract.1

On June 1, 1953, the Army Corps of Engineers solicited lump-sum bids for clearing all the trees and brush along a 20-mile stretch of the Cumberland River near Nashville, Tennessee. The bid specifications stated that there were approximately 10,480 acres involved, but that only approximately 2,828 acres were actually wooded; the rest being farm land. The specifications further stated that the approximations had been taken from aerial photographs, and the contractor would be required to clear all the trees and brush encountered, whether greater than 2,828 acres or not.

Since the 30-day period allowed for bidding admittedly was not sufficient to permit intelligent on-site estimates of the wooded acreage involved, bidders had no choice but to rely on the “2,828-acre estimate” furnished by the Corps of Engineers. The Army had derived its estimate from photographs rather than an actual survey because of the costs involved. As a result the estimate turned out to be off by 1,095 wooded acres — an overrun of 39 percent.

The Schutt Construction Company was the low bidder with a lump-sum bid of $565,946.85. Based on the 2,828-acre estimate this bid was about $200 per wooded acre. Other bids ranged from $642,455 to $972,000. The Govern[839]*839ment estimate, exclusive of profit, was $885,000. Schutt signed the contract on July 16, 1953, and then subcontracted the entire job to Yellow Pine Lumber Company for $509,352. Yellow Pine had been second lowest bidder on the original Government contract at $642,455 and so accepted this subcontract at a price $133,103 less than its original cost estimate.

Yellow Pine commenced clearing operations in August 1953. The contract called for clearing the area below elevation 420 within 130 days and the entire area within 300 days. The subcontractor elected to clear the entire area in one operation rather than first clearing the entire project at the lower elevation and then returning to the higher elevation. This resulted in a delayed completion at the lower level and an assessment of liquidated damages at $50 per day.

On December 27, 1953, the Yellow Pine partnership was succeeded as subcontractor by the Tri-States Construction Company. The managerial personnel remained the same, however, and clearing work continued uninterrupted. TriStates completed the project on July 3, 1954 — 26 days late. Liquidated damages were assessed in the amount of $9,900 for both the over-all delay and the delay in completing clearing of the lower level. The performance of the subcontractor was satisfactory.

During the clearing operations both the subcontractor and the Government inspector concluded that there were substantially more than 2,828 wooded acres. After completion, the subcontractor surveyed the area and determined that there actually had been 3,923 wooded acres cleared. This was an overrun of 1,095 acres — 39 percent. Tri-States (the subcontractor) then filed a claim with the contracting officer via Schutt (the prime contractor) for $200 per acre on the .extra 1,095 acres cleared. Return of the liquidated damages was also sought.

The contracting officer disallowed the entire claim on the ground that the overrun did not constitute a “changed condition” under Article 4 of the contract. This article calls for an adjustment in the price if the conditions actually encountered differ materially from those ordinarily found under such a contract.

[840]*840The decision of the contracting officer was appealed to the Corps of Engineers Claims and Appeals Board. The appeal was at first denied but on rehearing the Board reversed its previous decision and ruled that a “changed condition” did exist. However, the Board did not find that the plaintiff was entitled to recover costs for the entire 1,095-acre overrun. It concluded that the use of “approximate” in the bid specifications to modify “2,828 acres” obligated the plaintiff to clear a 15 percent overrun under the lump-sum price. Any overrun exceeding 15 percent was considered a material change and recovery was allowed. This amounted to $134,200 — $200 per acre on 671 acres. The subcontractor is presently seeking recovery on the remaining 15 percent — • 424 acres.

Since the plaintiff had not shown that any of the 1,095-acre overrun was encountered below elevation 420, the Board only allowed an extension of time for completion of the overall project. This resulted in a remission of $1,200 of the liquidated damages. The $8,700 assessed for the delay in clearing below level 420 was not returned to the plaintiff. The Board also denied recovery of the survey expenses.

Schutt was paid a total of $135,400 as a result of the Board’s decision. Five percent of this sum was retained by Schutt and the remainder, except for attorneys’ fees, was divided between the subcontractor (Tri-States) and the bonding company. Upon receipt of its share, Tri-States executed a general release of Schutt from any further liability on the contract. The release was dated March 12,1958.

On February 2, 1959, a bill was introduced in the House of Representatives for payment to Schutt, “for itself and on behalf of its subcontractors,” the sum of $142,694.64. This consists of payment of $200 per acre for the 15 percent overrun, survey costs, attorneys’ fees, other miscellaneous expenses and return of the liquidated damages. On June 23, 1959, the bill was referred to this court for a determination of whether there is any legal or equitable ground upon which to base this claim.

Counsel for the appellant admitted during oral argument that his theory of recovery rests solely in equity. . The general release given Schutt by Tri-States after the recovery [841]*841from the Appeals Board relieved the prime contractor from any further liability. And since the prime contractor has suffered no damages itself, and is no longer liable to the subcontractor for its losses, there is no legal ground for a claim against the Government. Privity exists only between the Government and the prime contractor. Severin v. United States, 99 Ct. Cl. 435 (1943), cert. denied, 322 U.S. 733 (1944). Furthermore, there are present no special circumstances such as fraud, duress, or mutual mistake as to the meaning of the release, which would allow the prosecution of the legal claim despite the release. E.g., Winn-Senter Construction Co. v. United States, 110 Ct. Cl. 34, 75 F. Supp. 255 (1948); Nippon Hodō Company, Ltd. v. United States, 142 Ct. Cl. 1, 160 F. Supp. 501 (1958).

The sole question presented then is whether, under the broad equity jurisdiction granted this court in congressional reference cases, the Government should in good conscience reimburse the subcontractor for any or all of its losses. Burkhardt v. United States, 113 Ct. Cl. 658, 84 F. Supp. 553 (1949). In this context we do not feel that the release between the subcontractor and the prime contractor, standing by itself, should work as a total bar to any possible recovery.2

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Statesman II Apartments, Inc. v. United States
71 Fed. Cl. 662 (Federal Claims, 2006)
Asphalt Roads & Materials Co. v. Commonwealth
512 S.E.2d 804 (Supreme Court of Virginia, 1999)
Kanehl v. United States
41 Cont. Cas. Fed. 77,160 (Federal Claims, 1997)
H.B. Mac, Inc. v. United States
41 Cont. Cas. Fed. 77,028 (Federal Claims, 1996)
Paul v. United States
20 Cl. Ct. 236 (Court of Claims, 1990)
McGrew Bros. Sawmill
27 Cont. Cas. Fed. 80,577 (Court of Claims, 1980)
Timber Investors, Inc. v. United States
587 F.2d 472 (Court of Claims, 1978)
Eriez Magnetics Corp. v. United States
209 Ct. Cl. 673 (Court of Claims, 1976)
Perini Corporation v. United States
381 F.2d 403 (Court of Claims, 1967)
Perini Corp. v. United States
381 F.2d 403 (Court of Claims, 1967)
Aurex Corp. v. United States
175 Ct. Cl. 1 (Court of Claims, 1966)

Cite This Page — Counsel Stack

Bluebook (online)
353 F.2d 1018, 173 Ct. Cl. 836, 1965 U.S. Ct. Cl. LEXIS 239, Counsel Stack Legal Research, https://law.counselstack.com/opinion/schutt-construction-co-v-united-states-cc-1965.