Joseph Meltzer, Inc. of New Jersery v. United States

77 F. Supp. 1018, 111 Ct. Cl. 389, 1948 U.S. Ct. Cl. LEXIS 55
CourtUnited States Court of Claims
DecidedJune 1, 1948
Docket43489
StatusPublished
Cited by8 cases

This text of 77 F. Supp. 1018 (Joseph Meltzer, Inc. of New Jersery v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Joseph Meltzer, Inc. of New Jersery v. United States, 77 F. Supp. 1018, 111 Ct. Cl. 389, 1948 U.S. Ct. Cl. LEXIS 55 (cc 1948).

Opinion

MADDEN, Judge.

The plaintiff made a contract on December 1, 1933, to construct for the Government Lock 21 in the Mississippi River, near Quincy, Illinois. The plaintiff sues under the general jurisdiction of the court, and, as to certain of its claims relating to labor, under the Act of July 23, 1937, 50 Stat. 533.

The first item of the plaintiff’s claims relates to the collapse of its cofferdam, which entailed great additional costs and delay. As to this claim the plaintiff’s po *1019 sition is that it encountered a subsurface and latent condition which materially differed from what was expected from the drawings and specifications and which, therefore, entitled the plaintiff to an equitable adjustment of the contract price to cover its increased costs. Article 4 of the contract, quoted in finding 9, is the basis of this claim. The plaintiff also asserts that the Government, in the drawings and writings presented to it before it made its bid, misrepresented material conditions of which the Government was aware, and thus breached its contract.

The facts with regard to the claim for the collapse of the cofferdam are, briefly, as follows: The Government, when it invited bids, gave to prospective bidders copies of the proposed contract, specifications, drawings, and other papers. A sheet marked 10/3 showing what was found by borings in the area of the work was distributed. Section 2-01 of the specifications said: “Character of Materials. — The borings indicated on Sheet 10/3 represent the character of the required excavation. It is believed that they represent the average conditions that will be encountered, and they are considered adequate to serve as a basis for planning the work and estimating the unit cost of performing the work.”

The original 10/3 drawing was withdrawn and a revised drawing with the same number was substituted for it on October 24, 1933. The only change was that, as to several of the borings, the notation which had been “quicksand” on the original was changed to “fine sand”. On November 14, 1933, another drawing, 10/3 A, was sent the plaintiff and other prospective bidders, showing additional data just obtained. Sheet 10/3A showed 25 borings, and as to only two of them did it show that conglomerate had been encountered. Conglomerate is a rocky substance consisting of cemented or conglomerated sand or gravel, not as hard, however, as rock. Its importance in this case is that the plaintiff says its unforeseen presence, under the cofferdam, was the cause of the collapse and the damage.

The plaintiff says that Drawing 10/3A misled it by causing it to think that the river bed in the area consisted, to such depth as was relevant, of sand, gravel and clay, since only 2 out of 25 borings showed rocky substance. It says it was further misled by the fact that it was given a document entitled “Investigation Report” which said — “Excavations and borings: Engineers have results of boring tests showing that practically all of the work will rest on sand and there is very little rock.” and by the fact that the specifications called for an Ohio River box type cofferdam, although saying that another type of cofferdam might be used if the approval of the Contracting Officer was obtained.

The significance of the specification of the box type cofferdam is that all the experts seem to agree that it is not a safe type of structure to use unless it rests on a yielding substance such as sand, gravel, or clay. It is a wooden crib which is placed on the river bottom and filled with sand or gravel and banked at the sides with the same material. If there is any tendency to wash out underneath it, the yielding material on which its rests caves down and fills the incipient cavity. But if a structure like this rests on or closely above a ledge of conglomerate, with sand under it, the tendency of the high standing water outside the cofferdam to seek its level inside the pumped out area surrounded by the dam, may wet or quicken the sand under the rocky ledge and start a “piping” which will carry away a great quantity of the sand and leave a cavity under the ledge. When this cavity extends under' a considerable length of the dam, the weight of the loaded dam will break through the layer of rock and a collapse of the dam will take place.

The box type cofferdam was built, and the water pumped out of the area surrounded by it. The plaintiff, in plain sight of the Government’s engineers and pursuant to a plan which had been submitted to and at least tacitly approved by them, dug ditches inside the working area to conduct the water which would inevitably seep in, to several pumps from which it would be *1020 pumped over the dam into the river, and the working area be thus kept dry.

The cofferdam had been unwatered by March IS, 1934. On April 20 a “boil” was seen in the bottom of one of the drainage ditches. A “boil” is an eruption of water like a spring, showing that water is coming, underground, from a higher level and finding an outlet at the surface of the ground. This boil was stopped by placing a large quantity of crushed stone on it. However, on April 24, another “boil” appeared, again in the bottom of a drainage ditch and within a few minutes a long section of the cofferdam collapsed and the water rushed in, scouring the river bed to a considerable depth under the place where the cofferdam had rested.

The plaintiff says the cofferdam failed because it rested on conglomerate, and a process of undermining such as is described above took place. The Government says the washout occurred because the plaintiff dug its drainage ditches too deep, thus cutting through the conglomerate which existed at the location of the ditches but which, it says, has not been proved to have underlain the cofferdam.

After the washout it was, of course, impossible to prove what had been under the cofferdam at the place of the washout. As we have said, the river bed was scoured to considerable depth, washing out everything that had been there. We think it is fairly evident that there was a rocky ledge under the cofferdam, and that the plaintiff’s explanation of why the collapse occurred is correct. If, as the Government urges, there was not conglomerate under the cofferdam though it was present thirty feet inside it where the plaintiff’s drainage ditch was dug, we do not see how such an extensive undermining of the cofferdam could have occurred. And the Govenment’s contention that the plaintiff brought on its trouble bjr digging its drainage ditches through the layer of conglomerate inside the cofferdam seems to us to assume that, though the ledge of conglomerate did not extend under the cofferdam, it began within a few feet inside the cofferdam and was so extensive and impervious that it alone held out the whole head of water of the river until it was punctured by the plaintiff’s drainage ditch. If this were a plausible hypothesis, which we think it. is not, it would mean that the trouble would, in any event, have come a little later when the-plaintiff excavated to place the walls of the-new lock, since some of this excavation would have had to penetrate the conglomerate.

We think that a subsurface condition was encountered which, as all of the-conduct of both the plaintiff and the Government’s engineers shows, was not foreseen by them when they made their contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
77 F. Supp. 1018, 111 Ct. Cl. 389, 1948 U.S. Ct. Cl. LEXIS 55, Counsel Stack Legal Research, https://law.counselstack.com/opinion/joseph-meltzer-inc-of-new-jersery-v-united-states-cc-1948.