James Julian, Inc., a Corporation v. The President and Commissioners of the Town of Elkton, a Municipal Corporation

341 F.2d 205, 1965 U.S. App. LEXIS 6975
CourtCourt of Appeals for the Fourth Circuit
DecidedJanuary 5, 1965
Docket9622_1
StatusPublished
Cited by3 cases

This text of 341 F.2d 205 (James Julian, Inc., a Corporation v. The President and Commissioners of the Town of Elkton, a Municipal Corporation) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
James Julian, Inc., a Corporation v. The President and Commissioners of the Town of Elkton, a Municipal Corporation, 341 F.2d 205, 1965 U.S. App. LEXIS 6975 (4th Cir. 1965).

Opinion

J. SPENCER BELL, Circuit Judge:

The plaintiff corporation, a contractor, brought this suit against the Town of Elkton, Maryland, to recover among other items the agreed costs for certain “extras” performed by it in the process of laying a sewer line for the town. Only the compensation sought for the alleged “extra work,” however, is involved in this appeal.

The plaintiff claimed under a provision of the contract which committed the defendant to payments in addition to the contract price if the “contractor encountered] * * * subsurface * * * conditions * * * or unknown conditions of an unusual nature differing materially from those ordinarily encoun *206 tered * * * in work of the character provided for in the drawings and specifications * * 1 The town’s primary defense was that the conditions were not unusual. In the alternative, the town contended that even if they were unusual, the contractor was negligent in failing to conduct a proper pre-bid inspection of the site. In this alternative defense, the town relied upon the usual exculpatory clauses contained in public contracts: paragraph 7 required the contractor to visit the site and to examine carefully the size and locality of the work contemplated, paragraph 19 permitted preliminary subsurface exploration at the bidder’s expense, and paragraph 39(d) required the contractor to warrant that he had examined the site and satisfied himself as to the nature and location of the work and the quality and character of the subsurface material likely to be encountered. Other paragraphs exonerated the town for insufficiency or error in the information furnished bidders.

The plaintiff’s general superintendent testified that before submitting its bid, his firm sent a crew consisting of an experienced foreman and three men to the job site to walk the line which the town had laid off for the sewer, to observe anything unusual, and to take test borings at the various manhole sites along the line and at any other places they deemed necessary to determine the subsurface conditions. The plaintiff’s general superintendent and its president testified that their corporation had laid “hundreds of miles” of sewer line under similar conditions and that this was their usual and customary practice. The crew foreman testified that he and his crew spent several days performing their work as directed — they walked the sewer right-of-way and saw nothing unusual, and they took borings near the site of each proposed sewer manhole. Between manholes 2 and 6, the area involved in this controversy, these borings disclosed that at from 5 to 7 feet the solid surface gave way to wet and sandy material in which their hand augers would not operate. This information was reported to company officials who concluded from the cor-ings thus obtained that no unusual geological formations should be anticipated. After taking into consideration the existence of the wet and sandy subsurface material which they concluded would require procedures for draining subsurface water, they prepared and submitted the Julian bid. This bid was the lowest one received, and the plaintiff was awarded the contract.

In the process of constructing the sewer, the line of which roughly paralleled the banks of the Elk River, the plaintiff encountered no difficulty until a point approximately 15 feet upstream from manhole 3 was reached. At this point, where the bottom of the trench was to be between 16 and 20 feet below the surface, it was impossible to insert well points 2 below 5 or 6 feet. Attempts to locate the trouble by excavation along and adjacent to the trench line disclosed what appeared to be parts of an old wharf or pier which had, over a long period of time, been covered over by natural or man-made fill to a depth of 5 or 6 feet. This structure consisted of horizontal planking and heavy supporting timbers which extended from the river bank toward the trench line for a distance of be *207 tween 20 and 30 feet. The structure was connected by one-inch steel rods to a concrete deadman. The deadman was a concrete slab which had a thickness of about 10 inches and was of undisclosed depth. It lay roughly parallel to the trench line on the opposite side from the river. 3 Opposite this deadman, along the bank of the Elk River, the tops of old and rotted pilings were visible. At low tide, some horizontal planking could be seen protruding from the embankment. The court found that anyone who walked the bank of the river should have been put on notice that some sort of bulkhead or pier had at one time existed there but that its direction or width would not necessarily have been apparent. At the point where the horizontal planking was visible, the sewer right-of-way was from 20 to 30 feet from the river bank. The difficulties encountered in the construction of the line covered a distance of approximately 450 feet lying between manholes 3 and 5. The contractor reported his inability to drain the ditch by normal methods to the firm serving as the town’s consulting engineer, and it suggested a process known as sheeting and shoring to correct the difficulty. The Julian representatives at the site, however, insisted that it was not possible to use this method, and they decided instead to excavate and remove the foreign material which was causing the ditch to flood from the river. Since the firm acting as the town’s consulting engineer did not consider the condition unusual and did not contemplate extra payments for correcting it, there was no insistence that its prior suggestion be complied with. Once the obstructions were removed, no further difficulty in laying the sewer line at this point was experienced. It is this removal work for which the plaintiff has claimed the extra compensation.

The trial court found

“that these conditions were ‘unknown conditions of an unusual nature differing materially from those ordinarily encountered and generally recognized as inhering in work of the character provided for’ in the contract, within the language of paragraph 24(d). However the Court further finds that a reasonable pre-bid inspection, both as a matter of common prudence, and under the specific requirements of para *208 graphs 7, 19, 39(d) and 3-23, previously quoted, would have made known the existence of ‘conditions of an unusual nature’.”

The court further declared that

“The Court finds as a fact, and concludes as a matter of law, that Julian was negligent in its examination of the job site and in testing for subsurface conditions; that this negligence was the proximate cause of Julian’s failure to discover the existence of ‘unusual conditions’ between manholes 3 and 5; and that Julian is not entitled to recover for ‘extra work’.”

The substance of the evidence offered by the plaintiff concerning the pre-bid site inspection has already been stated. The only evidence offered by the town on this point came from the testimony of Mr. Bartles, who was employed by the firm serving as the town’s consulting engineer for this job, and Mr. Crothers, the town’s resident engineer. The thrust of Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Horace Case v. Arthur E. Morrisette
475 F.2d 1300 (D.C. Circuit, 1973)
United States v. Ross Corp.
385 F.2d 564 (Sixth Circuit, 1967)
United States v. Ross Corporation
385 F.2d 564 (Sixth Circuit, 1967)

Cite This Page — Counsel Stack

Bluebook (online)
341 F.2d 205, 1965 U.S. App. LEXIS 6975, Counsel Stack Legal Research, https://law.counselstack.com/opinion/james-julian-inc-a-corporation-v-the-president-and-commissioners-of-the-ca4-1965.