Martin Bros. Contractors v. MILITARY INST.

675 S.E.2d 183, 277 Va. 586, 2009 Va. LEXIS 51
CourtSupreme Court of Virginia
DecidedApril 17, 2009
Docket081403
StatusPublished
Cited by2 cases

This text of 675 S.E.2d 183 (Martin Bros. Contractors v. MILITARY INST.) is published on Counsel Stack Legal Research, covering Supreme Court of Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Martin Bros. Contractors v. MILITARY INST., 675 S.E.2d 183, 277 Va. 586, 2009 Va. LEXIS 51 (Va. 2009).

Opinion

675 S.E.2d 183 (2009)

MARTIN BROS. CONTRACTORS, INC.
v.
VIRGINIA MILITARY INSTITUTE.

Record No. 081403.

Supreme Court of Virginia.

April 17, 2009.

*184 D. Stan Barnhill (Frank K. Friedman; Woods Rogers, on briefs), Roanoke, for appellant.

Kenneth C. Grigg, Senior Asst. Atty. Gen. (Robert F. McDonnell, Atty. Gen.; Maureen Riley Matsen, Deputy Atty. Gen.; Richard Tyler McGrath, Senior Asst. Atty. Gen., on brief), for appellee.

Associated Gen. Contractors of Virginia (Ralph L. Axselle, Jr.; W. Alexander Burnett; William Mullen, on brief), Richmond, amicus curiae in support of appellant.

Present: HASSELL, C.J., KOONTZ, KINSER, LEMONS, GOODWYN, and MILLETTE, JJ., and RUSSELL, Senior Justice.

OPINION BY Senior Justice CHARLES S. RUSSELL.

This appeal requires the Court to decide whether the terms of a public construction contract, purporting to limit a contractor's recovery of damages for construction delay caused by a public body, are rendered void by Code § 2.2-4335.

Facts and Proceedings

The facts pertinent to this appeal are undisputed and the parties agree that the case presents a pure question of law. In April 2004, Martin Bros. Contractors, Inc. (Martin), a licensed contractor, entered into a construction contract with Virginia Military Institute (VMI), a public educational institution organized as a public corporation pursuant to Code § 23-92. The contract provided for the renovation of Crozet Hall, the main dining facility on the VMI campus. Due to changes in the project requested by VMI, completion of the project was delayed by 270 days. The causes of the delay were entirely attributed to VMI and not to Martin or the weather.

Martin claimed $430,242.56 as damages for delay, plus the costs of recovery. VMI admitted that Martin was without fault in causing the delay and paid Martin $99,646.20 of the claimed delay damages. VMI relied upon the terms of the contract in limiting the amount of damages payable and contended that the parties were bound by those terms. Martin admitted that the terms of the contract purported to limit the damages recoverable, but contended that those terms were void and unenforceable as against public policy by virtue of Code § 2.2-4335.

Martin brought this action against VMI seeking recovery of the full amount of its claim. The parties submitted the case to the circuit court on cross-motions for summary judgment. By letter opinion, the court ruled that the contract provisions relied on by VMI were enforceable as liquidated damages provisions expressly permitted by Code § 2.2-4335 and did not have the effect of unfairly insulating VMI entirely from damages for delay. The court entered an order granting VMI's motion for summary judgment, denying *185 Martin's motion and dismissing Martin's complaint. We awarded Martin an appeal.

Analysis

This case turns on the interpretation of Code § 2.2-4335, which provides in pertinent part:

Public construction contract provisions barring damages for unreasonable delays declared void.
A. Any provision contained in any public construction contract that purports to waive, release, or extinguish the rights of a contractor to recover costs or damages for unreasonable delay in performing such contract, either on his behalf or on behalf of his subcontractor if and to the extent the delay is caused by acts or omissions of the public body, its agents or employees and due to causes within their control shall be void and unenforceable as against public policy.
B. Subsection A shall not be construed to render void any provision of a public construction contract that:
....
3. Provides for liquidated damages for delay[.]
....
D. A public body denying a contractor's claim for costs or damages due to the alleged delaying of the contractor in the performance of work under any public construction contract shall be liable to and shall pay such contractor a percentage of all costs incurred by the contractor to investigate, analyze, negotiate, litigate and arbitrate the claim. The percentage paid by the public body shall be equal to the percentage of the contractor's total delay claim for which the public body's denial is determined through litigation or arbitration to have been made in bad faith.

In Blake Construction Co. v. Upper Occoquan Sewage Authority, 266 Va. 564, 587 S.E.2d 711 (2003), we construed and applied the foregoing statute. We held that it "means what it says: `Any provision ... to waive, release, or extinguish the rights of a contractor ... shall be void.'" (Emphasis in original.) Id. at 576, 587 S.E.2d at 717-18. Applying the principle expressio unius est exclusio alterius, we held that any provision in a public contract that purported to limit or restrict a contractor's right to recover delay damages was void as against public policy unless it was specifically enumerated by Code § 2.2-4335(B) or other specific statutory enactment. Id. at 577, 587 S.E.2d at 718. The circuit court decided that Blake was not controlling and that this was a case of first impression. For the reasons stated below, we do not agree.

The contract language on which VMI relies appears in the General Conditions (GC) that form a part of the contract. GC 43(b) provides that the contractor may recover damages for owner-caused delay in the work, provided the delay is "unreasonable." In such an event, the contractor is permitted to submit a change order in accordance with GC 38 adding additional days for completion of the work. GC 38(e)(6) provides:

[T]he following Site direct overhead expenses for the change to the time may be considered ...:
The Site superintendent's prorata salary, temporary Site office trailer expense, and temporary Site utilities including basic telephone service, electricity, heat, water, and sanitary/toilet facilities. All other direct and indirect overhead expenses are considered covered by and included in the Subsection (d) markups above.

GC 38(f)(2) and (3) provide:

(f) Allowable costs for changes in the Work shall not include the following:
....
(2) Home office expenses including payroll costs for the Contractor's officers, executives, administrators, project managers, accountants, counsel, engineers, timekeepers, estimators, clerks, and other similar administrative personnel employed by the Contractor, whether at the Site or in the Contractor's principal or branch office for general administration of the Work. These costs are deemed overhead included in the percentage markups allowable in Subsection (d) above.
*186 (2) Home and field office expenses not itemized in Subsection 38(e)(6) above. Such items include, but are not limited to, expenses of Contractor's home and branch offices, Contractor's capital expenses, interest on Contractor's capital used for the Work, charges for delinquent payments, small tools, incidental job costs, rent, utilities, telephone and office equipment, and other general overhead expenses.

(Emphasis added.)

Martin claimed site delay damages amounting to $225,937.40 and home office delay damages amounting to $204,305.16.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Commonwealth of Virginia, etc. v. AMEC Civil, LLC
677 S.E.2d 633 (Court of Appeals of Virginia, 2009)
AMEC Civil, LLC v. Commonwealth of Virginia, etc.
Court of Appeals of Virginia, 2009

Cite This Page — Counsel Stack

Bluebook (online)
675 S.E.2d 183, 277 Va. 586, 2009 Va. LEXIS 51, Counsel Stack Legal Research, https://law.counselstack.com/opinion/martin-bros-contractors-v-military-inst-va-2009.