Pennsylvania Electric Coil, Ltd v. City of Danville

329 F. App'x 399
CourtCourt of Appeals for the Fourth Circuit
DecidedMay 11, 2009
Docket08-1746
StatusUnpublished

This text of 329 F. App'x 399 (Pennsylvania Electric Coil, Ltd v. City of Danville) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pennsylvania Electric Coil, Ltd v. City of Danville, 329 F. App'x 399 (4th Cir. 2009).

Opinion

*400 Affirmed by unpublished PER CURIAM opinion.

Unpublished opinions are not binding precedent in this circuit.

PER CURIAM:

This appeal arises out of a dispute over the responsibility for costs exceeding the •contract price for work done on three hydroelectric generating units, which supply power to the City of Danville, Virginia (“the City”). Pennsylvania Electric Coil, Ltd. (“PEC”) and the City entered into a contract under which PEC would disassemble, rewind, refurbish, and reassemble the units. PEC incurred extra costs to complete the work, which the City ultimately refused to pay. PEC sought recovery, alleging claims for breach of contract and .quantum meruit. The district court granted summary judgment in favor of the City, and PEC now appeals on its quantum meruit claim. Because the parties have an express, valid contract that prescribes a change order procedure to obtain approval and payment for extra work, PEC’s quantum meruit claim fails under Virginia law. We therefore affirm the judgment of the district court.

I.

In March 2003, the City of Danville issued an Invitation for Bids (“IFB”) on a project to disassemble, rewind, refurbish, and reassemble three hydroelectric units (“Units 1, 2, and 3”), which supply power to the City as part of the Pinnacles Hydro Dam on the Dan River. The City hosted a prebid meeting at the dam in April 2003 and allowed six potential bidders to tour and inspect the facility, ask questions, and seek modifications to the proposed contract. PEG submitted a bid in May 2003 in which it affirmed that it had “visited the site and become familiar with and [was] satisfied as to the general location and site conditions that may affect cost, progress, and performance or furnishing of the Work.” J.A. 282.

The City ultimately awarded the contract to PEC for $882,000 in August 2003. The parties’ fixed-price contract consisted of, among other things, a four-page agreement describing the work to be done, the City’s IFB, and the City of Danville Procurement Code. These documents outlined several constraints on the contract price and the manner in which the parties could agree on any increases to that price. Article 7 of the contract stated:

Notwithstanding any other provision of this contract to the contrary, the total obligation of the City shall not exceed $882,000.00 and no increase shall be made to this amount except by a written amendment executed by officials of the City and [PEC] who are authorized by law to execute agreements.

J.A. 14. In addition, article 8.e of the contract stated that PEC “shall bear all losses resulting from the amount or character of the work being different, or because the nature of the premises on which the work is done is different from what was expected or on account of the weather, or similar causes.” Id. Further, section 15.1 of the IFB stated:

The City, without invalidating any construction contract, and without notice to any surety, may order changes in the work within the general scope of the contract consisting of additions, deletions, or other revisions, providing the total amount added or eliminated does not exceed twenty-five percent (25%) of the total contract price, or $10,000, whichever is greater. All such changes in the work shall be authorized by change order, and shall be executed under the applicable conditions of the contract documents.

*401 J.A. 206. This 25% cap on price increases is mandated by Virginia state law, Va.Code § 2.2-4309, and is restated in section 30-13 the Danville Procurement Code, J.A. 398.

PEC began working on the project in October 2003. Significantly for purposes of the issue before us, the project required cost adjustments for work beyond the scope of the contract. PEC submitted written requests for and was granted authorization to conduct such work on several occasions at the outset of the project. For example, on October 14, 2003, PEC submitted a written proposal to perform a heat run test on Unit 1, suggesting that “it would be in the best interest of all concerned if a heat run test was performed on one of the units at the City of Danville Pinnacles Hydro Station while it was in service.” J.A. 436. Noting that “[tjhis heat nm test ... was not specified and, if opted for, would be an extra charge,” (emphasis added), the proposal included a suggested testing schedule and stated that the price for such a test would be $17,500. Id. at 436-37. The City approved the heat run test in December 2003 and issued a Purchase Order signed by Gary Via, the City’s Director of Purchasing. Id. at 439-40.

Also, after performing the heat run test and an uprate study required by the parties’ contract, PEC submitted a written proposal in March 2004 recommending additional work and design changes for all three units. J.A. 442-43. The written proposal noted that these changes “will require additional actions outside of the existing work scope; ” laid out PEC’s “pricing to complete the [required] actions;” and “requested] that the contract between Pennsylvania Electric Coil and The City of Danville ... be revised to include the above workscope and associated costs.” Id. (emphasis added). The City ultimately approved two of the recommended changes and issued a Purchase Order signed by Gary Via in June 2004. J.A. 447.

PEC subsequently began working on the disassembly of Unit 1 and determined that certain parts required repairs that the parties had not originally anticipated. In August 2004, PEC submitted a list of prices for these repairs, which totaled $23,065. J.A. 449-50, 52. The City approved these repairs and issued a Purchase Order signed by Gary Via in September 2004. J.A. 454. Work on Unit 1, including the reassembly and alignment, proceeded into early 2005. PEC also began work on Units 2 and 3 in March or April 2005.

This lawsuit primarily arises out of alignment and plumb work related to all three units, as well as additional repair work performed on Units 2 and 3 (together, “the disputed work”). During the course of PEC’s performance, the parties disagreed on whether PEC’s alignment work fell under the scope of the contract. Although the contract called for “shaft alignment” after the units were reassembled, J.A. 236, it also required each unit to “be assembled to the existing alignment and plumb condition,” id. at 233 (emphasis added). PEC discovered that the units were out of alignment at the outset of the project, a circumstance that the contract did not anticipate. 1 The record contains correspondence and documentation of conversations between the parties through the spring of 2005, discussing alignment problems for all three units as well as PEC’s concern that the contract failed to address *402 the fact that units were already out of alignment.

For example, a January 11, 2005 e-mail from Tim Jablonski, a City engineer, noted that PEC and City employees had “discussed the alignment and bearings” and that PEC’s field supervisor had pointed out that “the contract does not have provisions to correct the plumb if [it is] out of tolerance.” J.A. 639.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Erie Railroad v. Tompkins
304 U.S. 64 (Supreme Court, 1938)
Marine Development Corp. v. Rodak
300 S.E.2d 763 (Supreme Court of Virginia, 1983)
Main v. Department of Highways
142 S.E.2d 524 (Supreme Court of Virginia, 1965)
Hendrickson v. Meredith
170 S.E. 602 (Supreme Court of Virginia, 1933)
Royer v. Board of County Supervisors
10 S.E.2d 876 (Supreme Court of Virginia, 1940)

Cite This Page — Counsel Stack

Bluebook (online)
329 F. App'x 399, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pennsylvania-electric-coil-ltd-v-city-of-danville-ca4-2009.