D. R. Hall Construction, Inc. v. Spotsylvania County Board of Supervisors

40 Va. Cir. 260, 1996 Va. Cir. LEXIS 364
CourtSpotsylvania County Circuit Court
DecidedSeptember 3, 1996
DocketCase No. L96-8
StatusPublished
Cited by1 cases

This text of 40 Va. Cir. 260 (D. R. Hall Construction, Inc. v. Spotsylvania County Board of Supervisors) is published on Counsel Stack Legal Research, covering Spotsylvania County Circuit Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
D. R. Hall Construction, Inc. v. Spotsylvania County Board of Supervisors, 40 Va. Cir. 260, 1996 Va. Cir. LEXIS 364 (Va. Super. Ct. 1996).

Opinion

By Judge William H. Ledbetter, Jr.

The issue in this construction contract case is whether the contractor’s claims are barred because they were not submitted to the owner in a timely and proper manner as required by law and the parties’ contract.

Summary of Facts

Because no evidence has been taken at this stage of the litigation, the facts recited here are gleaned from the parties’ pleadings and attachments.

The Board of Supervisors of Spotsylvania County (the County) and D. R. Hall Construction, Inc. (Hall) entered into a contract dated October 14, 1994, for construction of a fire station. In addition to the basic standard form agreement, the contract documents include AIA General Conditions (AIA Document A201, 1987 Edition); a 23-page addendum to the General Conditions; plans and specifications; and various other documents about which there seems to be no dispute.

Work began on the project but was soon hampered, according to Hall, by “errors and omissions” in the plans and specifications and by “the County’s interference with [Hall’s] performance.” The County contends that the delays were caused by Hall’s “failure to follow the contract speci[261]*261fications” and “to properly supervise and coordinate suppliers and subcontractors.”

Despite the delays and other frustrations, Hall alleges that the work was substantially completed by June 23, 1995. The County occupied the building on July 10, 1995.

Then, three days later, according to Hall, the County presented a “bogus” punch list and refused to make final payment until the items on that list were corrected. On July 27, 1995, Hall continues, it submitted a request for payment based on “substantial completion,” but again, the County refused to pay. Attempts to resolve the disputed items were unsuccessful, but the County released all but $53,000.00 of the basic contract price in September of 1995.

Hall contends that it filed a formal claim pursuant to Virginia Code § 15.1-550 on September 15, 1995, and that the Board of Supervisors denied the claim on December 13, 1995.

On February 26, 1996, the County terminated the contract and has refused to pay the balance of the contract price or additional money demanded by Hall.

Status of the Litigation

Hall instituted this action on January 11, 1996. Hall’s motion for leave to file an amended pleading was granted on May 6, 1996. Thereupon, Hall filed a 33-page “Amended Motion for Judgment and Appeal of Disallowance of Claim.” The County filed a plea in bar, demurrer, and motion to crave oyer.

The court heard arguments on the County’s plea and demurrer on August 5, 1996, and took the matter under advisement.

The Contract

The contractual provisions pertinent to the issue before the court are not in dispute.

Claims and disputes are governed by §§ 4.3 and 4.4 of the General Conditions, as modified by the 23-page addendum to the General Conditions. Relevant here, the contract provides that claims made by the contractor “must be made within 21 days after occurrence of the event giving rise to such claim or within 21 days after the [Contractor] first recognizes the condition giving rise to the claim, whichever is later. Claims must be made by written notice.”

[262]*262Further, the provision expressly requires that the contractor submit any claim within the aforesaid time limits “as a condition precedent to the institution of litigation by the contractor with respect to the subject matter of that claim.” Pursuant to § 4.4 of the General Conditions, as modified by the Addendum, the contractor submits claims to the architect whose decision is final and binding but subject to review by the County.

First, Hall contends that this action is not based on “claims” as that term is used in § 4.3 of the contract. Rather, Hall points out, it seeks damages from the County based on the County’s failure to make payments when due, the County’s interference with progress of the work, and the County’s failure to provide adequate plans and specifications.

Generally, “claim,” a broad and comprehensive word, means “to demand as one’s own; to assert; to insist.” Black’s Law Dictionary (4th ed. 1951), p. 313. In common parlance, it simply means “to demand as rightfully belonging to one.” Webster’s New World Dictionary (Rev. 1984), p. 114.

In this case, however, the court need not resort to dictionary definitions. The contract itself defines the word. Under 4.3.1, a claim “is a demand or assertion by the contractor seeking, as a matter of right, adjustment or interpretation of contract terms, payment of money, extension of time, or other relief with respect to the terms of the contract.’'’

It is difficult to imagine a broader or more comprehensive definition of “claim” than the one used by the parties in their contract. Clearly and unambiguously, a “claim” includes any assertion of entitlement to monetary damages resulting from the County’s violation or breach of any provision in the contract or to any other relief with respect to contractual matters.

Therefore, Hall’s argument that the County’s breaches are not “claims” under § 4.3 of the General Conditions and are not affected by the time limits on “claims” in § 4.3.3 is without merit.

Next, Hall contends that the contract provisions regarding .the submittal and resolution of claims and disputes are void because, if literally construed, they impose unconscionable deadlines and leave the final decision on all such matters with the County, one of the parties to the contract.

The court finds that the time limits are not unconscionable. Given the nature of construction, it is reasonable for an owner to protect itself by contractual language against the assertion of claims and demands about which it may know little or nothing until after the project has progressed to other stages or is substantially completed and the owner’s funds have [263]*263been expended. Thus, an owner can insist that the parties agree to a provision in the construction contract requiring the contractor to submit any demand for more money, more time, or any other relief related to problems encountered during the course of construction, to the owner or the owner’s agent on the job, the architect, in a specified timely manner.

The Court also finds that the final resolution of “claims” under the contract is not left to the County. .Although the standard provisions for arbitration of unresolved claims and disputes were eliminated from the General Conditions by agreement and no administrative appeal procedures have been adopted, § 13.1.1 of the contract expressly allows for judicial review of any dispute involving “the performance, nonperformance or alleged breach” of the contract. Furthermore, the County does not contend that its decisions to withhold money from Hall and to refuse to pay additional money demanded by Hall are non-reviewable. In fact, the County implicitly concedes, at least for purposes of this decision, that Hall would have a right to maintain this action if it had submitted these claims during the course of construction in the required manner.

Hall also contends that the contract provisions limiting the time within which claims must be submitted are unenforceable because they are inconsistent with the Virginia Public Procurement Act.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

MCI Constructors v. Spotsylvania County
62 Va. Cir. 375 (Spotsylvania County Circuit Court, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
40 Va. Cir. 260, 1996 Va. Cir. LEXIS 364, Counsel Stack Legal Research, https://law.counselstack.com/opinion/d-r-hall-construction-inc-v-spotsylvania-county-board-of-supervisors-vaccspotsylvani-1996.