Higgins v. Trauger

2003 ND 3
CourtNorth Dakota Supreme Court
DecidedJanuary 17, 2003
Docket20020132
StatusPublished
Cited by4 cases

This text of 2003 ND 3 (Higgins v. Trauger) is published on Counsel Stack Legal Research, covering North Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Higgins v. Trauger, 2003 ND 3 (N.D. 2003).

Opinion

Filed 1/17/03 by Clerk of Supreme Court

IN THE SUPREME COURT

STATE OF NORTH DAKOTA

2003 ND 7

State of North Dakota,

the North Dakota Department

of Transportation, and its

Director David A. Sprynczynatyk, Plaintiffs, Appellants,

        and Petitioners

v.

Gratech Company, Ltd., Defendant, Appellee,

      and Respondent

American Arbitration Association,     Defendant

and

The Honorable Bruce B. Haskell,

Judge of the District Court,

South Central Judicial District   Respondent

No. 20020211

Appeal from the District Court of Burleigh County, South Central Judicial District, the Honorable Bruce B. Haskell, Judge.

TEMPORARY STAY VACATED, APPLICATION FOR SUPERVISORY WRIT DENIED, AND ORDER OF THE DISTRICT COURT AFFIRMED.

Opinion of the Court by Maring, Justice.

Charles S. Miller, Jr., Fleck, Mather & Strutz, P.O. Box 2798, Bismarck, N.D. 58502-2798, for appellants.

Ronald G. Schmidt (argued), Schmidt, Schroyer & Moreno, P.C., P.O. Box 860, Rapid City, S.D. 57709-8007, and Jack McDonald (appeared), Wheeler Wolf, P.O. Box 2056, Bismarck, N.D. 58502-2056, for appellee.

State v. Gratech Co., Ltd.

Maring, Justice.

[¶1] The State of North Dakota, the North Dakota Department of Transportation, and David Sprynczynatyk, Director of the Department of Transportation (collectively “the State”), appealed from a district court order dismissing the State’s action seeking a declaratory judgment that Gratech Company was not entitled to arbitrate its claim against the State and that the arbitrators lacked jurisdiction to arbitrate the claim.  The State also sought a stay pending appeal and a supervisory writ directing the district court to vacate its order and to permanently enjoin the arbitration proceedings.  We granted a temporary stay of the arbitration proceedings while this appeal is pending.  We conclude the arbitrators had jurisdiction to determine whether Gratech had timely filed an administrative claim, and we therefore vacate the temporary stay, deny the application for a supervisory writ, and affirm the order of the district court.

I

[¶2] In 1997, the State awarded a contract to Gratech on a highway construction project.  During construction Gratech encountered difficult soil conditions, and a dispute arose whether certain work was common excavation covered under the contract or was additional, unforeseen work entitling Gratech to extra compensation.  The project was completed on November 23, 1999, and accepted by the State on December 28, 1999.  On June 30, 2000, Gratech’s president wrote to the project engineer requesting that the parties meet to discuss Gratech’s claim that it was owed additional sums for unforeseen work on the project.

[¶3] The State sent a final estimate for the project to Gratech by certified mail on August 15, 2000.  The cover letter enclosed with the final estimate stated final payment would be withheld until Gratech submitted certain haul road releases, pit releases, and “DBE Participation Certificates.”  The State withheld payment of over $83,000 until these documents were provided.  The final estimate did not address payment for the alleged unforeseen work.

[¶4] On April 9, 2001, Gratech’s president wrote to the State advising that all required releases had been provided and requesting a progress payment reducing the retainage to a nominal amount.  Gratech also reiterated its request that the parties meet to discuss Gratech’s claim that it was owed additional sums for unforeseen work on the project.  In response to Gratech’s letter, the State on April 12, 2001, advised Gratech it would process an “intermediate payment” to Gratech reducing the retainage to $5,000.  The State also sent Gratech a supplemental final estimate dated April 17, 2001.  The State claims that, before it sent the supplemental final estimate to Gratech, it orally advised Gratech it would release the additional funds “but that processing the paperwork to pay down the retention would not start any clocks running over again.”  Gratech denies this statement was ever made.

[¶5] On July 13, 2001, Gratech submitted an administrative claim to the State seeking payment for the additional work.  Under N.D.C.C. § 24-02-26.1, before seeking arbitration on a highway construction contract the contractor must submit a written claim for compensation to the State “not later than ninety days after the department has submitted the final estimate to the contractor.”  The State denied Gratech’s claim, determining the claim was untimely because it had not been filed within ninety days of the August 2000 final estimate.

[¶6] On January 25, 2002, Gratech filed an arbitration complaint with the American Arbitration Association seeking payment for the additional work.  The State moved to dismiss the arbitration, arguing the arbitrators lacked jurisdiction because Gratech had failed to comply with the statutory requirements for arbitration by failing to file a timely administrative claim under N.D.C.C. § 24-02-26.1.  Gratech argued that the April 2001 supplemental final estimate was the “final estimate” for purposes of N.D.C.C. § 24-02-26.1, and that its administrative claim was timely filed within ninety days.  The arbitrators found that the April 2001 document was the relevant final estimate and denied the State’s motion to dismiss.

[¶7] The State then brought this action in district court seeking a stay of the arbitration proceedings and a declaratory judgment determining that the arbitrators lacked jurisdiction over Gratech’s claim.  The district court granted a temporary stay.  By written order dated July 31, 2002, the court determined the arbitrators had jurisdiction to determine whether Gratech had timely filed its claim.  Accordingly, the district court vacated the temporary stay and dismissed the declaratory judgment action.

[¶8] The State appealed from the district court order dismissing its action.  The State also sought a stay pending appeal and a supervisory writ directing the district court to vacate its order and to permanently enjoin the arbitration proceedings.  On August 21, 2002, we ordered that the arbitration proceedings be stayed pending further order of this Court.

II

[¶9] The sole question on appeal is whether the arbitrators had the authority to determine whether Gratech had timely submitted its administrative claim and was therefore entitled to demand arbitration.

[¶10] Under N.D.C.C. § 24-02-26, all disputes arising out of a highway construction contract must be submitted to arbitration:

All controversies arising out of any contract for the construction or repair of highways entered into by the director must be submitted to arbitration as provided in this chapter and chapter 32-29.2.  Any person who voluntarily enters into a contract for the construction or repair of highways must be considered as having agreed to arbitration of all controversies arising out of that contract.

Section 24-02-31, N.D.C.C., specifies that “[t]he arbitrators shall determine all controversies between the parties growing out of the contract.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of Harwood v. The City of Reiles Acres
2015 ND 33 (North Dakota Supreme Court, 2015)
In Re Estate of Loomer
2010 ND 93 (North Dakota Supreme Court, 2010)
McKechnie v. Berg
2003 ND 136 (North Dakota Supreme Court, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
2003 ND 3, Counsel Stack Legal Research, https://law.counselstack.com/opinion/higgins-v-trauger-nd-2003.