Murdock & Sons Construction, Inc. v. Goheen General Construction, Inc.

461 F.3d 837, 2006 U.S. App. LEXIS 21056, 2006 WL 2371352
CourtCourt of Appeals for the Seventh Circuit
DecidedAugust 17, 2006
Docket05-3036
StatusPublished
Cited by9 cases

This text of 461 F.3d 837 (Murdock & Sons Construction, Inc. v. Goheen General Construction, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Seventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Murdock & Sons Construction, Inc. v. Goheen General Construction, Inc., 461 F.3d 837, 2006 U.S. App. LEXIS 21056, 2006 WL 2371352 (7th Cir. 2006).

Opinion

KANNE, Circuit Judge.

Murdock & Sons Construction, Inc. (“Murdock”) was the subcontractor in a construction contract. Murdock was to perform all of the masonry work for a maximum security prison for the State of Indiana (the “State”). Unfortunately for Murdock, its union masons did not work nearly as fast as was projected in the original bid, for reasons that were never determined. This resulted in serious delays and cost overruns; however, the State was unwilling to provide Murdock with an extension of time in which to complete the project. Murdock eventually walked off the job and filed the rarely seen constructive acceleration claim against the general contractor and the State, as well as two other claims we need not address. Following a bench trial, the district court ruled against Murdock on all claims (including a counterclaim by the general contractor not at issue here). Murdock appeals, and we affirm.

I. HISTORY

The State, acting through its Department of Administration, decided to build a prison near Terre Haute. Goheen Gener *839 al Construction, Inc. (“Goheen”) contracted with the State to be the general contractor for the construction of Level VI housing for the prison, to be named the Wabash Valley Correctional Institution. The prison was to cost the State $6,970,000. Goheen and the State entered into a “Standard Agreement for Construction Projects” which also contained an index entitled “State of Indiana — General Conditions” (collectively, the “Contract”).

At the State’s suggestion, Murdock submitted a bid to Goheen on the masonry subcontract. Goheen only received three bids, even though it usually would receive between four and eight. Murdock was awarded the subcontract 1 with a fixed-price bid of $1,629,825. The other two bids were around $2,747,000 and $2,475,000, and they did not include rebar. Calvin Murdock (“Mr. Murdock”) was Murdock’s Chairman and CEO. He gave final approval for the bid. The bid was originally calculated by well-qualified and experienced experts in both engineering and construction.

The prison was to be a maximum security facility. Not surprisingly, Level VI housing is very dense with masonry. The plan called for 288 cells, 7 feet by 12 feet, and involved small, short walls. Each wall, arranged in a large honeycomb fashion, consisted of individual cement blocks. The blocks were reinforced with both horizontal and vertical rebar every eight inches. The specifications called for continuous grouting with cement, as opposed to the usual mortar. The specifications also required the extensive placement of embeds, which required a significant number of cuts be made in the blocks. Mur-dock, although experienced, had no previous experience with masonry projects that were reinforced as much as this prison.

Murdock was required to use union masons. It entered into a working agreement with the local union in Terre Haute. The masons would be employees of Mur-dock, and Murdock could not set any minimum level of productivity. Murdock had worked on four construction projects in Terre Haute in the past, although it never dealt directly with the local union. These projects were not as extensive as the prison.

Murdock began work in January 1992 and almost immediately encountered a serious problem. Typically, a mason can lay 200 blocks a day. Because of the difficulty of this particular project, Murdock had estimated that each mason could lay 150 blocks a day. From the beginning, however, Murdock’s masons were only laying 50 blocks a day. Murdock tried to increase productivity. Without going into detail, Murdock reviewed its plans, fired slow workers, provided additional equipment, and modified the construction process. Murdock also hired more masons, increasing its crew to 83, up from the planned 35; when more were hired, productivity increased, but not for very long. Ultimately, Murdock refused to add more manpower because the increased productivity was only temporary. Both Goheen and the State were well aware that construction was progressing slower than planned; they requested, and then demanded, that Murdock pick up the pace to meet the construction deadline.

In August 1992, Murdock formally notified Goheen that it wanted more money and more time. The notice was made pursuant to terms contained in the Contract. Goheen forwarded Murdock’s request to the State. In December, the State denied the request, stating any such request must come directly from Goheen. Almost immediately thereafter, Murdock *840 stopped work and left. The masonry work was not done, and the project was ultimately completed 180 days late.

Murdock filed suit, claiming it was entitled to the extension pursuant to 'the terms of the Contract. Murdock argued the delay was due to either a labor dispute or a cause beyond its control. The district court conducted a bench trial and thereafter ruled in favor of Goheen and the State.

II. ANALYSIS

“It is well established that following a bench trial, we review the district court’s conclusions of law de novo, but will reverse its findings of fact only if they are clearly erroneous.” Petrilli v. Drechsel, 94 F.3d 325, 329 (7th Cir.1996); see Lurie v. Comm’r, 425 F.3d 1021, 1025 (7th Cir.2005) (citation omitted); Levenstein v. Salafsky, 414 F.3d 767, 773 (7th Cir.2005) (citations omitted). We do not reweigh the evidence or determine the credibility of witnesses. Sullivan v. Gilchrist, 87 F.3d 867, 872 (7th Cir.1996) (citation omitted). The district court’s application of legal principles to factual determinations is reviewed only for clear error. Lurie, 425 F.3d at 1025 (citing Pittman v. Comm’r, 100 F.3d 1308, 1312-13 (7th Cir.1996)). “[Cjonstruction of the terms of a contract ordinarily presents an issue of law for the court,” subject to de novo review. Yockey v. Horn, 880 F.2d 945, 949 (7th Cir.1989) (quotations and citation omitted).

Murdock’s claim in diversity is based on constructive acceleration. The parties represent that there is no Indiana case law recognizing or applying a constructive acceleration claim. However, constructive acceleration is recognized in many jurisdictions, and we are of the opinion that such a claim is viable under Indiana law. See, e.g., Stephan v. Rocky Mountain Chocolate Factory, Inc., 129 F.3d 414, 417 (7th Cir.1997) (citations omitted).

Free access — add to your briefcase to read the full text and ask questions with AI