Joel Lehmkuhl Excavating v. Troy, Unpublished Decision (4-29-2005)

2005 Ohio 2019
CourtOhio Court of Appeals
DecidedApril 29, 2005
DocketNo. 2004-CA-31.
StatusUnpublished
Cited by4 cases

This text of 2005 Ohio 2019 (Joel Lehmkuhl Excavating v. Troy, Unpublished Decision (4-29-2005)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Joel Lehmkuhl Excavating v. Troy, Unpublished Decision (4-29-2005), 2005 Ohio 2019 (Ohio Ct. App. 2005).

Opinion

OPINION
{¶ 1} This case arises from a sanitary sewer extension project known as the McKaig Avenue Sanitary Sewer Extension (McKaig project) located within the City of Troy. The project contractor, Lehmkuhl Excavating, Inc., appeals from a judgment rendered against it on its claim for additional compensation. Lehmkuhl contends that the trial court erred in rendering judgment in favor of the City of Troy. Specifically, Lehmkuhl contends that the trial court erred in finding that the City was required to notify it of the existence of ground water on the project site. Lehmkuhl also contends that it is entitled to additional compensation under the terms of the contract.

{¶ 2} We conclude that the trial court did not err in rendering judgment against Lehmkuhl. Accordingly, the judgment of the trial court is affirmed.

I
{¶ 3} Lehmkuhl filed suit against the City alleging causes of action for equitable adjustment, breach of contract, breach of warranty, superior knowledge, negligence and unjust enrichment. Both parties waived jury trial, and the matter proceeded to a bench trial where the following evidence was adduced.

{¶ 4} In the early 1990's, the City sought engineers for the McKaig project. Lockwood, Jones and Beals, Inc. (LJB) submitted a "Statement of Qualifications and Technical Proposal" to the City. One section of the Statement, pertaining to the issue of fees and to the question of whether LJB would perform soil boring tests, contained the following statement: "A local geotechnical consultant who was contacted for this pricing stated that he believed that shallow ground water was present in the construction area but questioned the presence of rock at normal sewer depths."

{¶ 5} The City awarded a contract to LJB to act as the engineer for the project. The contract provided that LJB would prepare "detailed construction drawings, specifications, bidding documents, easement descriptions, and permit applications." The contract specifically excluded LJB from conducting any soil borings.

{¶ 6} LJB then issued the General Specifications and Contract Documents (Specifications) for bidders on the McKaig extension. In paragraph six of the section entitled "Information for Bidders" the Specifications state that bidders "are required to inform themselves fully of the conditions and requirements of the construction project being proposed." Paragraph nine provides that "no soil boring information is available in regards to this project * * * the Contractor may make subsurface investigations on this project." The contract also requires that any requests for changes in work or for compensation for extra work be made in writing. The contract provides that any loss from floods, storms or other natural causes shall be sustained by the contractor. Finally, the contract states that if water is encountered, the contractor is responsible for furnishing suitable pumping equipment.

{¶ 7} A legal advertisement for bids on the project was issued. Following the submission of bids, Lehmkuhl was awarded the project contract because its bid of $529,750.44 was approximately eleven thousand dollars lower than the next lowest bid. Lehmkuhl's bid also indicated that the project would be completed within one hundred and eighty days. This time estimate was much shorter than that of any other bidder.

{¶ 8} Work on the project began on January 14, 1993. According to Lehmkuhl's daily job reports there were many rainy days and days that water had to be pumped from the pipe trenches. There were even days that work was shut down due to rain. In April, the project experienced rain and/or snow. The job reports also indicate that from April 22 until April 29, the company experienced problems with the trench banks, which kept caving in. The job reports for May, June and part of July indicate that the rain continued to be a problem, as did trench cave-ins. The evidence also indicates that a change order was executed by the parties in June. That order added the sum of $3,240 to the contract price.

{¶ 9} Minutes from a meeting attended by Lehmkuhl and the City on June 28 indicate that Lehmkuhl complained that delays had been caused by "poor trench conditions over a large percent of the first half of the job, trouble with pipe joints not fitting correctly, and the rainy weather hampering the trucking of the excavated material." The minutes further indicated that Lehmkuhl still expected to complete the project on time. The minutes also indicate that Lehmkuhl pulled off the job for two weeks; the testimony at trial indicated that this was done in order to work on another project.

{¶ 10} On July 1, 1993, Lehmkuhl wrote a letter to the City requesting an extension of completion time due to being "rained out on numerous days, and unforseen underground conditions." Lehmkuhl indicated that it expected the project to be completed by the end of August.

{¶ 11} The project was substantially completed in August of 1993, and was considered by all parties to be timely completed.

{¶ 12} On November 30, Lehmkuhl sent a letter to the City stating that it had incurred extra costs. The letter went on to state that the company was in the process of figuring the extra costs and that it would provide the costs to the City as a request for an "equitable adjustment." The City replied in a letter setting forth various contract provisions and indicating that those provisions should answer Lehmkuhl's letter regarding extra costs. It appears that this letter was intended to constitute a denial of the request for equitable adjustment.

{¶ 13} Lehmkuhl submitted its Periodic Estimate for Partial Payment No. 6 on December 28, 1993. The document stated that it was a "true and correct" statement of the contract account up to and including that date. The document provided a line for "extra work performed to date." Lehmkuhl only claimed the amount set forth in the first change order as extra work. On December 30, Lehmkuhl prepared a document entitled "Change Order No. 2 Final." This change order, which was signed by the City on January 6, 1994, reduced the contract price by $1,240. Subsequently, Lehmkuhl submitted a request for adjustment seeking an additional payment of $335,361.04. The request was denied by the City, and Lehmkuhl filed suit.

{¶ 14} After a trial, the trial court rendered judgment for the City. The trial court noted that it could not determine whether the delays claimed by Lehmkuhl were caused by ground water, excessive rain, or both. It also noted that "the fact that a geotechnical consultant told LJB that he `believed' shallow ground water was in the area is also not dispositive. As noted earlier, there is no reference to exact tests or expert testimony. It is unclear to the Court if shallow ground water means three feet or fifteen feet deep and it is unclear if this was the cause of the problem or excessive rain." The court found that the City had not made any misrepresentations regarding the conditions of the project site. Finally, the trial court found that the claim for additional compensation had no merit because there was no discrepancy in the contract plans or specifications.

{¶ 15} From the judgment rendered against it, Lehmkuhl appeals.

II
{¶ 16} Lehmkuhl's First Assignment of Error states as follows:

{¶ 17}

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Meyer Tool, Inc. v. Mikrolar, Inc.
2023 Ohio 704 (Ohio Court of Appeals, 2023)
Fpc Financial v. Wood, Unpublished Decision (3-12-2007)
2007 Ohio 1098 (Ohio Court of Appeals, 2007)
Levy v. Thompson, Unpublished Decision (10-6-2006)
2006 Ohio 5312 (Ohio Court of Appeals, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
2005 Ohio 2019, Counsel Stack Legal Research, https://law.counselstack.com/opinion/joel-lehmkuhl-excavating-v-troy-unpublished-decision-4-29-2005-ohioctapp-2005.