Hrh Construction Corporation v. The United States

428 F.2d 1267, 192 Ct. Cl. 912, 1970 U.S. Ct. Cl. LEXIS 160
CourtUnited States Court of Claims
DecidedJuly 15, 1970
Docket77-69
StatusPublished
Cited by21 cases

This text of 428 F.2d 1267 (Hrh Construction Corporation v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hrh Construction Corporation v. The United States, 428 F.2d 1267, 192 Ct. Cl. 912, 1970 U.S. Ct. Cl. LEXIS 160 (cc 1970).

Opinion

ON PLAINTIFF’S MOTION AND DEFENDANT’S CROSS-MOTION FOR SUMMARY JUDGMENT

PER CURIAM.

This case was referred to Trial Commissioner Harry E. Wood with directions to prepare and file his opinion on the issues of plaintiff's motion and defendant’s cross-motion for summary judgment under the order of reference and Rule 166(c). The commissioner has done so in an opinion and report filed on January 12, 1970, wherein such facts as are necessary to the opinion are set forth. Plaintiff filed a request that the court review the commissioner’s report, defendant urged that it be adopted by the court and the case has been submitted to the court on oral argument of counsel and the briefs of the parties. Since the court agrees with the opinion and recommended conclusion of the trial commissioner, as hereinafter set forth, it hereby adopts the same as the basis for its judgment in this case. Therefore, plaintiff is not entitled to recover, plaintiff’s motion for summary judgment is denied, defendant’s cross-motion is granted and plaintiff’s petition is dismissed.

OPINION OF COMMISSIONER

WOOD, Commissioner: This ease, arising out of a 1964 contract for the construction of an “NCO HIGH RISE APARTMENT,” is before the court on cross-motions for summary judgment 1 for review, under Wunderlich Act 2 standards, of a decision by the Armed Services Board of Contract Appeals denying plaintiff’s claim to an equitable adjustment for an asserted change. 3

Plaintiff’s position was that by requiring the painting of certain interior surfaces of the apartment building, defendant constructively changed the contract. After a hearing limited to liability, the Board held that “The contract as awarded did require the disputed painting work, and the direction to perform it was not a change.”

For the reasons appearing below, it is concluded that plaintiff is not entitled to recover.

The facts are not in any dispute. The contract in suit, executed June 30, 1964, called for the construction of a twelve story, 120 unit, “NCO HIGH RISE APARTMENT” at Fort Myer, Virginia, at a fixed price o: $1,841,420.00. The contractor 4 agreed to furnish all la *1269 bor, materials and equipment and to perform the work required in strict accordance with the contract specifications, schedules, and drawings. The painting work was subcontracted to Clifton D. Mayhew, Inc., and plaintiff alleges that it “presents this Petition on behalf of said subcontractor.”

In early 1966, during the latter stages of construction, a dispute arose as to painting requirements under the contract. Plaintiff took the position that the contract did not require the painting of certain surfaces within specified interior areas of the building, viz:

(1) gypsum board walls in corridors and typical floor elevator lobbies;
(2) “Exposed concrete” ceilings in stairwells;
(3) “Exposed concrete” ceiling in the rubbish vestibule;
(4) gypsum board walls, “Exposed concrete masonry unit” walls, and “Exposed concrete” ceilings in non-dwelling areas;
(5) “Exposed concrete masonry unit” walls in the mechanical equipment room and the trash room; and
(6) certain mechanical pipe and equipment.

Defendant, insisting that painting of the disputed surfaces was contractually required, directed such painting, and the work was performed under protest. Claims for compensation for the asserted change were then made, denied by the contracting officer, and unsuccessfully appealed to the Armed Services Board of Contract Appeals.

General Provision No. 2 of the contract provided, inter alia, that anything mentioned in the specifications and not shown on the drawings, or vice versa, “shall be of like effect as if shown or mentioned in both”, and that, in ease of difference between drawings and specifications, the latter should govern. The same provision directed, “In case of discrepancy * * * in the drawings, or in the specifications, * * * ” that the matter promptly be submitted to the contracting officer for a written determination, and warned that any adjustment made without such a determination would be at the contractor’s own risk and expense.

Other relevant contractual provisions are set forth in an Appendix to this opinion. Among them are portions of Part III (“TECHNICAL PROVISIONS”), Section 20 of the specifications, “PAINTING, GENERAL”, containing general procedures for surface cleaning and painting. Section 20-09, “SURFACES TO BE PAINTED”, stated that, “Except as specified under SURFACES NOT TO BE PAINTED, the surfaces listed in the painting schedule below shall receive the surface preparation, paints, and the number of coats prescribed.” Section 20-10, “SURFACES NOT TO BE PAINTED”, contained a single entry: “Prefinished elevator doors and frames.” The painting schedule, which followed Section 20-11 (not here relevant), included entries for both interior and exterior surfaces, tabulated under headings for “Surface”, “Surface preparation and pretreatment”, “1st Coat”, “2d Coat”, and “3d Coat”.

The controversy at bar, involving certain interior surfaces only, stems from Sheet 2 of the contract drawings. Sheet 2 contained, inter alia, a tabulated Finish Schedule listing ten space names (designated by “mark” numbers), each with entries under five headings: “Floor”, “Base”, “Wall”, “Cealing”, and “Remarks”. Under the columns entitled “Wall” and “Ceiling”, and opposite five of the ten “space names”, the word “paint” (or “painted”, or “ditto” beneath such words) appeared and these surfaces manifestly had to be painted. Opposite the remaining five “space names”, however, the word “paint” (or “painted” or “ditto”) was omitted from the “Wall” or the “Ceiling” entry, or *1270 from both. Plaintiff’s claim is bottomed on the omission.

Plaintiff advances two principal lines of argument, which are here stated in reverse order. One is that General Provision No. 2 has no relevance, because there was no “difference” between the specifications and the Finish Schedule; that the precedence contractually accorded the specifications over the Finish Schedule in case of conflict is thus of no moment; and that it was under no duty to submit the matter to the contracting officer for determination, such action being a requisite only “In case of discrepancy”.

The other line of argument, closely related, is that plaintiff logically concluded, from the specifications, that some surfaces were not to be painted; that to determine where those surfaces not to be painted were located, resort to the Finish Schedule was necessary and reasonable; that plaintiff’s conclusion, from the specifications and Finish Schedule, that the areas in dispute did not require painting, was reasonable; and that, under familiar doctrine, 5

Free access — add to your briefcase to read the full text and ask questions with AI

Related

ECC International LLC
Armed Services Board of Contract Appeals, 2021
Navcom Defense Electronics, Inc. v. England
53 F. App'x 897 (Federal Circuit, 2002)
Fry Communications, Inc. v. United States
22 Cl. Ct. 497 (Court of Claims, 1991)
D'ANNUNZIO BROTH. v. Transit Corp.
586 A.2d 301 (New Jersey Superior Court App Division, 1991)
T.F. Powers Construction Company v. The United States
918 F.2d 187 (Federal Circuit, 1990)
Brutoco Engineering & Construction, Inc. v. United States
34 Cont. Cas. Fed. 75,249 (Court of Claims, 1987)
Tibshraeny Bros. Construction, Inc. v. United States
32 Cont. Cas. Fed. 73,017 (Court of Claims, 1984)
Enrico Roman, Inc. v. United States
30 Cont. Cas. Fed. 70,907 (Court of Claims, 1983)
Newsom v. United States
676 F.2d 647 (Court of Claims, 1982)
Bromley Contracting Co. v. United States
652 F.2d 70 (Court of Claims, 1981)
Wickham Contracting Co. v. United States
546 F.2d 395 (Court of Claims, 1976)
James A. Mann, Inc. v. United States
535 F.2d 51 (Court of Claims, 1976)
United Pacific Insurance v. United States
497 F.2d 1402 (Court of Claims, 1974)
Blake Construction Co. v. United States
202 Ct. Cl. 794 (Court of Claims, 1973)
Merando, Inc. v. United States
475 F.2d 598 (Court of Claims, 1973)
Chris Berg, Inc. v. United States
455 F.2d 1037 (Court of Claims, 1972)

Cite This Page — Counsel Stack

Bluebook (online)
428 F.2d 1267, 192 Ct. Cl. 912, 1970 U.S. Ct. Cl. LEXIS 160, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hrh-construction-corporation-v-the-united-states-cc-1970.