T.F. Powers Construction Company v. The United States

918 F.2d 187, 1990 U.S. App. LEXIS 18065, 1990 WL 153817
CourtCourt of Appeals for the Federal Circuit
DecidedOctober 15, 1990
Docket90-1144
StatusUnpublished

This text of 918 F.2d 187 (T.F. Powers Construction Company v. The United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
T.F. Powers Construction Company v. The United States, 918 F.2d 187, 1990 U.S. App. LEXIS 18065, 1990 WL 153817 (Fed. Cir. 1990).

Opinion

918 F.2d 187

37 Cont.Cas.Fed. (CCH) 76,025

Unpublished Disposition
NOTICE: Federal Circuit Local Rule 47.8(b) states that opinions and orders which are designated as not citable as precedent shall not be employed or cited as precedent. This does not preclude assertion of issues of claim preclusion, issue preclusion, judicial estoppel, law of the case or the like based on a decision of the Court rendered in a nonprecedential opinion or order.
T.F. POWERS CONSTRUCTION COMPANY, Appellant,
v.
The UNITED STATES, Appellee.

No. 90-1144.

United States Court of Appeals, Federal Circuit.

Oct. 15, 1990.

Before NIES, Chief Judge, and ARCHER and CLEVENGER, Circuit Judges.

DECISION

CLEVENGER, Circuit Judge.

T.F. Powers Construction Company ("Powers") appeals from three decisions made by the Armed Services Board of Contract Appeals ("Board") after a consolidated proceeding in which Powers's claims for equitable adjustment were denied. All three claims arise out of a contract awarded to Powers "to alter and upgrade four two-story unaccompanied enlisted personnel housing (UEPH) buildings at Minot Air Force Base" in North Dakota. In re T.F. Powers Construction Co., ASBCA Nos. 38031, 38479 and 38872, slip op. at 1 (Armed Services Board of Contract Appeals Nov. 20, 1989) ("Powers"). In two of the three claims on appeal, Powers asserts its interpretation of specific contract terms. In the other, Powers seeks reversal of the Board's conclusion that Powers was charged with knowledge of particular site conditions shown in the contract drawings. Because the Board's interpretations of the contract are correct and Powers has not shown the Board's conclusion to be in error, we affirm. Since the operative terms and facts of each claim are not related, we deal with each separately.

OPINION

I. THE BATHROOMS

As part of the housing renovation, Powers was to renovate bathrooms located in each of the sleeping rooms of the dormitories. The bathroom renovation included supplying and installing new bathtubs and new ceramic tile for the bathroom walls. Powers's first claim is for an equitable adjustment to pay for the installation of waterproof wall coverings above the bathtubs in the renovated bathrooms.

Powers was supplied with specifications and drawings that described the extent of the work to be performed. The drawing at issue depicts the bathrooms and appears to require the installation of a fiberglass bathtub and shower combination unit with doors. Drawing A-45, entitled TYPICAL BATHROOM PLANS ("FIBERGLASS BUT/SHOWER COMBINATION W/DOORS"). The specifications flatly contradict this apparent requirement. The "[s]pecification [at] Section 15C, PLUMBING, GENERAL-PURPOSE, called for the installation of showers and new enamelled cast iron bathtubs" instead of the fiberglass single unit. Powers at 2. Both parties concede the blatant conflict between the specifications and the drawing. There is also no dispute that Powers was to rely on the written specifications rather than on the drawing, because the contract contains a clause that directs the contractor to follow the specifications when a conflict exists between specifications and drawings. Powers at 4 (citing General Clause 58, SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION). Neither party contends that there was any ambiguity with regard to the plumbing fixtures required by the contract.

With regard to the ceramic wall tile, "Drawing A-11, [entitled] ROOM FINISH SCHEDULE, and Specification Section 9G, [entitled] DECORATING SCHEDULE (INTERIOR DESIGN SCHEDULE), called for all the walls in the bathrooms to be ceramic tiled." Powers at 2. The specifications further state that "tile shall be ... in colors as specified in SECTION: DECORATING SCHEDULE," Sec. 9B-2 at p 5.1, and that "[t]ile in colors and patterns indicated shall be supplied in the areas shown on the drawings." Specification Sec. 9B-3 at p 6. Id. Drawing A-45 depicts the location of the ceramic tile by the use of cross-hatching. Testimony of Mr. Giere, Corporate Secretary for Powers. Since drawing A-45 erroneously depicts a fiberglass tub/shower combination, there is no cross-hatching in the area immediately above what should be the location of the enamel tub. On the other hand, cross-hatching is present on all otherwise uncovered wall surfaces.

Powers contended that since the specifications only require ceramic tile as depicted in the drawing, and there is no ceramic tile depicted in the drawing above the putative location of the enamel tub, the contract does not call for any type of water resistant wall covering above the enamel tub. No doubt flabbergasted by Powers's interpretation of the contract, the contracting officer directed Powers to install a fiberglass tub-surround to protect the uncovered wall. Powers seeks equitable adjustment for what it considers a constructive change order.

The Government asserts that the contract required ceramic tile as protective wall covering in the bathbay area because, as the Board found, "the ROOM FINISH SCHEDULE on Drawing A-11 and specification Section 9G, DECORATING SCHEDULE, call for all bathrooms walls to be covered with ceramic tile." Powers at 5. The government further asserts that "drawing A-45, TYPICAL BATHROOM PLANS, shows that, where not otherwise covered, the walls in the bathbay area are to be covered with ceramic tile." This assertion requires us to replace the fiberglass tub/shower depicted with an enamel tub. The Government's argument next requires the now exposed wall imputed to the drawing to be covered with cross-hatching. These steps taken, drawing A-45 would require ceramic tile to be installed in the bathbay area.

The Board agreed with the government and held that the terms of the contract "call for all bathroom walls to be covered with ceramic tile." Powers at 5. Furthermore, the Board found that the failure of the tile subcontractor to include tile for all uncovered walls did not absolve Powers of its duty to bid the contract as its terms dictated. Id.

The issue here is one of contract interpretation. "[T]his dispute, turning as it does on an interpretation of contract provisions, involves a question of law which the court is free to answer independently of the Board's decision." HRH Construction Corp. v. U.S., 428 F.2d 1267, 1271 (Ct.Cl.1970). Powers contends that the contract requires tile only where explicitly depicted on the drawings by cross-hatching. The Government contends that specification section 9G-14, ROOM FINISH & COLOR SCHEDULE, and drawing A-11 definitively require "tile on all four walls." However, Powers responds that neither this specification section nor this drawing give any "indication as to where the tile is to be located on those walls" and that, notwithstanding anything implicitly therein to the contrary, the contractor is required expressly by specification section 9B-3, p 6, to place "[t]ile in colors and patterns indicated ... in the areas shown on the drawings." Powers thereby asserts that drawing A-11 and specification section 9G-14 merely "list[ ] each room individually, with columns to show what finish the room was to receive on its floor, ceiling, walls, and doors" as stated at specification Sec. 9B-2, p 5.1 and Sec.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hol-Gar Manufacturing Corp. v. The United States
351 F.2d 972 (Court of Claims, 1965)
Unicon Management Corporation v. The United States
375 F.2d 804 (Court of Claims, 1967)
Hrh Construction Corporation v. The United States
428 F.2d 1267 (Court of Claims, 1970)
Edward R. Marden Corporation v. United States
803 F.2d 701 (Federal Circuit, 1986)
United States v. Turner Construction Co.
819 F.2d 283 (Federal Circuit, 1987)
H & M Moving, Inc. v. United States
499 F.2d 660 (Court of Claims, 1974)
Franchi Construction Co. v. United States
609 F.2d 984 (Court of Claims, 1979)

Cite This Page — Counsel Stack

Bluebook (online)
918 F.2d 187, 1990 U.S. App. LEXIS 18065, 1990 WL 153817, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tf-powers-construction-company-v-the-united-states-cafc-1990.