Paschen Contractors, Inc. And Peter Kiewit Sons' Co., Joint Venturers v. The United States

418 F.2d 1360, 190 Ct. Cl. 177, 1969 U.S. Ct. Cl. LEXIS 164
CourtUnited States Court of Claims
DecidedDecember 12, 1969
Docket451-65
StatusPublished
Cited by8 cases

This text of 418 F.2d 1360 (Paschen Contractors, Inc. And Peter Kiewit Sons' Co., Joint Venturers v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Paschen Contractors, Inc. And Peter Kiewit Sons' Co., Joint Venturers v. The United States, 418 F.2d 1360, 190 Ct. Cl. 177, 1969 U.S. Ct. Cl. LEXIS 164 (cc 1969).

Opinion

PER CURIAM:

This case was referred to Trial Commissioner Louis Spector with directions to prepare and file his opinion on the issues of plaintiff’s motion and defendant’s cross-motion for summary judgment under the order of reference and Rule 99(c) [since September 1, 1969, Rule 166(c)]. The commissioner has done so in an opinion and report filed on February 27, 1969, wherein such facts as are necessary to the opinion are set forth. Requests for review by the court were filed by both parties and the case has been submitted to the court on oral argument of counsel and the briefs of the parties. Since the court agrees with the opinion and recommended conclusion of the trial commissioner, with a minor deletion by the court, it hereby adopts the same, as modified, as the basis for its judgment in this case as hereinafter set forth. Therefore, plaintiff is entitled to recover on Count II, Claim Two, and plaintiff’s motion for summary judgment is granted, and defendant’s cross-motion denied, with respect thereto. Further proceedings thereon are stayed pursuant to Rule 167 [prior to September 1, 1969, Rule 100] for a period of 90 days to afford the parties an opportunity to obtain an administrative resolution by the General Services Administration Board of Contract Appeals, or by the contracting officer, of the equitable adjustment to which plaintiff is entitled under the “Changes” clause contained in the contract. In all other respects plaintiff’s motion for summary judgment is denied, defendant’s cross-motion for summary judgment is granted, and the petition is dismissed.

Commissioner Spector’s opinion, as modified by a minor deletion by the court, is as follows:

Plaintiff is a joint venture which entered into a contract with the United States, acting through the General Services Administration [hereinafter referred to as GSA], for construction, of the United States Courthouse and Federal Office Building in Chicago, Minios. There are two separate claims involved in this action, each of which has heretofore been denied by the agency’s contracting officer, and thereafter on appeal by its Board of Contract Appeals. Each claim hinges upon a proper interpretation of the contract terms, and therefore each essentially involves an administrative decision on a question of law. The administrative decisions are therefore not final 1 and are subject to plenary consideration in this court. 2

Count I in this proceeding (which was designated GSABCA No. 1196 before the Board) relates to a requirement by the contracting officer that plaintiff *1362 cover or insulate certain mixed air supply ducts in hung ceiling spaces, at an alleged additional cost of $161,001.79. Count II (GSABCA No. 1265 before the Board) relates to a requirement by the contracting officer that certain hot, cold and mixed air supply ducts in the basement of the building be covered or insulated at an alleged additional cost of $61,690.40. In both instances, plaintiff in effect claims that these requirements were in excess of and beyond contractual requirements properly interpreted, that they therefore amounted to constructive changes within the meaning of the “Changes” clause of the contract, and that plaintiff is therefore entitled to equitable adjustments in contract price under that clause in the amounts claimed.

GENERAL STATEMENT OF FACTS

The contract called for recirculating air systems employing outside air and recirculated interior air to heat, cool and ventilate the building. Under these systems outside air is drawn into the building through fresh air inlets by fans located in the subbasement where it is mixed with interior air in the ratio of one part outside air to two parts interior air. In accordance with seasonal demand, the air flow is thereafter divided with part being heated by passage through steam coils to a temperature of 87° Fahrenheit, and the remainder passed through chilled water coils to attain a design temperature of 52°.

Heated air leaves the steam coils under high pressure at a velocity of about 5,000 feet per minute and passes through large galvanized metal ducts extending from the subbasement up through the core or center shafts of the building to take-off points on each floor. Chilled air similarly moves at high pressure and velocity in separate ducts to these takeoff points, where mixing boxes are located. There, the pressure and velocity is reduced, and the air mixed to provide a condition on each floor of not over 78° on extreme summer days (95° outdoors), nor less than 70° on extreme winter days (10° outdoors). The mixed air then moves through low pressure ducts where it is emitted through ceiling diffusers into the occupied spaces below.

Some high pressure hot air and cold air is premixed down in the subbasement, and thereafter passes up through a third high pressure duct system in the core or center shafts of the building. Without going to mixing boxes, this premixed air moves directly through its own duct system to individually controlled floor convector units located adjacent to the outside wall of the building, where the convectors themselves serve to reduce the pressure as the air is expelled into the occupied spaces.

These last mentioned high pressure mixed air ducts, and the previously described low pressure mixed air ducts which terminate in ceiling diffusers, are both located on each floor in so-called hung ceiling spaces. A hung ceiling is one suspended by wires and channel iron from the bottom of the concrete ceiling (which is also the floor above). The space between the hung ceiling and the floor above provides a concealed area for the mixed air ducts. In addition, this space is employed as a plenum which acts, in effect, as a return duct for the collection and return of used air from the occupied areas to the subbasement. There part of it is exhausted into the atmosphere, and the rest mixed with fresh outside air for reheating, recooling, and recirculation as above described. For the cooling coils to produce 52° air when it is 95° outdoors, the return air should not exceed 78°. 3

Under Count I of its petition, plaintiff contends that neither the contract specifications, the physical characteristics and requirements of the system, nor trade usage, required the above described *1363 mixed air ducts located in hung ceiling spaces to be insulated or covered.

Under Count II of its petition, plaintiff contends that the earlier described high pressure hot, cold and mixed air ducts were to be interior lined with acoustic material 4 from the supply fans in the subbasement to the ceiling of the first floor. To the extent that they were thus interior lined, the specifications did not require exterior thermal insulation or covering. Plaintiff contends that defendant modified the requirement for interior acoustic lining, substantially reducing the length of duct to be acoustically lined, and thereby correspondingly increasing the length of duct requiring the more costly exterior thermal covering.

As a second argument under Count II, relating to only part of the claim, plaintiff further contends with respect to the high pressure hot

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Farrell Lines Inc. v. United States
499 F.2d 587 (Court of Claims, 1974)
Merando, Inc. v. United States
475 F.2d 598 (Court of Claims, 1973)
Rawleigh, Moses & Co. v. United States
475 F.2d 606 (Court of Claims, 1973)
Southwestern Engineering Co.
196 Ct. Cl. 782 (Court of Claims, 1971)
The Martin Lane Company, Inc. v. The United States
432 F.2d 1013 (Court of Claims, 1970)
Hrh Construction Corporation v. The United States
428 F.2d 1267 (Court of Claims, 1970)

Cite This Page — Counsel Stack

Bluebook (online)
418 F.2d 1360, 190 Ct. Cl. 177, 1969 U.S. Ct. Cl. LEXIS 164, Counsel Stack Legal Research, https://law.counselstack.com/opinion/paschen-contractors-inc-and-peter-kiewit-sons-co-joint-venturers-v-cc-1969.