Tibshraeny Bros. Construction, Inc. v. United States

32 Cont. Cas. Fed. 73,017, 6 Cl. Ct. 463, 1984 U.S. Claims LEXIS 1282
CourtUnited States Court of Claims
DecidedOctober 12, 1984
DocketNo. 610-81C
StatusPublished
Cited by19 cases

This text of 32 Cont. Cas. Fed. 73,017 (Tibshraeny Bros. Construction, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tibshraeny Bros. Construction, Inc. v. United States, 32 Cont. Cas. Fed. 73,017, 6 Cl. Ct. 463, 1984 U.S. Claims LEXIS 1282 (cc 1984).

Opinion

OPINION

TIDWELL, Judge:

This is a government contract ease which comes before the court pursuant to the Tucker Act, 28 U.S.C. 1491, and the Contract Disputes Act of 1978, 41 U.S.C. 609(a)(1). Plaintiff appeals the contracting officer’s decision which denied plaintiff’s claims for damages in the amount of $127,-269 for breach of contract. In addition, plaintiff seeks the release of $20,000 retained by defendant under the contract. Plaintiff claims money damages for time delays and extra costs incurred because of defendant’s alleged failure to provide a complete and accurate set of electrical control drawings. For want of a better name [465]*465this court will refer to the allegedly omitted drawing or drawings as the “control wiring diagram.”1 Defendant denies plaintiff’s contentions and alleges that the drawings were complete and adequate and that the contract required plaintiff to provide the control wiring diagram. Trial was held in Phoenix, Arizona and after careful review of the evidence presented and the applicable law, the court holds for plaintiff on the issue of liability.

FACTS

On July 8, 1977 the Department of the Air Force publicly advertised bids for the modification of existing fueling facilities and for the construction of a hydrant fueling system with POL (jet fuel) operation facility, blast deflector and taxiway at the Arizona Air National Guard facility located at Sky Harbor International Airport, Phoenix, Arizona. Plaintiff, Tibshraeny Brothers Construction Company, a general contractor with offices in Mesa, Arizona, was low bidder and on September 10, 1977 was awarded Contract No. DAHA02-77-C-0023 to construct the project.

In order to prepare the specifications and drawings for the construction of the hydrant fueling system, the Air Force within the same time period entered into a contract with Benham-Blair Ditzler & Elling (Benham-Blair) to provide architect-engineer services. Benham-Blair was required under its contract to design and prepare a completely operational hydrant fueling system based on definitive design drawings prepared by the Air Force.2 Benham-Blair utilized the definitive design drawings to prepare the plans and drawings for the hydrant fueling system which became part of the bid documents. In addition, Ben-ham-Blair modified a set of standard government specifications which also became a part of the bid documents. Before issuing the plans and specifications, they were reviewed by the contracting officer, Harold P. Porter, and the legal and engineering staffs for the Air National Guard in Washington, D.C., and by the regional civil engineer, Department of the Air Force, Western Division, San Francisco, California, and were accepted for use on this project. These modified plans, drawings and bid specifications became part of the contract documents for the hydrant fueling system upon award of the contract to plaintiff.

Originally, the contract was to be completed within 240 days after acknowledgement of the notice to proceed which was issued on September 15, 1977. However, the project was not completed and approved until some 752 days beyond the scheduled completion date. A pre-con-struction conference was held on September 12, 1977 to discuss all aspects of the project including completion schedules. No questions were raised at that conference or at any time prior to the conference by either party about the electrical diagrams shown on pages E-7 and E-8 of the drawings and addressed in several places in the specifications.

Plaintiff began performance within ten days after acknowledging receipt of the notice to proceed and continued construction of the project until forced by weather conditions at the work site to halt construction. Consequently, the contracting officer issued a change order (contract modifica[466]*466tion P-00010) extending the completion date of the contract 63 days or until July 15, 1978.3

During construction of the hydrant fueling system, a dispute arose regarding responsibility for preparation of the control wiring diagram which was necessary for completion of the project. In February of 1978 a meeting was held between defendant, plaintiffs electrical subcontractor, Paradise Valley Electric Company, and plaintiffs representative where the need for the control wiring diagram was discussed. At that meeting plaintiffs subcontractor provided a scheduled completion plan for installation of the control wiring system by July of 1978.4 Plaintiff, however, testified that the issue of whether or not more definitive drawings were needed for the control wiring diagram was not raised at the meeting. Plaintiff also testified that it did not become aware that defendant expected plaintiff to provide the control wiring diagram until July of 1978, near the amended completion date of the contract, when the government notified plaintiffs project manager that plaintiff was to provide the control wiring diagram.

Regardless of when it was first brought to plaintiffs attention, it is clear that at some point the issue of responsibility for preparation of the control wiring diagram arose. It was plaintiffs contention that the control wiring diagram was a design function for which either the government or the government’s architect-engineer, Benham-Blair, was responsible. Plaintiff also contended that nowhere in its contract with the government was it required to provide a control wiring diagram. Instead, plaintiff insisted that Benham-Blair was to perform all design work for the project and to provide complete construction plans and drawings for a fully operational hydrant refueling system including the control wiring diagram. Benham-Blair, however, refused to provide the control wiring diagram contending, with the government’s support, that it was plaintiff’s obligation.

Plaintiff, under protest and in an effort to complete the job, asked the Paradise Valley Electrical Company, to prepare a control wiring diagram. Paradise Valley Electric Company obtained the services of Russell Scholtz, an experienced electrical engineer, and instructed him to “design an operable control diagram for the hydrant refueling system.”

After several weeks of effort, Mr. Scholtz completed a control wiring diagram of his own design which corrected major defects in the original design concept. Plaintiff, on December 15, 1978, submitted the diagram to Benham-Blair through defendant for approval. Benham-Blair rejected the submittal almost immediately on the basis that “the basic design of the diagram was different from that set out in the plans and conceptual drawings E-7 and E-8.” The Benham-Blair rejection also contained the statement “submit in accord with contract documents.”

Plaintiff contends that Benham-Blair gave no indication that the design of the control wiring diagram as prepared by Mr. Scholtz would not work, but that the sub-mittal was rejected because Mr. Scholtz did not use Benham-Blair’s symbols or style of drawing. Plaintiff further contends that Mr. Scholtz was told by a representative of Benham-Blair that he was to use the symbols on the Benham-Blair drawings, make corrections as needed, and design a control wiring diagram within the parameters of the Benham-Blair design concept.

Thereafter, Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

PCL Construction Services, Inc. v. United States
47 Fed. Cl. 745 (Federal Claims, 2000)
Miller Elevator Co. v. United States
39 Cont. Cas. Fed. 76,635 (Federal Claims, 1994)
North Star Alaska Housing Corp. v. United States
39 Cont. Cas. Fed. 76,607 (Federal Claims, 1993)
M.A. Mortenson Co. v. United States
39 Cont. Cas. Fed. 76,555 (Federal Claims, 1993)
Orange Cove Irrigation District v. United States
28 Fed. Cl. 790 (Federal Claims, 1993)
Shearson Lehman Hutton, Inc. v. United States
37 Cont. Cas. Fed. 76,245 (Court of Claims, 1991)
Ludka v. United States
37 Cont. Cas. Fed. 76,228 (Court of Claims, 1991)
Coflexip & Services, Inc. v. United States
37 Cont. Cas. Fed. 76,089 (Court of Claims, 1991)
Romala Corp. v. United States
37 Cont. Cas. Fed. 76,050 (Court of Claims, 1990)
Chevron U.S.A., Inc. v. United States
36 Cont. Cas. Fed. 75,838 (Court of Claims, 1990)
Blue Cross & Blue Shield Ass'n v. United States
35 Cont. Cas. Fed. 75,688 (Court of Claims, 1989)
Diggins Equipment Corp. v. United States
35 Cont. Cas. Fed. 75,687 (Court of Claims, 1989)
Beta Systems, Div. of Velcon Filters, Inc. v. United States
35 Cont. Cas. Fed. 75,613 (Court of Claims, 1989)
Underground Construction Co. v. United States
35 Cont. Cas. Fed. 75,604 (Court of Claims, 1988)
Big Chief Drilling Co. v. United States
15 Cl. Ct. 295 (Court of Claims, 1988)
Kunz Construction Co. v. United States
34 Cont. Cas. Fed. 75,243 (Court of Claims, 1987)
John C. Grimberg Co. v. United States
32 Cont. Cas. Fed. 73,264 (Court of Claims, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
32 Cont. Cas. Fed. 73,017, 6 Cl. Ct. 463, 1984 U.S. Claims LEXIS 1282, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tibshraeny-bros-construction-inc-v-united-states-cc-1984.