Coflexip & Services, Inc. v. United States

37 Cont. Cas. Fed. 76,089, 23 Cl. Ct. 67, 1991 U.S. Claims LEXIS 155, 1991 WL 71217
United States Court of Claims·Decided May 2, 1991·No. No. 33-88C·Published·Cited by 1 cases

Opinion

ORDER

MOODY R. TIDWELL, III, Judge:

This matter is again before the court on the parties’ cross-motions for summary judgment pursuant to Rule 56 of the United States Claims Court (RUSCC) following partial denial of their prior cross-motions for summary judgment in Coflexip & Servs., Inc. v. United States, 20 Cl.Ct. 412 (1990) (Coflexip I). For the reasons stated below, the court now grants defendant’s motion for summary judgment, and denies plaintiff’s cross-motion for summary judgment for costs incurred in developing a prototype of its offered design.

FACTS

Plaintiff Coflexip & Services, Inc., an unsuccessful offeror on a component of an Offshore Petroleum Delivery System (OPDS) contract awarded by the United States through the Department of Transportation, Maritime Administration (Mar-Ad), seeks damages for defendant’s breach of an implied contract to consider plaintiff’s proposal honestly and fairly.1

On March 2, 1984, AMETEK, a subagent acting for Watters Marine, Inc., MarAd’s general ship operating agent, issued a Request for Proposals (RFP) to procure a system that would deliver petroleum from a tanker anchored offshore to an on-shore military facility. The RFP sought proposals for three primary components: a tanker, a single point mooring system, and a flexible pipe conduit system. Offerors could propose to furnish the entire system, a single component, or a combination of components. The RFP stated the standard and level of performance required of the entire system but provided little, if any, technical guidance as to how contractors were to meet those requirements.

Shortly after issuance of the RFP, plaintiff and five other companies submitted proposals to furnish some or all of the components for the requested system. Plaintiff submitted a proposal to furnish only the flexible conduit system. AME-TEK reviewed and immediately eliminated four of the proposals, and recommended further review of the proposals of plaintiff and Simplex Wire & Cable, the remaining offerors on the flexible conduit pipeline component of the system. Throughout April and May, 1984, plaintiff, MarAd, and Watters discussed various aspects of the procurement, the significance of which the parties dispute. In July, 1984, MarAd informed plaintiff that the contract for the flexible conduit would go to Simplex, and [69] formally awarded the contract to Simplex on August 3, 1984.

Coflexip filed a formal protest of the award with the General Accounting Office (GAO) in October, 1984. The comptroller General found Simplex’s system technically superior, but that the government had breached its implied-in-fact contract to consider plaintiff’s proposal honestly and fairly. Specifically, the Comptroller General opined that defendant had relaxed certain technical specifications and the delivery schedule for Simplex, but not for plaintiff. The Comptroller General declined to overturn the contract award in the matter of Coflexip & Services, Inc. because of the high costs of terminating for convenience, but did conclude that plaintiff was entitled to reimbursement for its proposal preparation costs. 85-1 Comp.Gen.Proc.Dec. 554 (May 16, 1985).

Pursuant to the GAO finding, plaintiff filed a claim with the United States for $257,142.63 which amount included costs associated with the development of a prototype of its flexible conduit pipe system, and the protest before the GAO. The Defense Contract Audit Agency (DCAA) performed an audit of plaintiff’s claim and found that plaintiff incurred approximately $200,-000.00 of its claimed $257,142.63 proposal preparation expenses after it submitted its technical and cost proposals in March, 1984. It concluded that post-submission costs could not be considered proposal preparation costs. Based on the audit, defendant reimbursed plaintiff for only $54,-141.00 of the total amount claimed. This figure did not include any costs associated with the prototype. In Coflexip I, plaintiff sought the cost of the protest and prototype costs. Both parties moved for summary judgment.

This court granted summary judgment for defendant on plaintiff’s claim for protest costs because the Competition in Contracting Act of 1984 (CICA), Pub.L.N. 98-369, 98 Stat. 1175, was not in force at the time defendant issued the RFP. Absent the specific waiver of sovereign immunity contained in CICA, this court found that it had no jurisdiction to award recovery of a money judgment for contract protest costs against the United States. Coflexip I, 20 Cl.Ct. at 415, (citing United States v. Mitchell, 445 U.S. 535, 538, 100 S.Ct. 1349, 1351-52, 63 L.Ed.2d 607 (1980)); see also United States v. Testan, 424 U.S. 392, 398, 96 S.Ct. 948, 953, 47 L.Ed.2d 114 (1976); United States v. Connolly, 716 F.2d 882, 885 (Fed.Cir.1983) (en banc), cert. denied, 465 U.S. 1065, 104 S.Ct. 1414, 79 L.Ed.2d 740 (1984). The court did not grant summary judgment on the costs incurred by plaintiff in developing a prototype of the flexible conduit system because it could not conclude, as a matter of law, that defendant did not require or induce plaintiff to develop a prototype of its system as a precondition to contract award.

DISCUSSION

An unsuccessful bidder’s standing to challenge the award of a government contract is based on an implied-in-fact contract, arising upon the submission of a proposal, that the government will consider the proposal honestly and fairly. Heyer Prods. Co. v. United States, 140 F.Supp. 409, 135 Ct.Cl. 63, 69 (1956). The terms of the implied contract are those elements of the RFP governing activities of offerors and the government prior to award of the contract. AT & T Technologies, Inc. v. United States, 18 Cl.Ct. 315, 321 (1989). An unsuccessful bidder may recover only those costs incurred in preparing its technical proposal or bid. Keco Indus. Inc. v. United States, 192 Ct.Cl. 773, 785 (1970).

Free access — add to your briefcase to read the full text and ask questions with AI

Coflexip & Services, Inc. v. United States, 37 Cont. Cas. Fed. 76,089, 23 Cl. Ct. 67, 1991 U.S. Claims LEXIS 155, 1991 WL 71217 (cc 1991).

37 Cont. Cas. Fed. 76,089 (Coflexip & Services, Inc. v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Coflexip & Services, Inc. v. The United States
961 F.2d 951 (Federal Circuit, 1992)