Coflexip & Services, Inc. v. The United States

961 F.2d 951, 37 Cont. Cas. Fed. 76,297, 92 Daily Journal DAR 5622, 1992 U.S. App. LEXIS 6743, 1992 WL 72730
CourtCourt of Appeals for the Federal Circuit
DecidedApril 14, 1992
Docket91-5118
StatusPublished
Cited by17 cases

This text of 961 F.2d 951 (Coflexip & Services, Inc. v. The United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Coflexip & Services, Inc. v. The United States, 961 F.2d 951, 37 Cont. Cas. Fed. 76,297, 92 Daily Journal DAR 5622, 1992 U.S. App. LEXIS 6743, 1992 WL 72730 (Fed. Cir. 1992).

Opinion

LOURIE, Circuit Judge.

This is an appeal from the May 2, 1991, decision of the United States Claims Court granting the Maritime Administration, U.S. Department of Transportation’s (MarAd’s), motion for summary judgment. Coflexip & Servs., Inc. v. United States, 23 Cl.Ct. 67 (1991). The court denied Coflexip’s claim for certain proposal preparation costs, limiting recovery to those costs required as a *952 precondition of the contract award. Id. at 70. Because we conclude that the court erred, we vacate and remand.

BACKGROUND

In 1984, MarAd issued a solicitation for the procurement of a system to deliver petroleum from a tanker anchored offshore to a military facility located on-shore. Coflexip submitted a proposal to furnish the flexible pipe conduit sub-system for this solicitation. Upon award of the contract to another contractor, Coflexip filed a formal protest with the General Accounting Office. The GAO determined that Coflexip was entitled to recover its proposal preparation costs because MarAd had improperly conducted the procurement and, but for MarAd’s improper conduct, Coflexip would have had a substantial chance of being awarded the contract. Coflexip & Servs., Inc., 85-1 Comp.Gen. 554 (1985).

Coflexip submitted a request to MarAd for reimbursement of $257,142 in proposal preparation costs. Following a government audit, MarAd reimbursed Coflexip for all proposal preparation costs Coflexip incurred prior to its submission of the technical and cost proposals to MarAd, a total of $54,141. The remaining costs claimed by Coflexip included $46,359 in legal expenses relating to the bid protest, $10,340 in miscellaneous travel and entertainment expenses, and $146,302 in prototype development expenses. Coflexip filed suit in the United States Claims Court seeking recovery of these remaining expenses. Coflexip & Servs., Inc., 20 Cl.Ct. 412 (1990).

On cross-motions for summary judgment, the court rejected MarAd’s argument that, as a matter of law, prototype costs incurred subsequent to proposal submission in a negotiated procurement cannot be proposal preparation costs. Furthermore, the court determined that genuine issues of material fact remained regarding any contractual requirement for Coflexip to build a prototype as a precondition of the contract award. As a result, the court denied both summary judgment motions. 1

MarAd filed a second motion for summary judgment of nonliability for Coflexip’s prototype development expenses. Coflexip filed a cross-motion. Determining that the solicitation did not require Coflexip to build a prototype as a precondition of contract award, the court granted MarAd’s motion. 2 Coflexip appealed.

ISSUE

Whether the Claims Court erred in its determination that Coflexip’s prototype development expenses could not be reimbursed as proposal preparation costs?

DISCUSSION

A court’s interpretation of a contract is an issue of law that is reviewed de novo. George Hyman Constr. Co. v. United States, 832 F.2d 574, 579 (Fed.Cir. 1987). We conclude that the Claims Court applied an improper standard for determining which proposal preparation costs could be recovered by Coflexip. Specifically, the court erred in determining that an unsuccessful bidder’s recoverable proposal preparation costs are limited to those costs required by the solicitation or approved by MarAd upon notification by the contractor.

It is clear that, under certain circumstances, an unsuccessful bidder on a government contract may recover its proposal preparation costs. See, e.g., Keco Indus. Inc. v. United States, 203 Ct.Cl. 566, 492 F.2d 1200, 1203-1205 (1974). Recovery can be obtained, inter alia, if the government breached an implied-in-fact contract “to treat a bid honestly and fairly,” in which case its “conduct was arbi *953 trary and capricious toward the bidder-claimant.” Coastal Corp. v. United States, 713 F.2d 728, 730 (Fed.Cir.1983). Entitlement to recovery of some costs is not at issue here. What is contested is which costs are properly recoverable.

The Claims Court held that Coflexip incurred prototype development costs after submission of its initial technical proposal and that, because these costs were not required by the solicitation, they were not recoverable. Coflexip does not contest that it incurred the prototype costs post-submission. However, it argues that the proper standard for determining recoverability is well-defined in the federal procurement regulations and that, under certain circumstances, post-submission costs voluntarily incurred may be recoverable proposal preparation costs. MarAd argues that the Claims Court properly limited the terms of the implied-in-fact contract to the pertinent provisions in the solicitation and that the solicitation did not require development of a prototype. We conclude that the court erred and that Coflexip is correct.

In a written answer to a bidder’s presubmission question, MarAd stated that all the proposals would be treated in accordance with standard federal procurement regulations. Neither Coflexip nor the other bidders disagreed. Therefore, the terms of the present implied-in-fact contract incorporate the pertinent provisions of the regulations, as well as those of the solicitation.

Part XV of the regulations defines proposal preparation costs as “costs of preparing bids or proposals on potential Government ... contracts, ... including the development of engineering data and cost data necessary to support the contractor’s bids or proposals.” 3 41 C.F.R. § 1-15.205-3 (1983). Additionally, Part XV states that “[these] costs shall be allowed to the extent that they are reasonable (see § 1-15.201-3), [and] allocable (see § 1-15.201-4).” 41 C.F.R. § 1-15.204 (1983). Accordingly, proposal preparation costs that are reasonable and allocable may be recovered by the contractor. This definition, however, does not address the issue whether post-submission costs may be proposal preparation costs.

The Claims Court held that Mar-Ad anticipated a negotiated procurement for this solicitation, and MarAd does not dispute this on appeal. Part I of the regulations states that “[w]henever negotiations are conducted with several offerors ... [they] shall be offered an equitable opportunity to submit such price, technical, or other revisions in their proposals as may result from the negotiations.” 41 C.F.R. § 1-3.805-1 (1984). Additionally, the offerors must be informed of the specific date of the closing of negotiations, and proposal revisions must be submitted by that date. Id. Therefore, in a negotiated procurement, the costs a contractor incurs pursuant to ongoing negotiations

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Arxium, Inc. v. United States
Federal Claims, 2023
State of Georgia v. President of the United States
46 F.4th 1283 (Eleventh Circuit, 2022)
Hymas v. United States
117 Fed. Cl. 466 (Federal Claims, 2014)
Neie, Inc. v. United States
Federal Claims, 2013
Reema Consulting Services, Inc. v. United States
107 Fed. Cl. 519 (Federal Claims, 2012)
Alabama Aircraft Industries, Inc. v. United States
85 Fed. Cl. 558 (Federal Claims, 2009)
Geo-Seis Helicopters, Inc. v. United States
79 Fed. Cl. 74 (Federal Claims, 2007)
Rothe Development Corp. v. U.S. Department of Defense
499 F. Supp. 2d 775 (W.D. Texas, 2007)
Beta Analytics International, Inc. v. United States
75 Fed. Cl. 155 (Federal Claims, 2007)
S.K.J. & Associates, Inc. v. United States
67 Fed. Cl. 218 (Federal Claims, 2005)
Lion Raisins, Inc. v. United States
52 Fed. Cl. 629 (Federal Claims, 2002)
R.R. Donnelley & Sons, Co. v. United States
42 Cont. Cas. Fed. 77,249 (Federal Claims, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
961 F.2d 951, 37 Cont. Cas. Fed. 76,297, 92 Daily Journal DAR 5622, 1992 U.S. App. LEXIS 6743, 1992 WL 72730, Counsel Stack Legal Research, https://law.counselstack.com/opinion/coflexip-services-inc-v-the-united-states-cafc-1992.