Beta Analytics International, Inc. v. United States

75 Fed. Cl. 155, 2007 U.S. Claims LEXIS 21, 2007 WL 315097
CourtUnited States Court of Federal Claims
DecidedJanuary 31, 2007
DocketNo. 04-556C
StatusPublished
Cited by17 cases

This text of 75 Fed. Cl. 155 (Beta Analytics International, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Beta Analytics International, Inc. v. United States, 75 Fed. Cl. 155, 2007 U.S. Claims LEXIS 21, 2007 WL 315097 (uscfc 2007).

Opinion

MEMORANDUM OPINION AND ORDER

WOLSKI, Judge.

The matter before the Court is the application of plaintiff Beta Analytics International, Inc. (“BAI” or “Beta”) for an award of bid preparation and proposal costs, brought under 28 U.S.C. § 1491(b)(2). The Court had previously determined—after contract performance had already begun—that the government acted arbitrarily and capriciously in awarding a Defense Advanced Research Projects Agency (“DARPA”) contract to intervenor Maden Tech Consulting, Inc., see Beta Analytics Int’l v. United States, 67 Fed.Cl. 384, 408 (2005) (“Beta I ”), and ordered a re-procurement to replace this contract. See Beta Analytics Int’l v. United States, 69 Fed.Cl. 431, 434-35 (2005) (“Beta II ”). Beta has applied for a total of $128,382.51 in bid preparation and proposal costs, broken down as follows: $103,759.86 for administrative staff time, labor, and overhead costs; $4,900 in consulting fees; and $19,722.65 for publishing costs. Pl.’s Appl. at 2. For the reasons below, the Court concludes that BAI is entitled to $111,900.82.

I. BACKGROUND

Beta had been the incumbent contractor performing the predecessor to the contract which was the subject of this case. See Beta I, 67 Fed.Cl. at 386. It filed a complaint and a motion for a preliminary injunction with this court shortly before the intervenor was to begin performance under the new contract, and without the benefit of an administrative record (as BAI did not precede this filing with a protest before the United States General Accounting Office, for which a record would have been assembled, see Orion Int’l Techs, v. United States, 60 Fed.Cl. 338, 343 (2004)). See Beta I, 67 Fed.Cl. at 393. Under the handicap of the absence of a record, the motion for a preliminary injunction was denied by the Court, and intervenor assumed the contract a few days later. Id.

The case was then placed on a normal schedule for the briefing and argument of motions for judgment on the administrative record. Finding that BAI would have had a substantial chance to receive the contract award had the government not acted arbitrarily and capriciously in evaluating the proposals, the Court requested a joint status report from the parties to address potential remedies. See id. at 408.- The parties all agreed that a re-procurement should be ordered for a new contract scheduled to begin upon the expiration of the one-year option which had already been exercised. Beta II, 69 Fed.Cl. at 432. There was also agreement on a schedule under which BAI would be given the opportunity to apply for bid proposal costs, and the government be given the opportunity to respond. Id.

After some delay, BAI submitted its application for bid preparation and proposal costs. The application was supported by three exhibits. See Pl.’s Appl. The first was an affidavit from Mr. Fred D. McDougall, BAI’s Vice President for Operations. See Ex. A to Pl.’s Appl. Mister McDougall explained the work performed by BAI’s staff, id. 11113-8, its consultant, id. HH 9-10, and its publishing company. Id. 1111. His affidavit, in turn, contains six exhibits: the list “Staff and Proposal Task Assignments for DARPA Proposal,” Ex. A-l to Pl.’s Appl.;1 a list of dates and activities entitled “DARPA Proposal Task Work Schedule,” Ex. A-2 to id.; the agenda from the organizational meeting at which the work on the proposal was planned, Ex. A-4 to id.; two spreadsheets re-creating the hours worked to prepare for and write the proposal-—one showing each employee’s monthly total, Ex. A-3 to id., and the other showing the hours worked by each employee on various tasks, Ex. A-5 to id.; and a table showing the effective hourly rates for each [158]*158employee who worked on the proposal. Ex. A-6 to id. The second exhibit to the application was a set of three invoices from BAI’s consultant. Ex. B to id. The application’s third exhibit was a set of fifteen invoices from its publishing company. Ex. C to id.

The government, after some delay, filed its response to BAI’s application, arguing that only $3,993.44 in printing costs should be awarded. See Def.’s Resp. at 8. After two enlargements of time were granted, BAI filed a reply to the government’s response. See Pl.’s Reply. Accompanying this reply, and filed under seal, was a binder containing two additional exhibits. The first reply exhibit consisted of 807 pages of material pertaining to the preparation and drafting of BAI’s proposal—including some letters and the slides from meeting presentations, Ex. 1 to Pl.’s Reply at 2-4, 9-70, but mostly composed of numerous drafts of the various sections and sub-sections of the proposal. Id. at 71-609, 614-804. The second reply exhibit was a table showing the hours worked by each employee on the proposal, this time divided among the three volumes of the proposal and the “organization and administration” category encompassing planning meetings and the like. Ex. 2 to Pl.’s Reply.

The government was then given leave to file a sur-reply, and BAI was permitted to file a response. See Def.’s Mot. for Leave to File Sur-reply (“Def.’s Sur-reply”); Pl.’s Resp. to Def.’s Sur-reply (“Pl.’s Resp.”). This opinion comes after a careful consideration of the arguments made in the five papers submitted by the parties, and of the exhibits filed in support of the application.

II. DISCUSSION

A. Court Authority to Award Bid Preparation and Proposal Costs

It has long been recognized by our court (and its predecessor) that under certain circumstances, bid preparation and proposal costs may be recovered by unsuccessful bidders. Initially, this was the only remedy available to unsuccessful bidders for the government’s breach of an imphed-in-faet contract guaranteeing that solicited proposals would be fairly and honestly considered by agency evaluators. See Heyer Products Co. v. United States, 135 Ct.Cl. 63, 69-71, 140 F.Supp. 409 (1956). The circumstances justifying such an award first appeared limited to fraudulent, intentionally unlawful procurement activity. See id. at 71; but see Heyer Products Co. v. United States, 147 Ct.Cl. 256, 258, 177 F.Supp. 251 (1959) (explaining, using broader terms, that there could be no recovery of bid costs if the government was “not fraudulent nor arbitrary nor capricious nor so unreasonable as to necessarily imply bad faith” in its procurement actions). The Court of Claims later explicitly rejected the notion that bid preparation and proposal costs could only be recovered in “situations involving favoritism and discrimination.” Keco Indus. v. United States, 192 Ct.Cl. 773, 780, 428 F.2d 1233 (1970). The court instead adopted “a broad general rule which is that every bidder has the right to have his bid honestly considered by the Government,” id., which protected bidders from ordinary arbitrary and capricious actions. See id. at 783-84, 428 F.2d 1233

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mayvin, Inc v. United States
Federal Claims, 2026
Arxium, Inc. v. United States
Federal Claims, 2023
Caddell Construction Company v. United States
125 Fed. Cl. 30 (Federal Claims, 2016)
Cms Contract Management Services v. United States
123 Fed. Cl. 534 (Federal Claims, 2015)
Square One Armoring Service, Inc. v. United States
123 Fed. Cl. 309 (Federal Claims, 2015)
Caddell Construction Co., Inc. v. United States
111 Fed. Cl. 49 (Federal Claims, 2013)
Reema Consulting Services, Inc. v. United States
107 Fed. Cl. 519 (Federal Claims, 2012)
Technical Innovation, Inc. v. United States
93 Fed. Cl. 276 (Federal Claims, 2010)
Klinge Corp. v. United States
87 Fed. Cl. 473 (Federal Claims, 2009)
Alabama Aircraft Industries, Inc. v. United States
85 Fed. Cl. 558 (Federal Claims, 2009)
CNA Corp. v. United States
83 Fed. Cl. 1 (Federal Claims, 2008)
Precision Images, LLC v. United States
79 Fed. Cl. 598 (Federal Claims, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
75 Fed. Cl. 155, 2007 U.S. Claims LEXIS 21, 2007 WL 315097, Counsel Stack Legal Research, https://law.counselstack.com/opinion/beta-analytics-international-inc-v-united-states-uscfc-2007.