Informatics Corp. v. United States

42 Cont. Cas. Fed. 77,311, 40 Fed. Cl. 508, 1998 U.S. Claims LEXIS 51, 1998 WL 117916
CourtUnited States Court of Federal Claims
DecidedMarch 18, 1998
DocketNo. 98-16C
StatusPublished
Cited by14 cases

This text of 42 Cont. Cas. Fed. 77,311 (Informatics Corp. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Informatics Corp. v. United States, 42 Cont. Cas. Fed. 77,311, 40 Fed. Cl. 508, 1998 U.S. Claims LEXIS 51, 1998 WL 117916 (uscfc 1998).

Opinion

OPINION

MILLER, Judge.

This post-award bid protest case is before the court on the administrative record, as supplemented, after argument on cross-motions for summary judgment. The issue to be decided is whether the contracting officer’s finding that plaintiff’s proposal presented an organizational conflict of interest that could not be avoided or mitigated was arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law.

FACTS

1. The solicitation

On or about June 19, 1997, the Human Systems Center for Environmental Contracting Division (“HSC/PKV”) at Brooks Air Force Base issued a draft request for proposal No. F41624-97-R-8001 (the “RFP” or “solicitation”) for “Systems Engineering and Technical Assistance (“SETA”), Assistance and Advisory Services” to support the Air Force Center for Environmental Excellence (“AFCEE”).1 The subsequent modified RFP was issued on July 30, 1997, and, notably, contemplated award to two qualified contractors. The contract had a ceiling not to exceed $46.1 million.

The SETA solicitation’s Statement of Work (the “SOW”) called for the contractor to support AFCEE’s environmental programs such as Base Realignment and Closure, Environmental Planning, Environmental Quality (including pollution prevention and compliance), infrastructure and weapons systems, Environmental Impact Analysis Process, and Military Family Housing Initiatives. Although the SETA solicitation en[510]*510compassed a multitude of diverse tasks,2 individual Task Orders would be employed, so the exact nature and location3 of the work to be performed would be somewhat speculative until the Task Orders actually were issued.

The SETA RFP included several organizational conflict of interest (“OCI”) clauses,4 which incorporate AFMC FAR Supp. Clause 5352.209-9002 (July 1997), and which provide, in pertinent part:

(a)(2) Restrictions:
(i).... [T]he Contractor’s judgment and recommendations must be objective, impartial, and independent. To avoid the prospect of the Contractor’s judgment or recommendations being influenced by its own products or capabilities, it is agreed that the Contractor is precluded for the life of the system [5] from award of a DoD contract to supply the system or any of its major components, and from acting as a subcontractor or consultant to a DoD supplier for the system or any of its major components.
ALTERNATE I (Jul.1997) (a)(2)(h) The contractor shall prepare and submit complete specifications for nondevelopmental items to be used in a competitive acquisition. The contractor shall not furnish these items to the DoD, either as a prime or subcontractor for the duration of the contract plus one year.
ALTERNATE IV (Jul.1997) (e) The Contractor agrees to accept and to complete all issued Task Orders, and not to contract with Government prime Contractors or first-tier subcontractors in such a way as to create an organizational conflict of interest.
ALTERNATE VI (Jul.1997) (f) The above restrictions shall be included in all subcontracts, teaming arrangements, and other agreements calling for performance of work which is subject to the organizational conflict of interest restrictions identified in this clause, unless excused in writing by the Contracting Officer.

Section L-2 of the solicitation also included a clause entitled “Potential Organizational Conflict of Interest,” which provides:

(a) There is a potential organizational conflict of interest (see FAR Subpart 9.5, Organizational and Consultant Conflicts of Interest) due to the nature of the Statement of Work Requirements. Accordingly:
(1) Restrictions are needed to avoid the prospect of the contractor’s judgment or recommendations being influenced by its own products or capabilities. Theses restrictions shall be in effect for the life of the contract plus 1 year. "
[511]*511(2) As a part of the proposal, the offeror shall provide the Contracting Officer with complete information of previous or ongoing work that is in any way associated with the contemplated acquisition.
(b) If award is made to the offeror, the resulting contract may include an organizational conflict of interest limitation applicable to subsequent Government work, at either a prime contract level, at any subcontract tier, or both. During evaluation of submitted proposals, the Government may, after discussions with the offeror and consideration of ways to avoid the conflict of interest, insert a special provision in the resulting contract which will disqualify the offeror from further consideration for award of future contracts.
(c) The organizational conflict of interest clause included in this solicitation may be modified or deleted during negotiations.
2. Plaintiff’s proposal and OCI mitigation plan

In response to the RFP, Informatics Corporation (“plaintiff’), designated a small disadvantaged business operating under the United States Small Business Administration’s (“SBA”) 8(a) program, 15 U.S.C.A. § 637(a) (West.Supp.1997), submitted a proposal stating that all SETA work would be performed by plaintiff itself or by one of three subcontractor team members: Operational Technologies (“OpTech”), Team LC, or SMS. Although none of these subcontractors held any direct contracts with AFCEE, OpTech held two subcontracts under two AFCEE contracts for environmental remedial work to be performed at Otis Air Force Base. At the time it submitted its proposal, plaintiff held another contract with AFCEE, as a subcontractor to the SBA, to perform “community relations” work with respect to base-closure programs.6 Pursuant to this contract, which expires on January 25, 1999, and covers a nine-state area, plaintiff had performed work at five Air Force bases. Plaintiffs work now involves only Lowry Air Force Base and requires approximately 24 hours of work per week, generating $60,-000.00 in revenues per year.

By letter dated August 8, 1997 to Mary Habib, the Contracting Officer for the Program Support Branch, HSC/PKV at Brooks Air Force Base, plaintiff requested written clarification that the contracting officer agreed that it had no OCI regarding its AFCEE community relations/administrative record contract. In her August 20, 1997 response, Ms. Habib informed plaintiff that “[t]he successful SETA contractor must be eligible/qualified to perform on all orders. There are currently no provisions in either the SETA solicitation or the Community Relations Contract to allow the successful offer- or to decline delivery/task orders.”7 Ms. Habib also stated, that the OCI clause “applies to the prime contractor and all subcontractors. Because OPTECH is a contractor or subcontractor on a current AFCEE contract, the inclusion of OpTech as a subeontractor/teaming member would most likely create an OCI.” Ms. Habib did not specify whether plaintiffs community relations contract presented a potential OCI, although defendant argues that her reference to the Community Relations contract in regard to declining delivery orders implicitly communicated that this contract did pose an OCI. Finally, Ms.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Alabama Aircraft Industries, Inc. v. United States
85 Fed. Cl. 558 (Federal Claims, 2009)
Beta Analytics International, Inc. v. United States
75 Fed. Cl. 155 (Federal Claims, 2007)
Filtration Development Co. v. United States
60 Fed. Cl. 371 (Federal Claims, 2004)
Filtration Development Co., LLC v. United States
59 Fed. Cl. 658 (Federal Claims, 2004)
Vantage Associates, Inc. v. United States
59 Fed. Cl. 1 (Federal Claims, 2003)
LeBoeuf, Lamb, Greene & MacRae, LLP v. Abraham
215 F. Supp. 2d 73 (District of Columbia, 2002)
Ceres Environmental Services, Inc. v. United States
52 Fed. Cl. 23 (Federal Claims, 2002)
Bean Stuyvesant, L.L.C. v. United States
48 Fed. Cl. 303 (Federal Claims, 2000)
DSD Laboratories, Inc. v. United States
46 Fed. Cl. 467 (Federal Claims, 2000)
Cube Corp. v. United States
46 Fed. Cl. 368 (Federal Claims, 2000)
MVM, Inc. v. United States
46 Fed. Cl. 137 (Federal Claims, 1999)
Synetics, Inc. v. United States
45 Fed. Cl. 1 (Federal Claims, 1999)
Miller-Holzwarth, Inc. v. United States
42 Fed. Cl. 643 (Federal Claims, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
42 Cont. Cas. Fed. 77,311, 40 Fed. Cl. 508, 1998 U.S. Claims LEXIS 51, 1998 WL 117916, Counsel Stack Legal Research, https://law.counselstack.com/opinion/informatics-corp-v-united-states-uscfc-1998.