Essex Electro Engineers, Inc. v. United States

31 Cont. Cas. Fed. 71,391, 3 Cl. Ct. 277, 1983 U.S. Claims LEXIS 1652
CourtUnited States Court of Claims
DecidedAugust 12, 1983
DocketNo. 480-83C
StatusPublished
Cited by69 cases

This text of 31 Cont. Cas. Fed. 71,391 (Essex Electro Engineers, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Essex Electro Engineers, Inc. v. United States, 31 Cont. Cas. Fed. 71,391, 3 Cl. Ct. 277, 1983 U.S. Claims LEXIS 1652 (cc 1983).

Opinion

OPINION

NETTESHEIM, Judge.

This is a suit for temporary, preliminary, and permanent injunctive relief and a declaratory judgment restraining the Federal Aviation Administration (the “FAA”) from awarding a contract to any bidder other than plaintiff Essex Electro Engineers, Inc. (“Essex”), declaring that Essex is entitled to award of the contract, and directing the FAA to award the contract to Essex.1 The parties have cross-moved for summary [279]*279judgment on the merits, and a hearing has been held.

FACTS

Over one year ago, the FAA issued Invitation for Bids No. DTFA-02-82-B-00663 (the “IFB”) for the production of 17 engine generator sets to be used at new automated flight service stations in different locations within the United States. On September 9, 1982, eight bids were opened displaying a range of approximately $600,000. The low bidder was Forster Enterprises (“Forster”) at $777,746; Essex’s bid of $845,560 was the second low bid; and Introl Corporation (“Introl”) was the third low bid at $969,325. Forster provisionally was found to be the lowest responsive and responsible bidder by the FAA and the Small Business Administration.

Shortly thereafter, Introl initiated what has proved to be unflagging efforts to eliminate Forster and Essex. In its first protest lodged with the General Accounting Office (the “GAO”), as clarified by a subsequent letter, Introl urged two arguments, one of which would have disqualified Introl’s own bid. The FAA rebuffed Introl and recommended that the GAO deny this protest. In connection with Introl’s first protest, the contracting officer had submitted his statement finding both Forster and Essex responsive. Introl then addressed another protest to the GAO, and, after clarifying its protest both orally and in writing (the record is incomplete as to Introl’s communications with the FAA and GAO on its protest), Introl found a more receptive audience.

The IFB specified engines operating at 60 Hertz in accordance with certain requirements, one of which was that the engine run at a maximum synchronous speed of 1200 rpm. The IFB provided in pertinent part:

NOTICE H SUBMITTAL OF DATA

1. The Bidder is requested to furnish descriptive literature for the proposed engine, generator, and transfer equipment .... This is requested for information purposes only, but any equipment furnished during the contract performance must comply with paragraphs 3.3.2, engine; 3.4.1, generator; ... and any and all pertinent paragraphs of specification FAA-E2204c, as amended.

The IFB also required identification of the manufacturer and model of the engine which the bidder proposed to furnish.

Forster offered a Cummins NT-855G engine and submitted several descriptive commercial bulletins. This material revealed that the proposed Cummins engine operated at 1500 rpm or 1800 rpm engine output and not the required 1200 rpm. For its part Essex offered to supply the same Cummins engine or an Allis-Chalmers No. 6138T engine.2 Essex did not provide any descriptive literature on the Cummins engine, although two pages of literature applicable to a standard model Allis-Chalmers engine were included. This literature did not address engine output. Introl based its bid on a General Motors No. 8V-71 series engine “1200 rpm per spec.” and tendered no descriptive literature or model number.

The cover letter accompanying Essex’s bid stated in part:

Enclosed herewith is our bid for referenced solicitation, including some descriptive literature. It is to be noted that the literature submitted is general in nature, and is not intended to completely describe the items.
If any specification conflicts, or ommis-sions [sic] exist between the general literature and the bid specification, the bid specification FAA-E-2204c as amended, shall govern.
Proposed sources are listed for information purposes only, and other sources of supply which meet all the applicable requirements of the specification FAA— E-2204c, as amended, may be supplied.

[280]*280Introl’s second-wave protest was that both Forster and Essex were nonresponsive because the descriptive literature submitted with Forster’s bid disqualified the Cummins engine. Given that the Cummins engine was identical to one of the two engines Essex proposed to furnish, Essex’s bid was rendered nonresponsive,. as well. Introl contended that Essex’s submission of partial literature on the Allis-Chalmers was inconsistent with the IFB specification requirements in that “the missing pages of the descriptive literature [furnished by Essex] for the Allis [sic] Chalmers engine show that this engine operates at 1800 rpm.” Feb. 23,1983 ltr. from FAA to GAO at 3. The FAA obtained a complete brochure from Allis-Chalmers that confirmed Introl’s allegation. The FAA concluded that the engines specified by Essex were noncomplaint, determined that the Forster and Essex bids were nonresponsive and that Introl’s was responsive, and so advised the GAO. These decisions sparked Forster’s protest. Essex appeared before the GAO as an interested party.

On June 9, 1983, the GAO issued its decision upholding Introl’s protest, denying Forster’s, and declaring Introl responsive and both Forster and Essex nonresponsive. Introl Corp., B-209096, 83-1 C.P.D. ¶ 633 (June 9, 1983) [hereinafter “Introl GAO decision”]. In addition to basing its rejection of Essex on the nonresponsiveness of the Cummins engine, the GAO agreed with the FAA that the descriptive literature on the Allis-Chalmers engine indicating normal operation at 1800 rpm and the need for modifications to enable operation at 1200 rpm rendered Essex’s bid nonresponsive. Essex’s evidence supporting compliance was not considered, “because a contracting agency’s determination whether a product offered by a bidder meets the solicitation specifications must be based on the data submitted with the bid.... ” Introl GAO decision at 6 (citation omitted). Moreover, according to the GAO, Essex’s bid as to the output of the Allis-Chalmers engine was ambiguous based on literature submitted and, thus, nonresponsive. Introl’s bid was deemed responsive based, in part, on descriptive literature submitted after Forster protested that the General Motors engine did not operate at 1200 rpm.

Relying on the GAO decision, the contracting officer recommended award of the contract to Introl. The FAA’s Procurement Review Board concurred.

After the Introl GAO decision, Forster unsuccessfully sought in this court to enjoin issuance of the contract to Introl and to mandate an award in its favor. Forster Enterprises v. United States, No. 443-83C (Cl.Ct. July 21, 1983) (HARKINS, J.). In the interim Essex had submitted a request for reconsideration of the GAO decision. Upon the filing of Essex’s suit in this court, a call was issued on the GAO to render its decision on reconsideration prior to the hearing on the preliminary injunction. GAO did not respond to the call. At argument defendant asked the court to consider GAO’s June 9, 1983 decision as final.

DISCUSSION

The rejection of Essex’s bid as non-responsive should not be overturned unless no rational basis exists for the agency’s determination. Harris Data Communications, Inc. v. United States, 2 Cl.Ct. 229, 237 (1983) (NETTESHEIM, J.), affirmed, 723 F.2d 69 (Fed.Cir.1983) (citing M. Steinthal & Co. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Red River Communications, Inc. v. United States
109 Fed. Cl. 497 (Federal Claims, 2013)
Dellew Corp. v. United States
108 Fed. Cl. 357 (Federal Claims, 2012)
Sierra Nevada Corp. v. United States
107 Fed. Cl. 735 (Federal Claims, 2012)
Contracting, Consulting, Engineering LLC v. United States
104 Fed. Cl. 334 (Federal Claims, 2012)
Acrow Corp. of America v. United States
97 Fed. Cl. 161 (Federal Claims, 2011)
Office Depot, Inc. v. United States
95 Fed. Cl. 517 (Federal Claims, 2010)
Global Computer Enterprises, Inc. v. United States
88 Fed. Cl. 350 (Federal Claims, 2009)
Gear Wizzard, Inc. v. United States
87 Fed. Cl. 218 (Federal Claims, 2009)
Totolo/King v. United States
87 Fed. Cl. 680 (Federal Claims, 2009)
ViroMed Laboratories, Inc. v. United States
87 Fed. Cl. 493 (Federal Claims, 2009)
RhinoCorps Ltd. v. United States
87 Fed. Cl. 673 (Federal Claims, 2009)
Wackenhut Services, Inc. v. United States
85 Fed. Cl. 273 (Federal Claims, 2008)
Dyonyx, L.P. v. United States
83 Fed. Cl. 460 (Federal Claims, 2008)
Information Sciences Corp. v. United States
80 Fed. Cl. 759 (Federal Claims, 2008)
Axiom Resource Management, Inc. v. United States
80 Fed. Cl. 530 (Federal Claims, 2008)
Erinys Iraq Ltd. v. United States
78 Fed. Cl. 518 (Federal Claims, 2007)
Textron, Inc. v. United States
74 Fed. Cl. 277 (Federal Claims, 2006)
Blue & Gold Fleet, LP v. United States
70 Fed. Cl. 487 (Federal Claims, 2006)
Group Seven Associates, LLC v. United States
68 Fed. Cl. 28 (Federal Claims, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
31 Cont. Cas. Fed. 71,391, 3 Cl. Ct. 277, 1983 U.S. Claims LEXIS 1652, Counsel Stack Legal Research, https://law.counselstack.com/opinion/essex-electro-engineers-inc-v-united-states-cc-1983.