HENRY SPEN & CO., INC. v. Laird

354 F. Supp. 586, 1973 U.S. Dist. LEXIS 14963
CourtDistrict Court, District of Columbia
DecidedFebruary 10, 1973
DocketCiv. A. 50-73
StatusPublished
Cited by2 cases

This text of 354 F. Supp. 586 (HENRY SPEN & CO., INC. v. Laird) is published on Counsel Stack Legal Research, covering District Court, District of Columbia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
HENRY SPEN & CO., INC. v. Laird, 354 F. Supp. 586, 1973 U.S. Dist. LEXIS 14963 (D.D.C. 1973).

Opinion

MEMORANDUM-ORDER

GASCH, District Judge.

This case came on for consideration on the plaintiff’s verified complaint, its motions for a preliminary injunction and cross-motion for partial summary judgment, the defendant’s motion for summary judgment, points and authorities and exhibits filed by both parties, and argument by counsel in open Court.

There is no dispute about the material facts in this case. Briefly, they are as follows. On April 21, 1972, the Defense Supply Agency, Defense Construction Supply Center (hereafter called agency) issued an invitation for bids on a contract for supply of certain items of lubrication maintenance equipment (IFB No. DSA700-72-B-2207). Bids were to be opened at 10:30 A.M., June 6, 1972. On June 2, Henry Spen & Co. (Spen), a New York corporation with a large portion of its business in government supply contracts, 1 submitted a bid in which it offered to supply 67 production units (items 1-4) at $6,000 per unit and a pre-production model with related testing and data (item 5) at a total price of $12,500. 2 At the time it compiled that bid, Spen was without current information from some of its suppliers; it arrived at its $6,000 figure for each production unit by using figures for components from a similar bid package compiled in 1968 and increasing that amount by 25 percent to allow for price increases since that time. On June 5, Spen reviewed its bid, partly in the light of more current information received from suppliers. Spen thereupon discovered that its bid was unduly low. In particular, it discovered that its per-unit figure for the production units did not include crating costs or costs of certain other components, and that it should be $7,982 per unit rather than $6,000 each. Regarding item 5, it found that the cost of the pre-production model to be delivered and labor costs for an additional 200 hours of needed testing were omitted; accordingly, it determined that its bid as to that item should be increased by $9,437 to a total of $21,937. At 5:44 that afternoon Spen dispatched a telegram, to be sent from the New York office of Western Union. 3 Although Western Union’s records in Brooklyn, New York, show that the telegram was sent to the designated bid-opening location, the Western Union office in Columbus, Ohio, has no record of its being received there. Western Union has been unable to explain the transmission failure. When bids were opened on June 6, Spen’s was the lowest of the four submitted. Because the • Spen bid of $6,000 each on the production units seemed unusually low in comparison to bids submitted by the three other bidders and because of some misalignments of prices in the bid, the contracting officer called Spen, pursuant to a provision of the Armed Services Procurement Regulations (ASPR), 32 C.F.R. § 2.-406-1, to request verification of the bid. At that time the agency learned about the dispatch of the June 5 telegram and Spen discovered that the telegram had not been received.

Although both its June 2 bid and its bid as increased by the June 5 telegram were lower than any of the three other *588 bids submitted, Spen saw fit to protect itself from award of the contract to another bidder by filing a protest with the Comptroller General on July 10, 1972; in its protest it contended that it should be awarded the contract on the basis of its June 2 bid as corrected by the June 5 telegram. In the meantime, the agency’s Contracting Officer was reviewing the matter, and on August 2 he determined that Spen had not made a mistake as to item 5 and so should not be permitted to increase its bid on that item, but that there was clear and convincing evidence that the per-unit bid of $6,000 for items 1-4, the 67 production units, was a mistake. Hence the agency was willing to allow correction of the price on items 1-4. Spen thereupon sought to withdraw its protest from the Comptroller General's office, with the exception of that portion concerned with item 5, the issue which the Contracting Officer had decided against Spen. The Comptroller General nevertheless considered the entire bid and issued an opinion on December 29, 1972 (No. B-176326), holding that there was no basis for allowing correction of any part of the June 2 bid, although the agency could properly permit Spen to withdraw the bid.

Whether the Comptroller General had “jurisdiction” to decide the question which the protestant sought to withdraw from consideration on appeal 'is not at issue here. An affidavit by the Chief of the Procurement Division with the Defense Supply Agency states that the Agency has not felt itself bound by the Comptroller General in this matter but has simply been persuaded by his reasoning to change its position (See Defendants’ Exhibit 1). It is clearly entitled to do so under case law of this Circuit. A. G. Schoonmaker Co., Inc., et al. v. Resor, 144 U.S.App.D.C. 250, 445 F.2d 726 (1971). Since the agency has been persuaded by the Comptroller General’s opinion to change its position, it is essentially that opinion which is to be tested here. The standard of review is the normal one for agency action: this Court will not set aside the decision unless it finds it to be arbitrary or capricious. M. Steinthal & Co. v. Seamans, 147 U.S.App.D.C. 221, 231, 455 F.2d 1289, 1298 (1971).

At the outset it should be determined whether the June 5 telegram can qualify under the regulations as an effective late bid modification, an issue which plaintiff raised in the memorandum accompanying its Motion for Preliminary Injunction. According to ASPR §§ 2.303-4, a telegraphic bid modification received after bid opening and before award cannot be considered for award “regardless of the cause of the late receipt, including delays caused by the telegraph company, except for delays due to mishandling on the part of the government in its transmittal to the office designated in its invitation for bids. . . . ” 4 It is clear to the Court that the June 5 telegram does not qualify as a late bid modification, and that the agency was thus correct in proceeding under the regulations governing mistakes in bids.

The applicable regulation is ASPR § 2.406-3, “Other Mistakes” (meaning mistakes other than “apparent clerical mistakes,” which are governed by ASPR § 2.406-2). Subsection (3) of that regulation is as follows:

(3) Where the bidder requests permission to correct a mistake in his bid and clear and convincing evidence establishes both the existence of a mistake and the bid actually intended, a determination permitting the bidder to correct the mistake may be made; provided that, in the event such correction would result in displacing one or more lower bids, the determination shall not be made unless the existence of the mistake and the bid actually intended are ascertainable substantially from the invitation and the *589 bid itself.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Essex Electro Engineers, Inc. v. United States
31 Cont. Cas. Fed. 71,391 (Court of Claims, 1983)
Vibra-Tech Engineers, Inc. v. United States
567 F. Supp. 484 (D. Colorado, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
354 F. Supp. 586, 1973 U.S. Dist. LEXIS 14963, Counsel Stack Legal Research, https://law.counselstack.com/opinion/henry-spen-co-inc-v-laird-dcd-1973.