M. Steinthal & Co., Inc. v. Robert J. Seamans, Jr., Secretary of the Air Force, Pioneer Parachute Co., Inc.

455 F.2d 1289, 147 U.S. App. D.C. 221
CourtCourt of Appeals for the D.C. Circuit
DecidedOctober 14, 1971
Docket24595
StatusPublished
Cited by534 cases

This text of 455 F.2d 1289 (M. Steinthal & Co., Inc. v. Robert J. Seamans, Jr., Secretary of the Air Force, Pioneer Parachute Co., Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
M. Steinthal & Co., Inc. v. Robert J. Seamans, Jr., Secretary of the Air Force, Pioneer Parachute Co., Inc., 455 F.2d 1289, 147 U.S. App. D.C. 221 (D.C. Cir. 1971).

Opinion

LEVENTHAL, Circuit Judge:

This case involves a protest by a bidder for a government contract. Plaintiff-appellee Steinthal & Co. contests a determination by the Air Force rejecting what Steinthal alleges was the lowest bid on a contract to supply parachutes and directing a readvertisement of bids. The District Court granted a permanent injunction restraining the Secretary of the Air Force from opening bids submitted pursuant to the readvertisement and from awarding a contract for the parachutes to any bidder other than Stein-thal. At the oral argument, on the application of intervenor-appellant Pioneer Parachute Co. for a stay pending appeal, the parties agreed that this court could proceed to dispose of the merits of the appeal. In view of the urgency of the situation, we issued an order within a few days after oral argument, reversing the ruling of the District Court and dissolving the permanent injunction in order to allow the Air Force to open the resolicited bids and to award a contract for the parachutes.

In Scanwell Laboratories, Inc., v. Shaffer 1 we held that a bidder for a government contract had standing under the Administrative Procedure Act to obtain judicial consideration of a claim of illegality in the award of the contract to another. 2 In this opinion we consider the approach that is appropriate when an action under Scanwell, claiming that pro *1292 curement officials have acted arbitrarily or capriciously, confronts the court with technical and complex issues of interpretation of procurement regulations. It is being issued simultaneously with the opinion in Wheelabrator Corp. v. Chafee, #24705, 147 U.S.App.D.C.-, 455 F.2d 1306, which involves related considerations.

I. THE PRESENT CONTROVERSY

A. The Background

On May 1, 1970, the Secretary of the Air Force, Robert Seamans (appellee), issued an invitation for bids [IFB#1] through the Department of Procurement and Production [DP&P], Kelly Air Force Base, San Antonio, Texas. The IFB covered a contract involving the production and delivery of 1040 parachutes. 3 The delivery schedule of IFB#1 4 provided:

Part III Desired Delivery
Delivery is desired as follows:
140 Days 170 Days 200 Days
40 40 80 and continue at the rate of 80 each per month thereafter

This schedule was made subject to a slippage provision:

If the bidder is unable to meet the above delivery schedule, he may, without prejudice to the evaluation of his bid, set forth below the delivery schedule he is prepared to meet, provided, in no event shall the bidder’s delivery schedule [extend beyond 30 days], af--ter completion date of each increment specified above, as bids proposing .delivery after that period will be eon-sidered nonresponsive to the invitation and will be rejected. If the bidder does not state a different delivery schedule, the Government’s desired delivery schedule will apply.

The brackets surrounding the phrase “extend beyond 30 days” were not in slippage clause as issued. They have been used to signify the fact that this phrase was deleted by an amendment issued June 1 [amended IFB]. This amendment also revised the delivery schedule by providing that the first shipment 5 would be due 120 days after the award. The bid opening was extended from June 2 to June 30 in order, as the record shows, 6 to allow a third manufacturer to qualify for the bidding by satisfying the Air Force’s requirements.

The intention of those drafting the amendment of the slippage clause, as the record indicates, was to respond to the delay occasioned by the deferral of the opening of bids from June 2 to June 30, and to the need of the buyer for the first 40 parachutes by January 15, 1971, by deleting the entire slippage provision. The intent was to provide for a mandatory schedule of delivery of the parachutes.

Although none of the prospective bidders questioned the provisions of the amended IFB, each of the three bids opened on June 30 reflected a different interpretation of its provisions. Pioneer Parachute Co., Inc., interpreted the amended IFB to establish a required delivery of the first shipment of parachutes within the stated 120 day period. M. Steinthal and Co. concluded that the amendment called for a desired, delivery schedule and submitted a bid providing *1293 for delivery within 150 days of the award. A third bidder’s response provided for initial delivery within 170 days of the award.

The third bidder specified the lowest price, but its parachute did not meet specifications. Steinthal’s price was lower than Pioneer’s, but Pioneer protested the award of the contract to Steinthal contending that Pioneer had submitted the only bid responsive to the delivery schedule in the amended IFB.

Pioneer’s protest was originally considered by Joseph R. Blazi, the Contract-ting Officer at Kelly Air Force Base. 7 On July 8 he issued a Statement of Facts and Findings in which he denied the protest and recommended award of the contract to Steinthal. Mr. Blazi found that the deletion of “extend beyond 30 days” rendered the amended IFB “subject to two possible interpretations”: (a) as specifying a mandatory schedule; however he noted that this ignored the presence of “desired” in the delivery schedule, and the absence of “required.” (b) as providing a desired delivery schedule, with delivery required only within a reasonable time after the desired date. His' analysis, set forth in the footnote, 8 culminated in the opinion that the second construction should be adopted, although he expressly concluded that he found it impossible to state whether this interpretation advanced by Steinthal was more sound than Pioneer’s “mandatory” interpretation and he could “only conclude that neither interpretation is superior to the other.” He recommended award of the contract to Steinthal since he found that directing a readvertisement of bids after opening would cause substantial prejudice to Steinthal but would only slightly disadvantage Pioneer because, as he found on the basis of his experience with these contractors, Pioneer’s bid would not have been lower even if it had proposed the same delivery schedule as Steinthal. 9

*1294 This Statement of Facts and Findings was then submitted by the contracting officer to Air Force Logistics Command at Dayton, Ohio (HQ, AFLC). 10 Subsequently, he received a list of Comments

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
455 F.2d 1289, 147 U.S. App. D.C. 221, Counsel Stack Legal Research, https://law.counselstack.com/opinion/m-steinthal-co-inc-v-robert-j-seamans-jr-secretary-of-the-air-cadc-1971.