Clark Const. Co., Inc. v. Pena

895 F. Supp. 1483, 1995 U.S. Dist. LEXIS 10905, 1995 WL 457844
District Court, M.D. Alabama·Decided June 26, 1995·No. Civ. A. 95-D-447-N·Published·Cited by 4 cases

Opinion

MEMORANDUM OPINION

DE ME NT, District Judge.

BACKGROUND

Before the court is plaintiff Clark Construction Company, Inc.’s (hereafter “Clark Construction”) motion for preliminary injunction filed March 30,1995. The plaintiff seeks to enjoin the Federal Highway Administration (hereafter “FHWA”), the U.S. Department of Transportation (hereafter U.S. DOT), and the Alabama Department of Transportation (hereafter ADOT) from depriving it of a construction contract which the State of Alabama originally proposed to award Clark Construction. The plaintiffs low bid was rejected by the FHWA after the agency discovered that the project plans and specifications that it approved and submitted to prospective bidders contained an error relating to a traffic control note. Upon discovering the omitted term, the FHWA directed ADOT to reject all of the then public bids and solicit bids a second time. Two bids, one of which belonged to the plaintiff, were submitted in the second let. Both bids were significantly lower than the bids submitted in the first let, notwithstanding the fact that the previously omitted traffic control note appeared to increase the cost of the project in the view of the FHWA. The plaintiff was underbid in the second let by its competitor APAC Construction and presently, ADOT has requested that the FHWA concur in the proposed award to APAC. The plaintiff seeks in its motion for preliminary injunction to prevent the FHWA from concurring in the proposed award to APAC. Furthermore, the plaintiff has asked in its complaint that this court direct the defendants to recognize the plaintiffs original low bid as the only lawfully obtained low bid and award the construction contract accordingly. In support of its motion, the plaintiff asserts that the defendants had no statutory or legal authority to reject the originally proposed award based on an insignificant mistake that the parties agree was entirely the fault of the defendants. Furthermore, the plaintiff argues that the defendants’ decisions with respect to the proposed award were both arbitrary and capricious.

On May 22,1995, the court held an eviden-tiary hearing on the plaintiffs motion for preliminary injunction, the transcript of which is a part of the record. Subsequent to that hearing, the parties were given the opportunity to file additional briefs in support of, and in opposition to, the plaintiffs motion. After careful consideration of the record as a whole and the applicable law, the court finds that the plaintiffs motion for preliminary injunction is due to be granted.

JURISDICTION AND VENUE

This is an action arising under the United States Constitution, the Administrative Procedure Act, 5 U.S.C. §§ 551 et seq. and the Federal Highway Act, 23 U.S.C. §§ 101 et seq. Subject matter jurisdiction is proper pursuant to 28 U.S.C. § 1331. Venue is properly founded upon 5 U.S.C. § 8912 and 28 U.S.C. § 1391(e).

STANDING

The plaintiffs legal standing to appeal the actions of the respective agency defendants lies in the Administrative Procedure Act. Section 702 of that Act provides that “[a] person suffering legal wrong because of agency action, or adversely affected or aggrieved by agency action within the meaning of a relevant statute, is entitled to judicial review” thereof. The court finds that the plaintiff, as an unsuccessful bidder, has standing to challenge the defendants’ proposed plan to award the contract to a third party. See Choctaw Mfg. Co., Inc. v. United States, 761 F.2d 609 (11th Cir.1985).

FINDINGS OF FACT 1

The construction contract in question arose out of a Federal Aid Project operating under *1487 the Federal Highway Act. 2 The project involves a joint effort by the FHWA and the State of Alabama to widen a portion of U.S. Highway 280, which is located in Jefferson County, Alabama. The terms of the State and Federal relationship in this matter are set forth in an operating agreement generated by the FHWA and the State of Alabama. The “Agreement” incorporates the statutory and regulatory requirements set forth in the Federal Highway Act and the Intermodal Surface Transportation Efficiency Act of 1991.

Under the law incorporated in the above mentioned Agreement, the State is required to prepare a document setting forth the specifications of the project. 3 The document itself is referred to as the Plans, Specifications & Estimates or “PS & E”. The PS & E’s specific purpose is to describe the location and design features and the construction requirements in sufficient detail so as to facilitate construction, contract control, and the estimation of construction costs. 23 C.F.R. § 630.205(b). Upon completion, the PS & E is submitted to the Division Administrator of the FHWA for approval. 23 C.F.R. § 630.205(e). The State’s plan must be approved by the FHWA before the State will be allowed to proceed with soliciting bids. 4 Upon approval of the plan, the State may then begin the sealed-bidding process used to select a contractor. The Federal Highway Act provides that a contract be “awarded only on the basis of the lowest responsive bid submitted by a bidder meeting the criteria for responsibility as may have been established by the SHA. [Applicable State Highway Authority] in accordance with Section 635.110.” 5

In the present case, ADOT and the FHWA spent a considerable amount of time discussing the construction specifications which would be included in the ADOT PS & E. One of the points that was discussed and eventually agreed upon related to the project “construction sequence.” Among other things, the construction sequence in this PS & E was to include a note limiting when traffic lanes could be closed for construction work. Both the FHWA and ADOT agreed that the note would alert prospective bidders that traffic lanes could not be closed from 6:30 a.m. to 7:00 p.m. on weekdays. Apart from that restriction, lane closures were to be permitted for construction purposes on weeknights and weekends.

Notwithstanding the Agencies agreement as to that particular note, the PS & E that was ultimately drafted by ADOT and submitted to the FHWA for approval did not contain the above mentioned restriction. Instead, the PS & E traffic control note simply prohibited lane closures on weekdays from 6:30 a.m. to 8:30 a.m. and from 3:30 p.m. to 6:30 p.m.

Free access — add to your briefcase to read the full text and ask questions with AI

Clark Const. Co., Inc. v. Pena, 895 F. Supp. 1483, 1995 U.S. Dist. LEXIS 10905, 1995 WL 457844 (M.D. Ala. 1995).

895 F. Supp. 1483 (Clark Const. Co., Inc. v. Pena) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Intergraph Corp. v. Intel Corp.
3 F. Supp. 2d 1255 (N.D. Alabama, 1998)
Clark Pacific v. Krump Construction, Inc.
942 F. Supp. 1324 (D. Nevada, 1996)
Clark Const. Co., Inc. v. Pena
930 F. Supp. 1470 (M.D. Alabama, 1996)