Clark Pacific v. Krump Construction, Inc.

942 F. Supp. 1324, 1996 U.S. Dist. LEXIS 16104, 1996 WL 617325
CourtDistrict Court, D. Nevada
DecidedOctober 15, 1996
DocketCV-N-96-0576-ECR
StatusPublished
Cited by2 cases

This text of 942 F. Supp. 1324 (Clark Pacific v. Krump Construction, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Nevada primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Clark Pacific v. Krump Construction, Inc., 942 F. Supp. 1324, 1996 U.S. Dist. LEXIS 16104, 1996 WL 617325 (D. Nev. 1996).

Opinion

ORDER

EDWARD C. REED, Jr., District Judge. Introduction

This is a dispute between Clark Pacific, a construction subcontractor on a public works project, Krump Construction, the general contractor, and Mr. Eric Raecke, Manager of the Nevada Public Works Board, which is responsible for awarding public works contracts in this State. Presently before the court for decision is Plaintiff Clark Pacific’s Motion for Preliminary Injunction (Doc. # 4). The court previously, by Order dated September 19, 1996 (Doc. # 10), issued a temporary restraining order against Defendants Krump Construction and Nevada Public Works Board Manager Erie Raecke, pending a hearing on the motion for preliminary injunction. The parties presented extensive evidence and argument at a hearing which commenced October 1, 1996 and concluded October 10, 1996. Having heard that evidence, and the parties’ arguments, the court is now prepared to issue its ruling on the motion for preliminary injunction.

Plaintiff Clark Pacific alleges both federal question and diversity jurisdiction. 28 U.S.C. §§ 1331, 1332. Clark Pacific claims that Defendants’ substitution of another construction subcontractor in its place violates its right under the Fourteenth Amendment to the United States Constitution not to be deprived of property without due process of law. Clark Pacific also claims a violation of its right under a Nevada statute not to be replaced as a public works construction subcontractor absent the existence of specific circumstances set out in that statute, and, as a citizen of California, invokes the court’s diversity jurisdiction over its suit against Krump, a Nevada corporation, and Eric Raecke, a Nevada public employee.

I. Facts

From the evidence adduced to date, the court makes the following findings of fact:

In May and June of 1996 the Nevada Public Works Board solicited bids for construction work to be performed at one of Nevada’s prisons, the Lovelock Correctional Center. The State planned additions to the Correctional Center consisting of new prisoner housing facilities and some modifications to the prison industries building. Only two companies bid for the prime contract; one was Clark & Sullivan, the other was Defendant Krump Construction. Under the terms of the solicitation documents, bids were to be submitted sealed, to be opened at two o’clock on the afternoon of June 18,1996 (“bid day”).

Clark Pacific, a California-based pre-cast concrete subcontractor, prepared a written *1328 bid to perform the design, manufacture, erection, alignment, welding and grouting of architectural precast concrete sandwich wall panels, interior walls, chases, floor and ceiling slabs, beams and columns for the three new prisoner housing units at Lovelock Correction Center. Early on the morning of June 18, Clark Pacific transmitted its bid form by electronic facsimile to Krump Construction and to Clark & Sullivan, omitting Clark Pacific’s base price. Such is standard practice in the construction industry: Bidders on public works subcontracts withhold their base price almost until the last minute, in order to give the general contractor no pre-bid-time opportunity to “shop” the subcontractors’ numbers to other subcontractors in the hope of obtaining a lower price.

Clark Pacific’s bid form was transmitted to Krump at 7:23 a.m. on bid day, June 18,1996. The Clark Pacific bid contained a number of qualifications and conditions including, of particular importance,

(1) the duration of the work to be performed by Clark Pacific. Clark Pacific’s bid contemplated a period of 125 days between the issuance by Krump of its “notice to proceed” and the commencement by Clark Pacific of precast concrete panel erection, and a period of 100 days for Clark Pacific to achieve “substantial completion” of its portion of the project;
(2) a requirement that the General Contractor provide 440-volt electrical power to the construction site for the welding together of the precast concrete panels;
(3) a requirement that the General Contractor provide and maintain all-weather access roads to the construction site;
(4) a requirement that the General Contractor provide “deadmen,” which are large concrete blocks designed to support temporarily the precast concrete panels until they can be welded into position.

During- the morning of June 18, 1996, Mark Robison, Clark Pacific’s Project Manager, phoned Rusty Heberger, Krump’s Project Manager, to confirm that Krump had received and reviewed Clark Pacific’s bid. Mr. Heberger told Mr. Robison that he had received the bid but had not yet reviewed it. Later the same morning Mr. Heberger telephoned Mr. Robison

(1) to determine the size of the deadmen required by Clark Pacific,
(2) to ascertain the number of coil rods required,
(3) to inquire whether Clark Pacific would stop work if progress payments were late,
(4) to discuss the liquidated damages provision of Clark Pacific’s bid,
(5) confer regarding Clark Pacific’s requirement that Krump provide electrical power for the welding, and
(6) to establish the maximum allowable markup to which Clark Pacific would be entitled on any orders changing the specifications on any portion" of Clark Pacific’s scope of work.

Mr. Robison advised Mr. Heberger that about 10,000 coil rods were needed, that he needed time to calculate the size of the dead-men, and that the maximum markup on change orders would be fifteen per cent.

At 11:34 a.m. Mr. Robison telephoned Mr. Heberger and informed him that he did not yet have the dimensions of the required deadmen, and further advised him that the provision by Clark Pacific of electrical welding power would add $20,000 to Clark Pacific’s base price.

At 1:14 p.m. Mr. Robison again telephoned Mr. Heberger and advised him that Clark Pacific would reduce the number of deadmen required from 500 to 300, and that Clark Pacific required three cubic yard deadmen for exterior walls and one cubic yard dead-men for interior walls. Mr. Robison then indicated to Mr. Heberger that Clark Pacific was adding a ninth “special condition” to its bid form. Special Condition No. 9 required the General Contractor to provide temporary heat at a minimum of fifty degrees Fahrenheit to allow proper curing of the grout used to join the precast concrete panels. This condition was designed to address the problem of pouring concrete in cold weather: Winters in Lovelock, Nevada, are bitter cold, *1329 too cold for concrete or grout to cure properly. The wet grout must be kept warm after it is applied to the joints between the precast panels, either by applying hot blankets to the surface of the material, or by heating the surrounding air. Mr. Robison read Special Condition No. 9 to Mr. Heberger and asked him to note it on the bid form, which Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Randazza v. Cox
920 F. Supp. 2d 1151 (D. Nevada, 2013)
City of Boulder City v. Boulder Excavating, Inc.
191 P.3d 1175 (Nevada Supreme Court, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
942 F. Supp. 1324, 1996 U.S. Dist. LEXIS 16104, 1996 WL 617325, Counsel Stack Legal Research, https://law.counselstack.com/opinion/clark-pacific-v-krump-construction-inc-nvd-1996.