Glenwood Bridge, Inc. v. City of Minneapolis John Doe John Smith Other Known Entities and Individuals

940 F.2d 367
Court of Appeals for the Eighth Circuit·Decided October 31, 1991·No. 91-1442·Published·Cited by 98 cases

Opinions

BEAM, Circuit Judge.

Glenwood Bridge, a Minnesota bridge-builder, appeals from the district court’s order of March 7, 1991, denying its motion for a preliminary injunction. Glenwood Bridge seeks to restrain the City of Minneapolis from rejecting its low bid on the Fifth Street North Bridge Project and awarding the contract, after rebidding, to another contractor. The City’s actions may or may not violate federal labor law. We think that Glenwood Bridge has shown a sufficient likelihood of success on the merits, however, that, together with a showing of irreparable harm, makes it entitled to preliminary relief. Accordingly, we reverse the judgment of the district court.

I. BACKGROUND

On December 5,1990, the City advertised for bids to build a new Fifth Street bridge. Glenwood Bridge submitted a bid which, when the bids were opened on January 22, 1991, proved to be low. Nine days later, however, the City’s purchasing department, in a letter to the chairman of the city council’s transportation and public works committee, suggested that the city council reject all bids. As the letter-writer explained, “After reviewing the bids, it was determined that there was no project labor agreement in place for this bid.” Letter from Richard L. Straub to Tony Scallon [368]*368(Jan. 31, 1991). The City claims that its review of the original bidding documents convinced it that without a labor stabilization agreement, the project might not be completed by November 15, 1991, in time for the holiday shopping season. Accordingly, the director of public works “recommended that we obtain a project labor agreement and ensure against any ... strikes or lockouts.” Id.

When Glenwood Bridge was made aware of the City’s concerns, it notified the City that its collective bargaining agreement with its union, the Christian Laborers Association Local No. 78 (CLA), an NLRB-certified labor organization, contained a no strike/no lockout clause. The city attorney advised the transportation and public works committee that this agreement was not good enough. “We have reviewed the Agreement and it is our opinion that it is not the kind of labor agreement which would protect the City from both strikes and lockouts.” Letter from Robert J. Alf-ton to Tony Scallon (Feb. 7,1991). The city attorney’s letter specified no reasons why the agreement was insufficient. Indeed, Glenwood Bridge was later advised that its contract with the CLA providing for no strikes or lockouts would satisfy the City’s concerns. See Transcript of Hearing on Motion for Preliminary Injunction at 9 (March 6, 1991) (Hearing Transcript).

Glenwood Bridge was so advised, however, only after the city council rejected all bids on February 8, 1991, and voted to readvertise the project. The City determined that it could best avoid strikes or lockouts by executing its authority under a Minnesota statute permitting the City to “enter into agreements ... with appropriate labor organizations and contractors which provide that no strike or lockout may be ordered during the term of the agreements.” 1989 Minn.Sess.Law Serv. Ch. 54, sec. 2 (West). Accordingly, the City entered into a project labor stabilization agreement with the Minneapolis Building and Construction Trades Council, AFL-CIO, which provides for no strikes or lockouts. The City then incorporated this agreement into its new bidding documents.

Glenwood Bridge did not submit a new bid, but instead filed this action in federal district court on February 13, 1991, alleging that the City’s actions were preempted by federal labor law, and seeking damages and declaratory and injunctive relief. Specifically, Glenwood Bridge asked the court to prohibit the City from readvertising for bids and from incorporating the AFL-CIO labor stabilization agreement into the new bidding documents. Glenwood Bridge also asked the court to mandate that the City award it the bridge contract under its original bid. On February 15, Glenwood Bridge filed a motion for a temporary restraining order.

The district court granted, in part, the motion for temporary restraining order on February 21, 1991. In its order, the district court allowed the City to readvertise the project and to receive new bids, but “restrained and enjoined [the City] from opening the bids submitted in response to its readvertisement for bids.” Glenwood Bridge v. City of Minneapolis, Civ. No. 3-91-85, Temporary Restraining Order (Feb. 21, 1991).1 The district court considered preliminary injunctive relief at a hearing on March 6, 1991, at which hearing the court concluded that it did not have the authority under Minnesota law to “order the City to award the contract to Glen-wood.” Hearing Transcript at 13. Because it could not award the contract, “a preliminary injunction [preserving the status quo until the matter is resolved would therefore be of no point.” Id. Thus, the district court denied the motion for preliminary injunction on March 7, but extended the temporary restraining order until 9:00 a.m. on March 11. Glenwood Bridge v. City of Minneapolis, Civ. No. 3-91-85, Or[369]*369der (March 7, 1991). Glenwood Bridge appealed from the district court’s order to this court on March 7. We extended, on March 8, the temporary restraining order pending appeal and heard oral argument on March 13, 1991. After argument, on March 27, the City filed a motion to modify the temporary restraining order to allow demolition of the existing bridge.

On May 10, 1991, we filed an opinion affirming the district court’s denial of Glenwood Bridge’s motion for a preliminary injunction, vacating our earlier order extending the temporary restraining order pending appeal, and denying as moot the City’s motion to modify the temporary restraining order. 932 F.2d 1239 On May 17, 1991, Glenwood Bridge filed a petition for rehearing with suggestion for rehearing en banc and a motion seeking an injunction to prohibit the City from either awarding the contract or beginning work on the project pending disposition of the petition for rehearing. By order of May 20, 1991, we issued an injunction “prohibiting [the City] from awarding the contract at issue and/or commencing work on the project contract until disposition of [Glenwood Bridge’s] motion for rehearing and the suggestion for rehearing en banc.” On May 23, 1991, the City filed a motion to increase the amount of the bond filed by Glenwood Bridge, and to allow the City to demolish the existing Fifth Street Bridge with its own forces. By order of May 28, 1991, we modified our May 20 injunction to do these things. Now, by this opinion, we grant rehearing by the panel, vacate the May 10 panel opinion, and substitute this opinion reversing the judgment of the district court.

II. DISCUSSION

We review the district court’s denial of injunctive relief for abuse of discretion. Modem Computer Sys. v. Modem Banking Sys., 871 F.2d 734, 737 (8th Cir.1989) (en banc) (“Unless the district court’s denial of injunctive relief is the product of an abuse of discretion or misplaced reliance on an erroneous legal premise, we may not reverse on appeal.”).

Free access — add to your briefcase to read the full text and ask questions with AI

Glenwood Bridge, Inc. v. City of Minneapolis John Doe John Smith Other Known Entities and Individuals, 940 F.2d 367 (8th Cir. 1991).

940 F.2d 367 (Glenwood Bridge, Inc. v. City of Minneapolis John Doe John Smith Other Known Entities and Individuals) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related