Mark Dunning Industries, Inc. v. Cheney

726 F. Supp. 810, 36 Cont. Cas. Fed. 75,886, 1989 U.S. Dist. LEXIS 14591, 1989 WL 147781
CourtDistrict Court, M.D. Alabama
DecidedNovember 7, 1989
DocketCiv. A. 89-T-1116-S
StatusPublished
Cited by10 cases

This text of 726 F. Supp. 810 (Mark Dunning Industries, Inc. v. Cheney) is published on Counsel Stack Legal Research, covering District Court, M.D. Alabama primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mark Dunning Industries, Inc. v. Cheney, 726 F. Supp. 810, 36 Cont. Cas. Fed. 75,886, 1989 U.S. Dist. LEXIS 14591, 1989 WL 147781 (M.D. Ala. 1989).

Opinion

MEMORANDUM OPINION

MYRON H. THOMPSON, District Judge.

In this lawsuit, plaintiff Mark Dunning Industries, Inc., challenges the termination of its refuse collection and waste disposal contract awarded by the United States Army, and the award of that contract to another bidder. The company has sued the following federal officials: the Secretary of Defense, the Secretary of the Army, and the Army Contracting Officer for Fort Polk, Louisiana. Based on the evidence and briefs submitted by the parties, the court finds that it is without jurisdiction to consider Mark Dunning’s challenge to the termination of its contract but that it does have jurisdiction over the company’s challenge to the award of the contract to another bidder. The court further finds that the award of the contract to another bidder was improper, and that appropriate relief is therefore in order. 1

I.

In October 1988, the contracting officer for the United States Army invited bids on a contract for refuse collection and disposal on a federal installation at Fort Polk. Interested small businesses were allowed to submit bids on either or both of two arrangements for disposal of the waste: “Schedule I” required that the disposal of the waste be on a government-owned, on-site landfill; and “Schedule II” required that the disposal be off the post on lands provided by the bidder. Schedule I further required that each bidder include in its bid price the cost of “covering” and “turfing” portions of the Fort Polk landfill that had been left unturfed by a previous contractor; these costs were not included in Schedule II. Reliable Trash Service Company of Maryland, Inc., was the lowest bidder on Schedule I, and Mark Dunning was the lowest bidder on Schedule II. The Army found Mark Dunning’s bid to be the lowest overall and announced that it intended to award the contract to that company.

Reliable Trash protested to the Army contracting officer that the Army had improperly evaluated the bids by including the costs of corrective work on the landfill in Schedule I but not in Schedule II. The contracting officer denied the protest as untimely and awarded the contract to Mark Dunning.

Reliable Trash then filed a protest with the General Accounting Office (GAO). The GAO sustained the protest and recommended to the Army that it “terminate for convenience” Mark Dunning’s contract and award the contract to Reliable Trash. The GAO found that the untimeliness of the protest to the contracting officer did not bar consideration of the merits by the GAO because the issues were significant enough to warrant an exception under federal regulations. The GAO also stated that the corrective work on the landfill was “unrelated” to the other waste disposal work and that, as a result, bidders offering on-post disposal were placed at “an unjustified competitive disadvantage.” Furthermore, in denying Mark Dunning’s request for reconsideration, the GAO found that the company had “not established that it was prejudiced by the defective evaluation scheme,” because it had not indicated how it would have bid differently if the costs for correc *812 tive work had not been a part of Schedule 1. The Army followed the GAO’s recommendation; it terminated Mark Dunning’s contract and awarded it to Reliable Trash.

II.

Mark Dunning seeks to invoke the court’s jurisdiction under 28 U.S.C.A. § 1331, claiming that its dispute with the Army “arises under” the Armed Services Procurement Act, 10 U.S.C.A. § 2305, 2 and various federal regulations. Defendants contend that such jurisdiction is precluded by the Contract Disputes Act of 1978, 41 U.S.C.A. §§ 601-613, and the Tucker Act, 28 U.S.C.A. §§ 1346, 1491. These two acts specifically abolished the jurisdiction of the federal district courts to hear claims “founded upon any express or implied contract with the United States,” 28 U.S.C.A. § 1346(a)(2), and, instead, provided for review of government contract disputes by the Claims Court, 41 U.S.C.A. § 609(a)(1), or the applicable agency board of contract appeals. § 606. 3 Congressional intent to deprive the district courts of jurisdiction in contract cases is clear in the legislative history of the Act. “[The Contract Disputes Act] is amended by allowing contractors with suits against the Government (excluding the Tennessee Valley Authority) to bring direct action only in the Court of Claims. U.S. district court jurisdiction is eliminated from Government contract claims.” S.Rep. No. 1118, 95th Cong.2d Sess., reprinted in 1978 U.S.Code Cong. & Ad.News 5235, 5244. The essential question presented is whether Mark Dunning is asserting a claim as an unsuccessful bidder under the Armed Services Procurement Act, or whether its claim is a contractual dispute governed by the terms and jurisdictional provisions of the Contract Disputes Act and the Tucker Act.

In Alabama Rural Fire Insurance Co. v. Naylor, 530 F.2d 1221 (5th Cir.1976), the plaintiff had emerged as low bidder for a contract to provide backup insurance to the Farmers Home Administration (FmHA). 4 After awarding the contract to Alabama Rural, but before a formal contract was signed, the FmHA concluded that the contract should be rescinded because the terms of the federal statute under which Alabama Rural was incorporated did not authorize it to enter into the contract. The former Fifth Circuit held that Alabama Rural’s action for declaratory and injunctive relief to restrain the FmHA from rescinding the contract or soliciting new bids was clearly designed “to compel the appellants in their official capacities to specifically perform a contract.” Id. at 1226. As a result, the court held that, under the Tucker Act, Alabama Rural was limited to an action for damages in the Court of Claims.

Similarly, in Ingersoll-Rand Co. v. United States, 780 F.2d 74 (D.C.Cir.1985), the Air Force terminated a contract less than one month after awarding it to IngersollRand and began to resolicit bids. The Court of Appeals for the District of Columbia upheld the district court’s conclusion that it lacked subject matter jurisdiction over Ingersoll-Rand’s claims. The court stated:

[Ingersoll-Rand] is not a disappointed bidder who seeks to void the award of a contract to another; instead, it complains of wrongful termination of its own contract with the government.

Id. at 79.

The Ingersoll-Rand court found that the “essence of [Ingersoll-Rand’s] claim is a request for specific performance of the *813 original contract.” Id. As a contract claim, the court explained, the action was governed by the Contract Disputes Act, with exclusive jurisdiction in the Claims Court. The fact that Ingersoll-Rand would not be able to obtain specific performance as a remedy in Claims Court did not demonstrate that the plaintiff had no adequate remedy in that court.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Clark Const. Co., Inc. v. Pena
895 F. Supp. 1483 (M.D. Alabama, 1995)
Buffalo Central Terminal v. United States
886 F. Supp. 1031 (W.D. New York, 1995)
Mark Dunning Industries, Inc. v. Perry
877 F. Supp. 1541 (M.D. Alabama, 1995)
Action Service Corp. v. Garrett
790 F. Supp. 1188 (D. Puerto Rico, 1992)
Mark Dunning Industries, Inc. v. Cheney
934 F.2d 266 (Eleventh Circuit, 1991)
Applications Research Corp. v. Naval Air Development Center
752 F. Supp. 660 (E.D. Pennsylvania, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
726 F. Supp. 810, 36 Cont. Cas. Fed. 75,886, 1989 U.S. Dist. LEXIS 14591, 1989 WL 147781, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mark-dunning-industries-inc-v-cheney-almd-1989.