Ingersoll-Rand Co. v. United States

31 Cont. Cas. Fed. 71,177, 2 Cl. Ct. 373, 1983 U.S. Claims LEXIS 1752
CourtUnited States Court of Claims
DecidedMay 11, 1983
DocketNo. 194-83C
StatusPublished
Cited by50 cases

This text of 31 Cont. Cas. Fed. 71,177 (Ingersoll-Rand Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ingersoll-Rand Co. v. United States, 31 Cont. Cas. Fed. 71,177, 2 Cl. Ct. 373, 1983 U.S. Claims LEXIS 1752 (cc 1983).

Opinion

OPINION

KOZINSKI, Chief Judge.

This is an action to enjoin the award of a subcontract by Hawaiian Dredging and Construction Company, a government contractor. Plaintiff claims that the award, nominally to be made by the contractor, is in fact controlled by the United States, through its Naval Facilities Engineering Command (NAYFAC) which had awarded the principal contract to Hawaiian Dredging.

[374]*374The United States admits to participation in the bidding process. The price of the subcontract, which calls for production of certain air compressors to be used by Hawaiian Dredging, is to be passed on to the United States on a cost-plus-award-fee basis. The United States therefore has an interest in assuring that the subcontract goes to the lowest bidder. NAVFAC drafted the terms of the request for quotations (RFQ), later issued by Hawaiian Dredging. NAVFAC also retained authority to approve the award of the subcontract.

Upon evaluation of the five bids received,1 Hawaiian Dredging recommended award of the. subcontract to Atlas Copco, the lowest bidder. NAVFAC was prepared to approve the award but before it could communicate its approval to Hawaiian Dredging, plaintiff filed this action. The government then agreed to withhold its approval of the award pending decision on plaintiff’s request for a preliminary injunction.

In support of its request, plaintiff asserts that the NAVFAC personnel who prepared the RFQ for the subcontract were biased toward Atlas Copco, a producer of rotary air compressors. It asserts that these persons drafted the RFQ to give rotary compressors an advantage over the centrifugal type of compressors that plaintiff produces. This was accomplished, plaintiff suggests, by burdening centrifugal compressors with costly requirements that were not applied to rotary compressors. Plaintiff maintains that these requirements are unrelated to performance needs and invalidate the RFQ. Plaintiff also maintains that, even under the RFQ as written, its bid was not fully and fairly evaluated.

Defendant has moved for summary judgment, arguing that the court lacks jurisdiction to enjoin the award of a subcontract and, in the alternative, that the court may not issue an injunction on grounds that the terms of a bid solicitation do not comply with procurement regulations or are otherwise unfair or inappropriate.

DISCUSSION

A. Award of Subcontracts

Defendant argues that this court’s in-junctive authority is limited to cases involving proposed awards of contracts by the United States. It points out that, under the Tucker Act, a contractual relationship must exist between the plaintiff and the government as a condition to suit. Where, as here, the contract to’be awarded is between private parties — the contractor on the one hand, and potential subcontractors on the other — defendant suggests that the appropriate contractual relationship with the United States is lacking, and with it the jurisdictional linchpin for maintaining an action in this court.

Plaintiff responds that award of a subcontract under these circumstances closely parallels the award of a government contract. It points out that NAVFAC, the entity responsible for the principal contract, dictated the terms of the RFQ; participated (to a degree which is in dispute, see n. 1 supra) in the evaluation of bids; is wholly responsible for the cost of the subcontract; and has retained full approval authority over the award. In plaintiff’s view, it would elevate form over substance to hold that the court lacks jurisdiction to review a contract award process which is virtually indistinguishable from normal government procurement. Plaintiff also points with alarm to the possibility that agencies will structure their contracts to circumvent this court’s injunctive jurisdiction by nominally delegating to principal contractors the authority to award subcontracts while, in fact, maintaining full control over the award process.

This court’s injunctive authority over pre-award contract cases derives from section 133(a) of the Federal Courts Improvement Act of 1982, Pub.L. No. 97-614, 96 Stat. 25, 40, codified at 28 U.S.C. § 1491(a)(3). This section is not a model of clarity. See United States v. John C. Grimberg Co., 702 F.2d [375]*3751362 (Fed.Cir.1983) (majority, concurring and dissenting opinions); Quality Furniture Rentals, Inc. v. United States, 1 Cl.Ct. 136, 138, 141 (1983) (KOZINSKI, C.J.). Neither the language of the statute nor its legislative history seems to have anticipated the rich variety of factual and legal issues that this court has been required to consider in the first few months of its existence. See, e.g., Speco Corp. v. United States, 2 Cl.Ct. 335 (Cl.Ct.1983) (MAYER, J.); Systems Architects, Inc. v. United States, 2 Cl.Ct. 456 (1983) (NETTESHEIM, J.); Quality Furniture, supra, 1 Cl.Ct. 136; Indian Wells Valley Metal Trades Council v. United States, 1 Cl.Ct. 43 (1982) (WIESE, J.). This case once again presents a situation that may not have been fully anticipated, yet where the court must, as best possible, determine the scope of its injunctive authority.

Section 1491(a)(3) limits the court’s injunctive authority to “contract claim[s] brought before the contract is awarded.” This short phrase contains reference to two entirely different contracts. The second reference is to the contract which is the subject of the proposed award, i.e., the contract for goods or services. At the preaward stage, that contract is not yet in existence and therefore cannot form the basis for our exercise of jurisdiction. Grimberg, supra, at 1367 & n. 8. The first contract mentioned in section 1491(a)(3) is an implied-in-fact contract between the United States and bidders on the underlying contract. See Keco Industries, Inc. v. United States, 192 Ct.Cl. 773, 778, 428 F.2d 1233 (1970); Heyer Products Co. v. United States, 135 Ct.Cl. 63, 69-70, 140 F.Supp. 409 (1956). This collateral contract arises from the bid solicitation process and guarantees that a bid submitted in conformity with the requirements of the invitation for bids will be fully and fairly considered. See Keko Industries, supra, 192 Ct.Cl. at 778, 428 F.2d 1233; Heyer Products, supra, 135 Ct.Cl. at 69-70, 140 F.Supp. 409; Quality Furniture, supra, 1 Cl.Ct. at 139. It is this implied contract which forms the jurisdictional basis for an exercise of this court’s equitable authority.

It is clear from the logic of section 1491(a)(3), as so interpreted, that the first contract mentioned in that section — the implied contract for a fair evaluation of bids— must be one directly with the United States. If that contractual relationship with the United States is lacking, jurisdiction in this court cannot attach. The same cannot be said, however, as to the second contract mentioned in the section, i.e., the underlying contract for goods or services. Since this underlying contract is not the basis for our jurisdiction over the bid protest, nothing in section 1491(a)(3) requires that the proposed contract be directly with the United States.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hawpe Construction, Inc. v. United States
46 Fed. Cl. 571 (Federal Claims, 2000)
United International Investigative Services, Inc. v. United States
42 Cont. Cas. Fed. 77,336 (Federal Claims, 1998)
ECDC Environmental, L.C. v. United States
42 Cont. Cas. Fed. 77,250 (Federal Claims, 1998)
Mike Hooks, Inc. v. United States
42 Cont. Cas. Fed. 77,191 (Federal Claims, 1997)
Aero Corp., S.A. v. United States
42 Cont. Cas. Fed. 77,213 (Federal Claims, 1997)
Cincom Systems, Inc. v. United States
41 Cont. Cas. Fed. 77,114 (Federal Claims, 1997)
Doe v. United States
37 Fed. Cl. 74 (Federal Claims, 1996)
Levine v. Johnson
78 F.3d 603 (Federal Circuit, 1996)
IMS Services, Inc. v. United States
40 Cont. Cas. Fed. 76,784 (Federal Claims, 1995)
Control Data Systems, Inc. v. United States
40 Cont. Cas. Fed. 76,743 (Federal Claims, 1994)
McMaster Construction, Inc. v. United States
37 Cont. Cas. Fed. 76,150 (Court of Claims, 1991)
McIlvaine v. United States
23 Cl. Ct. 439 (Court of Claims, 1991)
Stellacom, Inc. v. United States
37 Cont. Cas. Fed. 76,127 (Court of Claims, 1991)
Boehm v. United States
37 Cont. Cas. Fed. 76,073 (Court of Claims, 1991)
TRW Environmental Safety Systems, Inc. v. United States
35 Cont. Cas. Fed. 75,712 (Court of Claims, 1989)
Almar Industries, Inc. v. United States
35 Cont. Cas. Fed. 75,621 (Court of Claims, 1989)
CACI Field Services, Inc. v. United States
34 Cont. Cas. Fed. 75,410 (Court of Claims, 1987)
Isometrics, Inc. v. United States
33 Cont. Cas. Fed. 74,889 (Court of Claims, 1986)
New York Telephone Co. v. Secretary of the Army
657 F. Supp. 18 (District of Columbia, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
31 Cont. Cas. Fed. 71,177, 2 Cl. Ct. 373, 1983 U.S. Claims LEXIS 1752, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ingersoll-rand-co-v-united-states-cc-1983.