Isometrics, Inc. v. United States

33 Cont. Cas. Fed. 74,889, 11 Cl. Ct. 346, 1986 U.S. Claims LEXIS 750
CourtUnited States Court of Claims
DecidedDecember 17, 1986
DocketNo. 714-86C
StatusPublished
Cited by5 cases

This text of 33 Cont. Cas. Fed. 74,889 (Isometrics, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Isometrics, Inc. v. United States, 33 Cont. Cas. Fed. 74,889, 11 Cl. Ct. 346, 1986 U.S. Claims LEXIS 750 (cc 1986).

Opinion

[347]*347OPINION

MOODY R. TIDWELL, III, Judge:

This case began with the filing by plaintiff of a Complaint seeking a preliminary and permanent injunction and declaratory relief and a motion for temporary restraining order to enjoin defendant from making award of a contract under a U.S. Marine Corps invitation for bids to any bidder other than itself. Plaintiff, the third lowest bidder on the procurement, charges that the lowest bid was nonresponsive to the IFB, that the second lowest bidder was not responsible, and that it, therefore, submitted the lowest responsive, responsible bid and is entitled to award of the contract.

The temporary restraining order was denied by a ruling from the bench on November 13, 1986. Shortly thereafter the Corps awarded the contract. Defendant filed a motion for summary judgment and the low bidder, now the contractor, The Sharman Company and second low bidder, GIL, Inc., intervened in the case. RUSCC 24(a)(2).

On November 26, 1986 GIL, Inc. filed a Complaint seeking to enjoin award of a contract to any bidder other than itself on the grounds that the bid of The Sharman Company was nonresponsive. The Sharman Company filed a Motion for Summary Judgment on December 1, 1986 which stated that defendant was entitled to judgment as a matter of law. For all practical purposes GIL, Inc.’s Complaint mirrored plaintiffs challenge to The Sharman Company’s bid and The Sharman Company’s Motion for Summary Judgment was identical to that filed by defendant.

At the December 8, 1986 hearing on plaintiff’s and GIL, Inc.’s applications for injunctive relief and defendant’s and The Sharman Company’s Motions for Summary Judgment, the parties and intervenors agreed, and the court concurred, that there were no genuine issues of material fact in the dispute over the responsiveness of The Sharman Company’s bid.1 In accordance therewith the court ordered, for the purposes of this litigation, that the hearing of the action on the merits and the application for a preliminary injunction be consolidated, but only as to the issue of the responsiveness of The Sharman Company’s bid. RUSCC 65(a)(2). Accordingly, the instant Opinion addresses both the preliminary injunction and the case on its merits, i.e., the permanent injunction.2 Although the two parties and the two intervenors all participated in the December 8, 1986 hearing, in the interests of brevity and comprehension, the court will discuss only plaintiff’s and defendant’s positions but it must be understood that in so doing the positions of the intervenors will also be aired.

FACTS

On June 18, 1986 the United States Marine Corps issued IFB No. M00027-86-B0035, which called for the delivery of 667 large water tank storage modules from a small business concern within 120 days of first article approval. Subsequently, in recognition that no small business could possibly supply 667 modules in 120 days, the Corps modified the IFB by extending the delivery date to require the delivery of 50 modules beginning 120 days after first article approval, and 50 modules per month thereafter until completion of delivery of all 667 modules. In all, it would take a total of 750 days under the modified delivery schedule to complete delivery of the modules.

[348]*348The original IFB contained the following delivery provision:3

OFFEROR’S/BIDDER’S PROPOSED DELIVERY SCHEDULE

(To be Completed by Offeror/Bidder)

ITEM NO. QUANTITY WITHIN DAYS AFTER DATE OF CONTRACT

0001 667 each 120 days after first article approval

The amended delivery schedule stated:

ITEM NO. QTY WITHIN DAYS AFTER DATE OF CONTRACT

0001 667 each Delivery of 50 each units 120 days after First Article Approval and delivery of 50 each units per month thereafter until total amount of 667 units are delivered.

Offers/Bids that propose a delivery of a quantity under such terms or conditions that delivery will not clearly fall within the applicable required delivery period specified above, will be considered nonresponsive/unacceptable and rejected. If the offeror/bidder proposes no other delivery schedule, the desired delivery schedule above will apply.

The amended delivery schedule cites to Federal Acquisition Regulation 52.212-2 (Alternate III) which permits the contracting officer to use a delivery clause “substantially” as set forth therein, “if the Government desires delivery by a certain time but requires delivery by a specified later time.”

The bid form remained the same throughout the bidding process, i.e.:

0001 667 each

Isometrics and GIL, Inc. left the bid form blank and thereby agreed under language of the amendment to supply the modules at the desired delivery schedule, as amended. The Sharman Company, however, wrote the number “678” on the bid form in the column entitled “WITHIN DAYS AFTER DATE OF CONTRACT.” Thus, rose the dispute. The Corps awarded the contract to The Sharman Company because it was the lowest bidder and its bid was determined to be responsive to the delivery schedule of the contract. Defendant and The Sharman Company agree that under the IFB, as amended, that The Sharman Company is obligated to deliver 667 modules within 678 days of award at an incremental rate, necessarily, to exceed 50 units per month. Plaintiff disagreed. Plaintiff argued that The Sharman Company’s bid was nonresponsive to the delivery terms of the IFB, as amended, because it proposed [349]*349to deliver the modules “under such terms or conditions that delivery will not clearly fall within the applicable required delivery period.” Specifically, Isometrics argued that by penning the number “678” on the bid form it obligated itself to deliver all 667 modules within 678 days but was not obligated to meet the incremental 50 unit per month delivery beginning 120 days after first article approval.

DISCUSSION

The present case is before the court on plaintiff’s and intervenor GIL, Inc.’s request that the Marine Corps be enjoined from permitting The Sharman Company to perform under the recently awarded contract and on defendant’s and intervenor The Sharman Company’s Motions for Summary Judgment. Summary judgment is appropriate only where there are no issues of material fact in dispute and judgment is appropriate as a matter of law. South Louisiana Grain Services, Inc. v. United States, 1 Cl.Ct. 281, 289 (1982). This case involves no genuine issues of material fact and is ripe for resolution.

Defendant has a legally enforceable duty to give full and fair consideration to plaintiff’s bid vis-a-vis the Sharman Company’s bid, in view of Isometrics challenge that the government breached that duty by awarding the contract to The Sharman Company in the face of the latter’s alleged nonresponsive bid. The specific nature of defendant’s duty is to fully and fairly consider all of the bids under the IFB and the prescribed procurement guidelines. Eagle Construction Corp. v. United States, 4 Cl.Ct. 470, 475 (1980); Ingersoll-Rand v. United States, 2 Cl.Ct. 373, 376 (1983). The court in Heli-Jet Corp. v. United States, 2 Cl.Ct. 613 (1983) stated succinctly that:

[t]he obligation of the government upon issuance of a solicitation is to treat all bidders fairly and to give full consideration to all bids.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

ECDC Environmental, L.C. v. United States
42 Cont. Cas. Fed. 77,250 (Federal Claims, 1998)
Aero Corp., S.A. v. United States
42 Cont. Cas. Fed. 77,213 (Federal Claims, 1997)
Aerolease Long Beach v. United States
31 Fed. Cl. 342 (Federal Claims, 1994)
PNM Construction Inc. v. United States
34 Cont. Cas. Fed. 75,409 (Court of Claims, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
33 Cont. Cas. Fed. 74,889, 11 Cl. Ct. 346, 1986 U.S. Claims LEXIS 750, Counsel Stack Legal Research, https://law.counselstack.com/opinion/isometrics-inc-v-united-states-cc-1986.