F. Alderete General Contractors, Inc. v. United States

715 F.2d 1476, 31 Cont. Cas. Fed. 71,397, 1983 U.S. App. LEXIS 13653
CourtCourt of Appeals for the Federal Circuit
DecidedAugust 23, 1983
Docket83-1003
StatusPublished
Cited by62 cases

This text of 715 F.2d 1476 (F. Alderete General Contractors, Inc. v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
F. Alderete General Contractors, Inc. v. United States, 715 F.2d 1476, 31 Cont. Cas. Fed. 71,397, 1983 U.S. App. LEXIS 13653 (Fed. Cir. 1983).

Opinion

COWEN, Senior Circuit Judge.

The appellant, F. Alderete General Contractors, Inc. (Alderete or contractor), appeals from a decision of the United States Claims Court 1 (Claims Court) which held that it lacked the power under 28 U.S.C. § 1491(a)(3) to grant injunctive and other equitable relief under the circumstances.

The contractor first filed his suit for equitable relief in a district court, which transferred the case to the Claims Court. The contract was awarded after the transfer but before the Claims Court could rule on the merits of the application. Holding that it could not exercise the equitable powers granted by the statute beyond the pre-award stage of the procurement process, the Claims Court dismissed the contractor’s complaint. We reverse and remand for further proceedings.

Background

On January 21, 1983, Alderete filed a “Motion for Contempt, Application for Enforcement of Judgment, and for Further Relief” in the United States District Court for the Western District of Texas (District Court) on December 15, 1981. Prior to the filing of the motion, that court had issued a permanent injunction which required that the U.S. Army Corps of Engineers (Corps) offer the Keystone Project in El Paso, Texas, to the Small Business Administration (SBA) under the program established pursuant to Section 8(a) of the Small Business Act, 15 U.S.C. § 637.

Following the issuance of the injunction, the Corps offered the Keystone Project to the SBA, and in June 1982, Alderete was selected for this procurement. The ensuing negotiations between Alderete and the Corps were not successfully concluded and the Corps, after advising SBA, then removed the project from the Section 8(a) program. On January 14, 1983, an unrestricted invitation for bids was issued. Al-derete responded with the motion it filed on January 21, 1983, referred to above.

On February 19, 1983, the District Court entered an order holding the Corps in civil contempt for its decision to let the Keystone Project procurement on an unrestricted basis. However, the court also granted the Corps permission to seek relief from the injunction previously entered and to pro *1478 ceed with the bid opening then scheduled, provided that no award would be issued until the court ruled upon an application for relief from the injunction.

By order filed March 9, 1983, the District Court reconsidered its order of February 19, 1983, and ruled that the Corps’ decision to relet the contract on an unrestricted basis did not constitute contempt of the injunction which was issued December 15, 1981. The court also ruled that “the Corps may issue an award pursuant to said bid opening.” However, the court also found that the events which Alderete had complained of in its motion of January 21,1983, constituted a “new cause of action and as to that cause of action jurisdiction lies in the United States Claims Court pursuant to 28 U.S.C. 1491.” Accordingly, the District Court transferred the case to the Claims Court by order of March 9, 1983.

On the following day, March 10,1983, the Corps awarded the contract to Burns Construction Company, Inc.

On March 25,1983, pursuant to the transfer order, Alderete filed in the Claims Court its Complaint And Application For Temporary Restraining Order Preliminary Injunction And Permanent Injunction, seeking equitable relief enjoining construction work, placing the Keystone Project back into the SBA Section 8(a) program and providing for either an award to Alderete or an order that negotiations to this end be reconvened. In the Claims Court, Alderete filed a motion to remand the case back to the District Court, but the Government argued that the Claims Court had jurisdiction to grant in-junctive relief despite the award of the contract. Subsequently Alderete took the position that if the case was not remanded to the District Court, the Claims Court should grant the temporary restraining order which had been applied for. The Claims Court treated the Alderete motion for remand as if it were a request in the alternative for a transfer to the District Court or for the issuance of a temporary restraining order.

The Claims Court decided that our recent decision in United States v. John G. Grimberg Co., 702 F.2d 1362 (Fed.Cir.1983) was not directly applicable. However, the court quoted language from that decision which it felt was relevant, and held that its power to grant injunctive relief was limited to the pre-award stage of the contract. In dismissing Alderete’s cause, the Claims Court stated that its result would leave Alderete “free to institute whatever post-award action in the District Court it deems to be appropriate, which action will not then be encumbered with the issue of 28 U.S.C. Sec. 1491(a)(3) ‘exclusivity’ which would be present were this ‘pre-award’ action (now in the post-award stage) to be transferred to the District Court under 28 U.S.C. Sec. 1631.”

Alderete filed a timely appeal and the Government has filed a brief in which it joins Alderete in urging that the Claims Court has power to grant the equitable relief requested. Since the issue of the Claims Court’s jurisdiction was fully argued and considered below, it is appropriate for this court to decide the question.

Analysis

1.

A decision on the issue presented in this appeal requires an interpretation of 28 U.S.C. § 1491(a)(3) 2 and an assessment of the breadth of this court’s holding in Grim-berg, supra. The case has some unusual aspects.

The suit for equitable relief was first filed in the District Court, which recognized that it lacked jurisdiction, and transferred the case to the Claims Court. One day after the transfer was ordered (before the Claims Court was aware that the case was coming its way), the contracting officer awarded the disputed contract to another contractor.

*1479 Appellant and the Government are united in the view that the Claims Court has jurisdiction and both urge reversal.

The Claims Court is divided on the issue. The decision below was followed by Chief Judge Kozinski without discussion in Big Bud Tractors, Inc. v. United States, 2 Cl.Ct. 195 (1983).

In Dean Forwarding Company, Inc. v. United States, 2 Cl.Ct. 559 (1983), Judge Harkins opined that the decision is erroneous. He emphasized that the contract language “brought before the contract is awarded” accords with the standard rule and negates any construction that would have Congress intend the provision to read as though it said “brought and decided before the contract is awarded.” In Systems Architects, Inc. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gulley v. United States
Federal Claims, 2020
Cook v. United States
123 Fed. Cl. 277 (Federal Claims, 2015)
Barlow & Haun, Inc. v. United States
118 Fed. Cl. 597 (Federal Claims, 2014)
Coastal Environmental Group, Inc. v. United States
114 Fed. Cl. 124 (Federal Claims, 2014)
CBY Design Builders v. United States
105 Fed. Cl. 303 (Federal Claims, 2012)
Ford Motor Co. v. United States
806 F. Supp. 2d 1328 (Court of International Trade, 2011)
BLR Group of America, Inc. v. United States
94 Fed. Cl. 354 (Federal Claims, 2010)
USfalcon, Inc. v. United States
92 Fed. Cl. 436 (Federal Claims, 2010)
Technical Innovation, Inc. v. United States
93 Fed. Cl. 276 (Federal Claims, 2010)
Emerald Coast Finest Produce Co. v. United States
79 Fed. Cl. 466 (Federal Claims, 2007)
Sanofi-Synthelabo v. Apotex Inc.
488 F. Supp. 2d 317 (S.D. New York, 2006)
Travelers Indemnity Co. v. United States
72 Fed. Cl. 56 (Federal Claims, 2006)
Liberty Mutual Insurance v. United States
70 Fed. Cl. 37 (Federal Claims, 2006)
Nova Casualty Co. v. United States
69 Fed. Cl. 284 (Federal Claims, 2006)
Insurance Co. of the West v. United States
55 Fed. Cl. 529 (Federal Claims, 2003)
Southwest Soil Remediation, Inc. v. City of Tucson
36 P.3d 1208 (Court of Appeals of Arizona, 2001)
Washington International Insurance v. United States
138 F. Supp. 2d 1314 (Court of International Trade, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
715 F.2d 1476, 31 Cont. Cas. Fed. 71,397, 1983 U.S. App. LEXIS 13653, Counsel Stack Legal Research, https://law.counselstack.com/opinion/f-alderete-general-contractors-inc-v-united-states-cafc-1983.