GEWIN, Circuit Judge:
In 1949 the predecessors of Humble Gas Transmission Supply Company (hereinafter, Humble) and Mississippi Power and Light Company (hereinafter, MPL) negotiated an exclusive natural gas supply contract with an expiration
date of January 1, 1972. As last amended, the contract called for Humble to furnish natural gas via its Fowler-Baton Rouge System for MPL’s Natchez Steam Electric Station. Humble instituted this diversity action in May 1969 to enjoin MPL from breaching this contract by purchasing natural gas for its Natchez station from Mississippi Valley Gas (hereinafter, Valley), and to secure a declaratory judgment as to the rights of the parties. The district court denied the requested injunction because it concluded that the parties had terminated their contractual obligations pursuant to an oral agreement reached on November 22, 1968. On appeal, Humble contends primarily that certain of the district court’s findings of fact are clearly erroneous.
We affirm.
Both MPL and Valley receive gas via Humble’s Fowler-Baton Rouge line. The 1949 contract, as last amended, permitted MPL to take up to 20,000 MCF
per
day at a rate of 28.28 cents per MCF. Valley may take a maximum of 23,576 MCF per day from the line at 17.69 cents per MCF pursuant to Federal Power Commission Opinion No. 530 issued October 5, 1967.
The quantity and rate at which Valley takes its gas may be varied only by Commission order. No restrictions bind Valley in the use of its allotment of gas. Valley’s need for gas varies drastically depending on the temperature, the greatest demand occurring during the colder months of a year.
In July 1968, Humble informed MPL that its reserves of natural gas feeding the Fowler-Baton Rouge line were seriously depleted and that peak hour demands on the line could not be met. Humble stated that it had obligations of approximately 90,000 MCF per day and could supply only 70,000 MCF per day. Beginning immediately and continuing for the next four months, Humble alter-natedly threatened, cajoled and demanded that MPL officials either (a) terminate the '49 supply contract, or (b) renegotiate the ’49 firm supply contract into an interruptible supply agreement.
The district court found that officials of Humble and MPL met on November 22, 1968 and agreed to terminate the ’49 contract. Valley is presently supplying MPL with natural gas on an interrupti-ble basis. Valley has available for sale to MPL an amount equal to the difference between the quantity of gas required for sale to its other customers and 23,576 MCF per day, or about 12,-000 MCF per day at 19.834 cents per MCF.
Humble first challenges as clearly
erroneous
the lower court’s finding that an agreement to terminate was reached at the November 22 meeting between Humble and MPL. The district court stated:
It was agreed by the parties at such meeting that the plaintiff [Humble] was running out of its supply of natural gas in this Fowler-Baton Rouge system and that it could no longer furnish defendant [MPL] natural gas under its commitment from said system and that the defendant [MPL] agreed to obtain another supply of natural gas for its Natchez plant as quickly as possible and that plaintiff should supply natural gas from its system as best it could until such gas from another supplier could be obtained and the transition accomplished in an orderly manner.
The court also found that the agreement was “substantially confirmed” in a letter dated November 25, 1968 from Humble to MPL.
Humble argues that the November 25 letter contradicts, rather than supports, the district court’s finding that an agreement to terminate the 1949 contract was reached at the November 22 meeting. Before considering Humble’s interpretation of the letter, we hasten to point out that the factual finding here in issue was not based solely on the letter. Lengthy testimony was presented by both parties as to what actually transpired at the meeting. Needless to say, it is replete with contradictions and inconsistencies. A perusal of the entire record convinces us that the district court’s finding of an agreement to terminate is supported by substantial and persuasive evidence. The point here is that assuming Humble’s interpretation of the letter is correct, it does not follow that the district court’s findings are clearly erroneous.
We are convinced, nevertheless, that the letter does substantially confirm the November 22 agreement. The crucial pai’agraph, in Humble’s estimation, provides:
In addition you agreed to proceed to obtain another supply of gas for the Natchez Generating Plant and in this connection we agreed to hold our offer open to terminate the existing agreement at the earliest date possible. Our offer to convert the existing agreement into an interruptible contract also remains open in the event you desire io elect that course of action.
According to Humble, this paragraph contains only alternate contingent offers and does not recite the terms of an agreement. With reference to the letter Humble states:
The obligations of each party of the November 22 meeting were contingent: that is, first MPL had to obtain another supply of gas and thereafter, upon acceptance of either of Humble’s offers, Humble was obligated to terminate the contract.
Humble further explains:
[T]he language of the letter of November 22, 1968, plainly says that Humble
was making an offer to terminate
and, also,
making an offer to convert the contract into an interruptible contract.
One of the most troubling aspects of this interpretation is that both offers are contingent on MPL’s obtaining another supply of gas. And yet, if MPL secured another supply of gas, it would not need a second supply from Humble, especially an uncertain, interruptible supply. In addition, Humble’s interpretation totally ignores the obvious implications of the word “agreed” as used in the “crucial” paragraph of the letter. Finally, why would Humble “offer” to hold open an offer ? A simple offer would have been sufficient and would have remained open until revoked. The entire letter has all of the earmarks of exactly what it purports to be, the confirmation of an “understanding reached on November 22, 1968.” In effect,
Humble
promised
to hold open its offer to terminate at the earliest possible date in return for MPL’s promise to proceed to obtain another supply of gas. The letter also reiterated an offer which had been repeatedly rejected by MPL, i.e., to convert the existing agreement into an interruptible contract.
Free access — add to your briefcase to read the full text and ask questions with AI
GEWIN, Circuit Judge:
In 1949 the predecessors of Humble Gas Transmission Supply Company (hereinafter, Humble) and Mississippi Power and Light Company (hereinafter, MPL) negotiated an exclusive natural gas supply contract with an expiration
date of January 1, 1972. As last amended, the contract called for Humble to furnish natural gas via its Fowler-Baton Rouge System for MPL’s Natchez Steam Electric Station. Humble instituted this diversity action in May 1969 to enjoin MPL from breaching this contract by purchasing natural gas for its Natchez station from Mississippi Valley Gas (hereinafter, Valley), and to secure a declaratory judgment as to the rights of the parties. The district court denied the requested injunction because it concluded that the parties had terminated their contractual obligations pursuant to an oral agreement reached on November 22, 1968. On appeal, Humble contends primarily that certain of the district court’s findings of fact are clearly erroneous.
We affirm.
Both MPL and Valley receive gas via Humble’s Fowler-Baton Rouge line. The 1949 contract, as last amended, permitted MPL to take up to 20,000 MCF
per
day at a rate of 28.28 cents per MCF. Valley may take a maximum of 23,576 MCF per day from the line at 17.69 cents per MCF pursuant to Federal Power Commission Opinion No. 530 issued October 5, 1967.
The quantity and rate at which Valley takes its gas may be varied only by Commission order. No restrictions bind Valley in the use of its allotment of gas. Valley’s need for gas varies drastically depending on the temperature, the greatest demand occurring during the colder months of a year.
In July 1968, Humble informed MPL that its reserves of natural gas feeding the Fowler-Baton Rouge line were seriously depleted and that peak hour demands on the line could not be met. Humble stated that it had obligations of approximately 90,000 MCF per day and could supply only 70,000 MCF per day. Beginning immediately and continuing for the next four months, Humble alter-natedly threatened, cajoled and demanded that MPL officials either (a) terminate the '49 supply contract, or (b) renegotiate the ’49 firm supply contract into an interruptible supply agreement.
The district court found that officials of Humble and MPL met on November 22, 1968 and agreed to terminate the ’49 contract. Valley is presently supplying MPL with natural gas on an interrupti-ble basis. Valley has available for sale to MPL an amount equal to the difference between the quantity of gas required for sale to its other customers and 23,576 MCF per day, or about 12,-000 MCF per day at 19.834 cents per MCF.
Humble first challenges as clearly
erroneous
the lower court’s finding that an agreement to terminate was reached at the November 22 meeting between Humble and MPL. The district court stated:
It was agreed by the parties at such meeting that the plaintiff [Humble] was running out of its supply of natural gas in this Fowler-Baton Rouge system and that it could no longer furnish defendant [MPL] natural gas under its commitment from said system and that the defendant [MPL] agreed to obtain another supply of natural gas for its Natchez plant as quickly as possible and that plaintiff should supply natural gas from its system as best it could until such gas from another supplier could be obtained and the transition accomplished in an orderly manner.
The court also found that the agreement was “substantially confirmed” in a letter dated November 25, 1968 from Humble to MPL.
Humble argues that the November 25 letter contradicts, rather than supports, the district court’s finding that an agreement to terminate the 1949 contract was reached at the November 22 meeting. Before considering Humble’s interpretation of the letter, we hasten to point out that the factual finding here in issue was not based solely on the letter. Lengthy testimony was presented by both parties as to what actually transpired at the meeting. Needless to say, it is replete with contradictions and inconsistencies. A perusal of the entire record convinces us that the district court’s finding of an agreement to terminate is supported by substantial and persuasive evidence. The point here is that assuming Humble’s interpretation of the letter is correct, it does not follow that the district court’s findings are clearly erroneous.
We are convinced, nevertheless, that the letter does substantially confirm the November 22 agreement. The crucial pai’agraph, in Humble’s estimation, provides:
In addition you agreed to proceed to obtain another supply of gas for the Natchez Generating Plant and in this connection we agreed to hold our offer open to terminate the existing agreement at the earliest date possible. Our offer to convert the existing agreement into an interruptible contract also remains open in the event you desire io elect that course of action.
According to Humble, this paragraph contains only alternate contingent offers and does not recite the terms of an agreement. With reference to the letter Humble states:
The obligations of each party of the November 22 meeting were contingent: that is, first MPL had to obtain another supply of gas and thereafter, upon acceptance of either of Humble’s offers, Humble was obligated to terminate the contract.
Humble further explains:
[T]he language of the letter of November 22, 1968, plainly says that Humble
was making an offer to terminate
and, also,
making an offer to convert the contract into an interruptible contract.
One of the most troubling aspects of this interpretation is that both offers are contingent on MPL’s obtaining another supply of gas. And yet, if MPL secured another supply of gas, it would not need a second supply from Humble, especially an uncertain, interruptible supply. In addition, Humble’s interpretation totally ignores the obvious implications of the word “agreed” as used in the “crucial” paragraph of the letter. Finally, why would Humble “offer” to hold open an offer ? A simple offer would have been sufficient and would have remained open until revoked. The entire letter has all of the earmarks of exactly what it purports to be, the confirmation of an “understanding reached on November 22, 1968.” In effect,
Humble
promised
to hold open its offer to terminate at the earliest possible date in return for MPL’s promise to proceed to obtain another supply of gas. The letter also reiterated an offer which had been repeatedly rejected by MPL, i.e., to convert the existing agreement into an interruptible contract.
Humble also attacks as clearly erroneous the district court’s finding that Valley constituted “another supply” of gas within the meaning of the termination agreement.
The court held:
Nothing was said in such agreement [of November 22] by either party to indicate that such supply of natural gas had to come from a different source, or could not come from Mississippi Valley Gas Company because it got its gas from plaintiff [Humble]. No such restriction or limitation was contained in such oral agreement of 'the parties which surely had a valuable consideration moving to each party from it.
Humble does not argue that the parties explicitly excluded Valley from consideration as “another supply” of gas. Humble explains that it wanted to terminate the contract in order to get MPL off the Fowler-Baton Rouge line and that, in effect, MPL is still on the line, receiving Humble’s gas at bargain-basement prices. Thus, it contends that MPL
must
have understood that Valley was not “another supply” of gas. MPL responds that no understanding of this nature was ever reached; that it has reduced Humble’s daily obligation on the line by 20,000 MCF by terminating the contract;
that it now has an interruptible, uncertain supply source through Valley; and, that natural gas on an in-terruptible basis is always cheaper.
The most that can be said in Humble’s favor is that there is a clear conflict in the evidence on this point. Our conces
sion is of little value, however, since we may not reverse the decision of the district court unless “clearly erroneous.”
The Supreme Court defined this term in United States v. United States Gypsum Co.: “A finding is ‘clearly erroneous’ when although there is evidence to support it, the reviewing court on the entire evidence is left with a definite and firm conviction that a mistake has been committed.”
Humble has vigorously and thoroughly argued its position and we have carefully and earnestly studied the record but the evidence in this case does not leave us with a “definite and firm conviction that a mistake has been committed.”
To paraphrase the district court, the parties agreed to terminate the ’49 contract when MPL obtained another supply of gas. Humble promised to hold open its offer to terminate, and MPL promised to proceed to obtain another supply of gas. No limitations on the source of supply were made. The ’49 contract was terminated when MPL accepted Valley’s offer to supply natural gas to the Natchez station.
Affirmed.