Metric Constructors, Inc. v. Daniel S. Goldin, Administrator, National Aeronautics and Space Administration

69 F.3d 554, 1995 U.S. App. LEXIS 36011, 1995 WL 620154
CourtCourt of Appeals for the Federal Circuit
DecidedOctober 20, 1995
Docket95-1078
StatusUnpublished

This text of 69 F.3d 554 (Metric Constructors, Inc. v. Daniel S. Goldin, Administrator, National Aeronautics and Space Administration) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Metric Constructors, Inc. v. Daniel S. Goldin, Administrator, National Aeronautics and Space Administration, 69 F.3d 554, 1995 U.S. App. LEXIS 36011, 1995 WL 620154 (Fed. Cir. 1995).

Opinion

69 F.3d 554

40 Cont.Cas.Fed. (CCH) P 76,865

NOTICE: Federal Circuit Local Rule 47.6(b) states that opinions and orders which are designated as not citable as precedent shall not be employed or cited as precedent. This does not preclude assertion of issues of claim preclusion, issue preclusion, judicial estoppel, law of the case or the like based on a decision of the Court rendered in a nonprecedential opinion or order.
METRIC CONSTRUCTORS, INC., Appellant,
v.
Daniel S. GOLDIN, Administrator, National Aeronautics and
Space Administration, Appellee.

No. 95-1078.

United States Court of Appeals, Federal Circuit.

Oct. 20, 1995.

Before NIES, LOURIE, and CLEVENGER, Circuit Judges.

Opinion for the court filed by Judge CLEVENGER. Dissenting opinion filed by Judge NIES.

CLEVENGER, Circuit Judge.

Metric Constructors, Inc. appeals from the August 5, 1994 Armed Services Board of Contract Appeals decision, Docket No. 46284, denying Metric an equitable adjustment for the installation of 84 drain trap primers. We reverse and remand.

* NASA hired general contractor Metric in February, 1991, to build a facility for NASA's Kennedy Space Center at a fixed price of $56,215,000. Metric subcontracted the project's plumbing aspects to Sauer, Inc. As with most plumbing projects, this project required that Sauer install traps in all drains. Traps are the U-shaped pipes at the bottom of the drain that provide a water seal in the drain pipe, thereby preventing sewer gases from rising up through the drain. Additionally, NASA required that Sauer install trap primers in some of the drains. Trap primers are devices that provide an independent water source for traps susceptible to evaporation. NASA and Metric, on behalf of Sauer, dispute the number of trap primers required by the contract.

Specifically, Metric contends that NASA made Sauer install 84 trap primers that the contract had not called for, and the cost for which Sauer had not included in its bid. Sauer installed these trap primers, per NASA's request, in open hub drains and in particular floor drains. Subsequently, in September, 1992, Metric submitted its certified claim in the amount of $65,692 for a "constructive change" to the contract. In February, 1993, the Contracting Officer issued his Final Decision denying the claim. Thereafter, Metric timely appealed to the Board.

The Board subsequently upheld the Contracting Officer's decision, concluding that NASA's desire for trap primers "was not as clearly expressed in the plain language of the specifications and drawings as it might have been, but we find it was stated with sufficient clarity." The Board based its opinion primarily on one specification drawing that required that the drains at issue be equipped with "1/2 [inch] primer connections", which the Board interpreted to mean that trap primers were required. In essence, the Board held that because a trap primer cannot be installed without a primer connection, a contractor seeing the requirement for primer connections would necessarily conclude that the government wanted trap primers to be installed at every drain location.

II

Contract interpretation is a question of law, which we review de novo. C. Sanchez & Son, Inc. v. United States, 6 F.3d 1539, 1544 (Fed. Cir. 1993). We interpret a contract in accordance with its express terms and the plain meaning thereof. Id. at 1543. A contract term is ambiguous if there is more than one reasonable interpretation. Id. at 1544.

In the case at hand, we conclude that the contract is ambiguous regarding the placement of the trap primers in the drains at issue. The contract specifies that trap primers were to be provided "as indicated on drawings." But some of the drawings indicate that trap primers were not required. For example, "isometric" drawings M-163, M-164, and M-165 illustrate the placement of trap primers at particular floor drains, by using specific symbols for trap primers and the term "TRAP PRIMER", but not at other floor drains. And no trap primers are illustrated on the isometric drawings for open hub drains. In another "flow diagram" drawing, M-140, many rooms for which NASA ultimately required trap primers are not addressed in the drawing.1

The Government, however, relies on the "schedules fixture" drawing, M-073, which specifies that open hub drains and floor drains FD-1, FD-2, and FD-3 be equipped with, inter alia, 1/2 inch primer connections and standard deep seal traps.2 M-073 does not, however, state that trap primers are required in these drains.3 Nevertheless, the Government contends that the requirement for primer connections can only mean that trap primers were also required. Metric asserts that the requirement for primer connections is separate from the requirement for trap primers. Indeed, in this regard each party argues that there is no ambiguity in the contract, because each is convinced that it is completely right and that the opposing party is completely wrong. This posture bolsters our conclusion that an ambiguity exists. H & M Moving, Inc. v. United States, 499 F.2d 660, 670-71 (Ct. Cl. 1974).

Reviewing many elements in the contract, we conclude that Metric reasonably interpreted that the requirement for primer connections did not necessarily compel the installation of trap primers under this contract. As an initial matter, the drawings fail to specify trap primers at the drains locations at issue. Next, although M-073 specifies primer connections and deep seal traps, it does not specify trap primers. And although the term "connection" may suggest the function of connecting, the trap connection item as specified in M-073 is a device sold as an individual unit. Notably, Sauer apparently did not quibble with the requirement for primer connections at all drains because it routinely installs them at all drains in a given project,4 and the Board noted that a "contractor might have reason to supply connections without trap primers to avoid field error." Such field error could only result if trap primers were required at some, but not all, drains.

Additionally, the Government has essentially conceded that at some point in time trap primers were not required at all of the drains at issue. In responding to Metric's assertion that M-140 did not specify the placement of trap primers, the Government said that the details in the drawings allowed for one trap primer to be connected to more than one drain, and thus "permitted the contractor the flexibility to determine the precise number and locations of the trap primers." NASA actually took that flexibility away from Metric when it required that the trap primers be installed at each and every drain.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Turner Construction Co.
819 F.2d 283 (Federal Circuit, 1987)
Fruin-Colnon Corporation v. The United States
912 F.2d 1426 (Federal Circuit, 1990)
C. Sanchez and Son, Incorporated v. United States
6 F.3d 1539 (Federal Circuit, 1993)
Peter Kiewit Sons' Co. v. United States
109 Ct. Cl. 390 (Court of Claims, 1947)
WPC Enterprises, Inc. v. United States
323 F.2d 874 (Court of Claims, 1963)
Chris Berg, Inc. v. United States
455 F.2d 1037 (Court of Claims, 1972)
H & M Moving, Inc. v. United States
499 F.2d 660 (Court of Claims, 1974)
Newsom v. United States
676 F.2d 647 (Court of Claims, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
69 F.3d 554, 1995 U.S. App. LEXIS 36011, 1995 WL 620154, Counsel Stack Legal Research, https://law.counselstack.com/opinion/metric-constructors-inc-v-daniel-s-goldin-administ-cafc-1995.