Jefferson Construction Co. Of Florida, a Florida Corporation v. The United States

364 F.2d 420, 176 Ct. Cl. 1363, 1966 U.S. Ct. Cl. LEXIS 263
CourtUnited States Court of Claims
DecidedJuly 15, 1966
Docket67-65
StatusPublished
Cited by23 cases

This text of 364 F.2d 420 (Jefferson Construction Co. Of Florida, a Florida Corporation v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jefferson Construction Co. Of Florida, a Florida Corporation v. The United States, 364 F.2d 420, 176 Ct. Cl. 1363, 1966 U.S. Ct. Cl. LEXIS 263 (cc 1966).

Opinion

PER CURIAM:

This case was referred to Trial Commissioner C. Murray Bernhardt with directions to make recommendation for conclusions of law on plaintiff’s motion for judgment on the pleadings and for summary judgment and defendant’s cross-motion for summary judgment. The commissioner has done so in an opinion and report filed on February 7, 1966. Exceptions to the commissioner’s report were filed by the parties and the case was submitted to the court on plaintiff’s request for review of the report and opinion, the briefs of the parties and oral argument of counsel. Since the court is in agreement with the opinion and recommendation of the commissioner, with modifications, it hereby adopts the same, as modified, as the basis for its judgment in this case, as hereinafter set forth. Therefore, plaintiff is not entitled to recover, plaintiff’s motions for judgment on the pleadings and for summary judgment are denied, defendant’s cross-motion for summary judgment is granted and the petition is dismissed.

*422 Commissioner Bernhardt’s opinion * , as modified by the court is as follows:

These dispositive cross-motions 1 portray a case of misleading contract drawings counteracted by a warning specification and a contractor’s duty to inquire. The case originates in a contract awarded plaintiff to construct a levee in Florida. Earth for the levee was to be obtained from a “continous borrow pit” bordering the levee embankment site throughout its 7.65-mile length. Specifications enumerated the minimum equipment to have on the job. Drawings provided dimensional and other data for the levee and the adjacent borrow pit. On behalf of its subcontractor which sustained the eventual loss, the plaintiff contends that the drawings depicted a borrow pit of much narrower width than was actually required, and that the greater width necessitated the use of more equipment and rehandling of more borrow material than the plaintiff could have reasonably contemplated. This came about because a dragline of a given boom length, operating in the center or on the edge of the berm could have scooped each load of earth from a borrow pit with a bottom width of 100 feet and deposited it in position on the levee embankment in one continuous motion, whereas in a wider borrow pit the reach of the dragline boom would be insufficient to perform the operation in one motion but would require rehandling of excavated material. At the conclusion of performance the contractor submitted a claim of $297,229.93 to the contracting officer under the standard Changes clause of the contract for its unanticipated costs. The Corps of Engineers Board of Contract Appeals confirmed the contracting officer’s rejection of the claim for the assigned reason that the plans and specifications, read together were not misleading and contained information sufficient to enable plaintiff to estimate accurately the width of the borrow pit required to provide the known quantity of earth to build the levee embankment to its design dimensions.

Sheet 3 of the contract drawings depicts a typical cross-section of the levee and its adjoining borrow pit on a given scale. Typically the levee cross-section shows an earth mound of prescribed configuration, a flat earth berm connecting it to the borrow pit, and a borrow pit with sloping sides and a flat bottom. An extension of one side of the borrow pit is shown in dotted lines marked “Additional Excavation as required for levee fill”, meaning that any additional borrow material to meet the earthfill requirements of the levee would be obtained from that side of the borrow pit farthest away from the levee. Application of the scale to the borrow pit drawing discloses a bottom width of 80 feet, plus 20 feet horizontally for additional excavation if needed. The typical cross-section states in a legend, however, that the bottom width of the borrow pit “Varies (see profile)”, and below that is the wording—

Bottom widths of required continuous borrow pit section shall be as shown on the profile except as otherwise provided in the specifications.

The profile information referred to in the drawing on sheet 3 is contained in sheet 4 of the drawings. Sheet 4 depicts core boring and elevation data at ten separate locations on the length of the levee. These ten sections reflect bottom widths of the continuous borrow pit ranging from 60 to 100 feet. In most areas of the levee the actual width of the excavated borrow pit approximated 200 *423 feet, thus causing the additional costs for which the plaintiff seeks reimbursement.

The Board reached no clearly stated decision on the conflicting evidence of the parties as to whether the job could have been performed on time with the equipment listed in the specifications as the minimum required to perform if the bottom width of the borrow pit had averaged 100 feet as the plaintiff had anticipated. The plaintiff had mobilized the minimum list of equipment on the job at the outset. However the notice to proceed issued by the contracting officer to the plaintiff warned the latter that it had “insufficient equipment to prosecute the work within the time element specified in the contract”, and threatened to terminate the contract if plaintiff did not prove within 90 days that it had sufficient equipment.

The Government’s principal defense is based on paragraph 2-03a. of the Technical Provisions of the contract, reading as follows:

a. Continuous Borrow Pit for L-49: The continuous borrow pit adjacent to Levee 49 shall conform to requirements prescribed herein and as shown on the drawings. Embankment materials available in the required cross section of the continuous borrow pit, as shown on the drawings, are estimated to be less than the amount required to build the levee. The additional levee fill required shall be obtained by extending the excavation as indicated on the drawings. If the required borrow pits should yield more fill material than needed for embankment construction, the width shall be decreased uniformly from top to bottom as required. It is recognized that variations in the nature of the materials encountered and the quantity of fill required for the levees will result in the width and/or depth of the borrow pits being greater than the “Required Continuous Borrow Pit Section” indicated on the drawings. The bottom of the canal shall be left relatively smooth and level. Abrupt changes of grade or width shall be avoided. All suitable materials excavated shall be used in the adjacent embankment.

The cited Technical Provision should have been enough to alert the plaintiff to the likelihood that the borrow pit would have to exceed the widths shown on sheets 3 and 4 of the drawings in order to provide sufficient fill for the levee design, or at least put plaintiff on notice to inquire, assuming that the contract documents furnished enough data for such ascertainment. While ambiguous contract provisions are construed against the author (Peter Kiewit Sons’ Co. v. United States, 109 Ct.Cl. 390 (1947), and a contractor is not usually obligated to seek clarification of all interpretative problems inhering in the contract terms, he must nevertheless inquire where the discrepancy, omission or conflict is obvious (Consolidated Eng’r Co. for use of Fulton Nat. Bank of Atlanta v. United States, 98 Ct.Cl. 256, 280 (1943); Jefferson Construction Co. v. United States, 151 Ct.Cl.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Langdon Engineering & Mgt
Armed Services Board of Contract Appeals, 2025
Travelers Casualty & Surety of America v. United States
74 Fed. Cl. 75 (Federal Claims, 2006)
Crown Laundry & Dry Cleaners, Inc. v. United States
39 Cont. Cas. Fed. 76,575 (Federal Claims, 1993)
A.S. McGaughan Co. v. United States
37 Cont. Cas. Fed. 76,239 (Court of Claims, 1991)
Hydro Group, Inc. v. United States
35 Cont. Cas. Fed. 75,723 (Court of Claims, 1989)
Titan Pacific Construction Corp. v. United States
35 Cont. Cas. Fed. 75,693 (Court of Claims, 1989)
Roflan Co. v. United States
32 Cont. Cas. Fed. 73,207 (Court of Claims, 1985)
Troup Bros. v. United States
643 F.2d 719 (Court of Claims, 1980)
Conrac Corp. v. United States
558 F.2d 994 (Court of Claims, 1977)
James A. Mann, Inc. v. United States
535 F.2d 51 (Court of Claims, 1976)
Aerojet-General Corp. v. United States
467 F.2d 1293 (Court of Claims, 1972)
Chris Berg, Inc. v. United States
455 F.2d 1037 (Court of Claims, 1972)
H. N. Bailey & Associates v. The United States
449 F.2d 376 (Court of Claims, 1971)
J. A. Jones Construction Company v. The United States
395 F.2d 783 (Court of Claims, 1968)
James H. Clack v. The United States
395 F.2d 773 (Court of Claims, 1968)
Unicon Management Corporation v. The United States
375 F.2d 804 (Court of Claims, 1967)

Cite This Page — Counsel Stack

Bluebook (online)
364 F.2d 420, 176 Ct. Cl. 1363, 1966 U.S. Ct. Cl. LEXIS 263, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jefferson-construction-co-of-florida-a-florida-corporation-v-the-united-cc-1966.