Olympic Marine Services, Inc. v. United States

792 F. Supp. 461, 1992 U.S. Dist. LEXIS 7211, 1992 WL 102960
CourtDistrict Court, E.D. Virginia
DecidedMay 13, 1992
DocketCiv. A. 91-128-N
StatusPublished
Cited by3 cases

This text of 792 F. Supp. 461 (Olympic Marine Services, Inc. v. United States) is published on Counsel Stack Legal Research, covering District Court, E.D. Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Olympic Marine Services, Inc. v. United States, 792 F. Supp. 461, 1992 U.S. Dist. LEXIS 7211, 1992 WL 102960 (E.D. Va. 1992).

Opinion

OPINION AND ORDER

REBECCA BEACH SMITH, District Judge.

Following a bench trial, the court awarded plaintiff Olympic Marine Services, Inc. (hereinafter “Olympic”) $141,678, plus costs and prejudgment and postjudgment interest, after concluding that defendant United States breached its contract with Olympic. Specifically, the court equitably adjusted the contract, in which Olympic agreed to deactivate a United States public vessel, to reflect the unforeseen and substantially worse condition in which Olympic found the vessel. This matter comes before the court on Olympic’s motion, pursuant to the Equal Access to Justice Act (hereinafter “EAJA”), 28 U.S.C. § 2412, to recover from the United States costs, attorney fees, and expenses in the amount of $121,618.47. While the motion was under consideration, Olympic also submitted a motion to compel settlement of a claim that the parties had purportedly settled on the first day of trial. The United States had conditioned payments of the settlement upon Olympic’s written waiver of any claim for attorney fees and expenses associated with the settled claim. The nature of Olympic’s motion to compel makes it appropriate for consideration and resolution with Olympic’s motion for attorney fees and expenses.

*463 I. Facts

Olympic contracted with the United States to deactivate the M/V Cape Henry, a public vessel of the United States. 1 The agreed total price was $944,250 and the contract period was sixty days. As part of the contract, and without an opportunity for inspection, 2 Olympic agreed to drain and clean five fuel tanks for $45,000. After beginning work on the tanks, 3 Olympic discovered that the actual condition of the tanks would significantly increase the cost of completing the contract. A second disputed contract item required Olympic to fill several piping systems with antifreeze. Again, after beginning work, Olympic found that it needed additional antifreeze and materials to meet the contract specifications.

Olympic then requested the United States to modify the contract by providing additional compensation and extending the deadline. 4 The United States refused to acknowledge that it had enlarged the scope of the contract and thus denied Olympic’s request. Instead, the United States contended that the plain language of the contract obligated Olympic to clean the tanks at the agreed price, and that the United States had made no representations about the condition of the tanks. Olympic completed the job, but did so after the sixty-day contract deadline and at substantially greater expense than anticipated. In addition to its refusal to modify the contract, the United States withheld $16,108 as liquidated damages for the late completion of the job.

Pursuant to the disputes clause of the contract, 5 on October 16, 1990, Olympic submitted a claim to the Contracting Officer to recover its additional costs and the liquidated damages withheld by the United States. Olympic sought additional compensation of $628,759.01 for the additional labor, equipment rental, materials and waste disposal necessary to meet the contract specifications. Because of the Contracting Officer’s alleged delay in issuing a Final Decision, Olympic filed this action on February 27, 1991, pursuant to the Contract Disputes Act of 1978, 41 U.S.C. §§ 601-613. 6 Nearly two months later, and six months after Olympic first submitted its administrative claim, the Contracting Officer issued a written decision, on April 17, 1991, awarding Olympic $3,500 for the additional costs to complete work on the fuel tanks, $7,500 for delay costs, $12,656 for the additional costs to complete work on the piping system, and a $1,500 reduction of the liquidated damages withheld by the United States. The Final Decision satisfied neither party and the case proceeded to trial. 7

At the trial, the court found that the United States violated accepted marine practice regarding its handling of the fuel tanks before delivering the Cape Henry to Olympic for deactivation. (Excerpt of Pro *464 ceedings at 5 (Nov. 15, 1991) [hereinafter “Tr.”].) The United States failed to pump the fuel in the fuel tanks below the bell-mouths in accordance with industry custom; excessive and unusual sediments and scales contaminated the tanks; and the tanks contained a heavier oil than the parties anticipated. The United States’ own expert witness supported this conclusion, as well as the Contracting Officer. (Tr. at 9-10.) The court found that the United States had an affirmative duty to disclose the condition of the tanks, but failed to do so. The court thus concluded that “this is an appropriate circumstance factually and legally for an equitable adjustment,” (Tr. at 13), and awarded Olympic $141,678 for the additional expenses incurred to clean the fuel tanks, but did not award delay damages or a return of the liquidated damages withheld by the United States. The court also awarded Olympic its costs of action in the Final Judgment entered nunc ;pro tunc as of November 15, 1991.

II. Legal Analysis

Title 28 U.S.C. § 1920 enumerates recoverable costs, but costs do not include expenses and attorney fees. See 28 U.S.C. § 2412(a) (Supp.1991). The EAJA, however, authorizes the court to award attorney fees and expenses in any civil action brought against the United States if (1) the claimant is a “prevailing party”; (2) the United States’ position was not “substantially justified”; (3) “no special circumstances make an award unjust”; and (4) the claimant submits a fee application supported by an itemized statement to the court within thirty days of final judgment. 28 U.S.C. § 2412(b), (d)(1)(AHB); see Commissioner, INS v. Jean, 496 U.S. 154, 158, 110 S.Ct. 2316, 2319, 110 L.Ed.2d 134 (1990). On the litigated claims the parties contest only whether the United States’ position was “substantially justified.” On the settled claim, the parties contest only whether Olympic was the “prevailing party.” 8

A. United States Position Not Substantially Justified

The United States has the burden of justifying its position. Abernathy v. Clarke, 857 F.2d 237, 238 (4th Cir.1988) (citing Campbell v. Bowen,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
792 F. Supp. 461, 1992 U.S. Dist. LEXIS 7211, 1992 WL 102960, Counsel Stack Legal Research, https://law.counselstack.com/opinion/olympic-marine-services-inc-v-united-states-vaed-1992.