C. W. Schmid D/B/A C. W. Schmid Plumbing & Heating v. The United States

351 F.2d 651, 173 Ct. Cl. 302, 1965 U.S. Ct. Cl. LEXIS 238
CourtUnited States Court of Claims
DecidedOctober 15, 1965
Docket75-63
StatusPublished
Cited by12 cases

This text of 351 F.2d 651 (C. W. Schmid D/B/A C. W. Schmid Plumbing & Heating v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
C. W. Schmid D/B/A C. W. Schmid Plumbing & Heating v. The United States, 351 F.2d 651, 173 Ct. Cl. 302, 1965 U.S. Ct. Cl. LEXIS 238 (cc 1965).

Opinion

COWEN, Chief Judge.

On March 15, 1957, plaintiff was awarded a construction contract for an addition to the central heating plant at Minot Air Force Base, Minot, North Dakota. A major item of the work, and the item over which this present controversy centers, was the furnishing and installation of two high temperature hot water boilers. These specifications for the boilers provided that they could be the product of any qualified manufacturer, provided they met certain stated capacity and performance requirements. Existing boilers in the heating plant were manufactured by International Boiler Works Company (hereinafter referred to as International).

The invitation for bids required bidders to submit data on the boilers proposed to be furnished, including the name of the boiler manufacturer and various dimensions, capacities, and sizes. Plaintiff initially submitted a bid accompanied by a data sheet naming and describing the product of International. Before bids were opened, plaintiff telegraphed a reduction of $34,000 in his bid price. Plaintiff says that his initial bid price was based on a quotation received from International, while the reduction was based upon a subsequent lower quotation from Combustion Engineering, Inc. (hereinafter referred to as Combustion). Another bidder for the job offered International boilers, while a third bidder proposed to install either International or Combustion boilers. The equipment of both manufacturers complied in all particulars with the requirements of the specifications.

The award to plaintiff was based on the price as revised by the telegraphic modification. Shortly thereafter, plaintiff signed a firm contract with Combustion to furnish the boilers in question. On May 17, 1957, the defendant’s Architect-Engineer rejected the shop drawings on the Combustion boilers on the ground that they did not conform to the equipment that had been described in the bid data sheets.

Plaintiff protested the rejection in a telegram dated May 23, 1957. He was informed on May 27 thereafter that equipment which did not conform to specifications and data sheets submitted with the bid would be rejected. He was also advised of his appeal rights and told that, pending final decision of the dispute, he was obligated to proceed diligently with the performance of the contract in accordance with the contracting officer’s decision. The written decision *653 and findings of fact of the contracting officer were issued on June 26, 1957.

After the award of the contract and before the dispute over the boilers arose, plaintiff had begun construction of the concrete foundations for the Combustion boilers. Because of the differences in dimensions, the International boilers would not fit these foundations. On July 2, 1957, the contracting officer pointed out this fact to plaintiff and stated that:

You are hereby directed to cease all construction on the boiler foundation until you have obtained approved shop drawings. You are also directed to submit shop drawings to the Architect-Engineer covering the correct boiler installation.
Your delay in submitting corrected shop drawings will seriously affect your ability to complete the work within the time specified. Unless satisfactory evidence is received by this office on or before 12 July 1957 that you have submitted proper shop drawings and have taken measures for removal of the improper foundations, such failure will, in accordance with Clause 5 of your contract, be considered lack of prosecution of the work with such diligence as will insure its completion within the time specified and will be the basis of a recommendation that your right to proceed with work under the contract be terminated.

Plaintiff stopped work on the boiler foundations, but he did not remove them. He then requested shop drawings from International which refused to supply them until it received a firm order. Plaintiff refused to place the order, since he felt that he had a right to install Combustion boilers. Therefore, he did not submit at any time shop drawings on the International boilers. The directive of the contracting officer was repeated several times, with matters remaining in status quo.

On July 11,1957, the plaintiff appealed the June 26 decision of the contracting officer. At a meeting convened on August 22, 1957, to discuss whether plaintiff’s contract should be terminated for default, the contracting officer announced that plaintiff’s appeal had been sustained by the Chief of Engineers and that plaintiff would be permitted to install Combustion boilers. Both the Chief of Engineers and the Comptroller General, to whom the question was referred, decided that the contracting officer had erred in requiring the International equipment, since both boilers complied with the specifications.

Subsequently, the shop drawings covering Combustion boilers were resubmitted and promptly approved. The contract was completed within the date fixed for completion, as extended pursuant to modifications not pertinent to this case.

Plaintiff claims that shortly after he took, his appeal, the boilers which had been reserved for him on Combustion’s fabrication schedule were assigned to another purchaser because of plaintiff’s inability to submit approved shop drawings. Plaintiff also asserts that as a consequence of the delay between the original submission of the drawings and their subsequent approval, the shipping date for the boilers was revised from July 1, 1957 to November 1, 1957, thus forcing the installation work into the winter months.

After installing the Combustion equipment, plaintiff submitted a claim for increased costs occasioned by the contracting officer’s rejection of the Combustion boilers and his order stopping work on the Combustion foundations. The contracting officer, the Corps of Engineers Board of Contract Appeals, and the Armed Services Board of Contract Appeals each rejected plaintiff’s claims, the latter by decision dated August 3, 1962.

In the administrative proceedings the parties stipulated that if plaintiff had proceeded to install International equipment during the period the appeal was pending, plaintiff’s costs, in terms of cancellation charges, the price differential between the two makes of boilers, the cost of taking out and rebuilding the Combustion foundations, and other *654 charges, would have exceeded the $60,000 now claimed and that the costs of compliance, if incurred, would have seriously jeopardized the contractor’s solvency. After plaintiff’s claim for increased costs had been denied by the contracting officer and the Corps of Engineers Board of Contract Appeals, the case was submitted to the ASBCA solely on the issue of whether the stipulated facts constituted a basis upon which relief could be granted under the Suspension of Work clause of the contract. The Board found that the contracting officer erroneously interpreted the contract to require the use of International boilers. As for the claimed suspension of work, the Board concluded that the work stoppage resulted from the plaintiff’s refusal to comply with the contracting officer’s directives pending appeal, rather than from any order issued by the contracting officer to suspend the work completely.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lassiter v. United States
60 Fed. Cl. 265 (Federal Claims, 2004)
Valley View Enterprises, Inc. v. United States
40 Cont. Cas. Fed. 76,920 (Federal Claims, 1996)
Tgs International, Ltd. v. The United States
949 F.2d 402 (Federal Circuit, 1991)
CCM Corp. v. United States
36 Cont. Cas. Fed. 75,876 (Court of Claims, 1990)
Thoen v. United States
32 Cont. Cas. Fed. 72,876 (Court of Claims, 1984)
J. L. Simmons Company, Inc. v. The United States
412 F.2d 1360 (Court of Claims, 1969)
Jefferson Construction Company v. The United States
392 F.2d 1006 (Court of Claims, 1968)

Cite This Page — Counsel Stack

Bluebook (online)
351 F.2d 651, 173 Ct. Cl. 302, 1965 U.S. Ct. Cl. LEXIS 238, Counsel Stack Legal Research, https://law.counselstack.com/opinion/c-w-schmid-dba-c-w-schmid-plumbing-heating-v-the-united-states-cc-1965.