Thoen v. United States

32 Cont. Cas. Fed. 72,876, 5 Cl. Ct. 823, 1984 U.S. Claims LEXIS 1319
CourtUnited States Court of Claims
DecidedAugust 31, 1984
DocketNo. 425-83C
StatusPublished
Cited by10 cases

This text of 32 Cont. Cas. Fed. 72,876 (Thoen v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Thoen v. United States, 32 Cont. Cas. Fed. 72,876, 5 Cl. Ct. 823, 1984 U.S. Claims LEXIS 1319 (cc 1984).

Opinion

OPINION

LYDON, Judge:

This contract case comes before the court on defendant’s motion for partial dismissal of plaintiff’s “Petition” (complaint) and plaintiff’s opposition thereto.1 The action is brought as a “direct access” case under section 10(a)(1) of the Contract Disputes Act of 1978, 41 U.S.C. § 609(a)(1) (1980). Defendant seeks dismissal of three “Items” of a four-item claim set forth in the complaint on the ground plaintiff failed to properly present these three claim items to the contracting officer for decision. Upon consideration of the complaint and the briefs of the parties, and without oral argument, the court concludes that plaintiff’s complaint should be dismissed.

I.

Plaintiff, an individual, is engaged in the business of providing consulting services. On July 18, 1978, plaintiff entered into a contract with the United States Department of the Army (DOA) to provide a working formula, with complete theoretical analysis, for predicting small journey bearing efficiency for the fixed contract price of $24,880. The contract performance period was 9 months, i.e., the completion date was April 30, 1979, and the contract price was to be paid at the completion of the contract upon the submission by plaintiff to the Contract Project Officer of one copy of a Final Technical Report for approval. During the period of contract performance, plaintiff was also required to submit monthly letter progress reports to the Contract Project Officer.

In a letter dated August 8, 1979, plaintiff, acknowledging that the contract was to be completed in 9 months and setting forth reasons for the delay in performance, requested “that the contract expiration date be extended to 31 December, 1979, with no increase or decrease in consideration.” On January 2, 1980, a contract modification, agreed to by plaintiff, extended the period of contract performance to April 30, 1980, and provided that, “[t]he total contract amount of $24,880 remains unchanged as a result of this action.” The contract performance period was subsequently extended until April 30, 1982, by contract modifications agreed to by plaintiff with no change in contract price as a result of said actions.

Plaintiff failed to submit on April 30, 1982, as required by the contract, a Final Technical Report on the project. On May 12, 1982, the contracting officer sent a “show cause” letter to plaintiff, advising that he had failed to perform the contract within the time required by the terms thereof and informing him that the government was considering termination of the [825]*825contract for default. Plaintiff was requested to respond to said letter within 10 days, giving reasons or excuses for his failure to perform the contract within the required time specified in the contract, as modified.

On May 27, 1982, plaintiff responded to the May 12, 1982 “show cause” letter. Plaintiff advised that the study (project) turned out to be more complex than anyone anticipated, that he had overrun the budget before he even identified all the factors that embraced the study project, and that he “spent four times the amount of money in the budget.” He further advised: “I could of course have terminated the contract at the beginning of the overrun, but I elected to continue, because the Army led me to believe that there would be a follow-on contract for the study of tooth friction * * *.” After a technical discussion of bearing friction and other matters, plaintiff closed his May 27, 1982, letter, responding to the “show cause” letter, as follows: “In short, I feel that so long as the Army does not have the money to rectify or prevent design deficiencies, then it should not expect me to put aside other work, just to wrap up a contract that would pay me only a small fraction of what I spent.”

On June 21, 1982, the contracting officer issued his final decision, notifying plaintiff that his contract with DOA was terminated for default for failure to complete the contract within the time required by its terms. The contracting officer also stated that plaintiffs failure in this regard had not been shown to have been caused by factors beyond plaintiffs control or without his fault or negligence. The decisional letter of the contracting officer advised plaintiff of his appeal rights.

On December 15, 1982, plaintiff wrote a detailed and rambling letter to the contracting officer which set forth a technical discussion relating to friction. Plaintiff, in this letter, also referenced his difficulties in performing the contract work and asserted that he was led to believe that there would be a follow-on contract for study of tooth (gear) friction and that this expectation was the only reason he continued to work on the contract and continued to expend money since he otherwise could have terminated the contract at the beginning of the overrun.

In his complaint, filed in this court on June 27, 1988, plaintiff seeks recovery as follows:

Item 1 — Judgment for $24,880, the original contract price;
Item 2 — Judgment for the fair price of his services which plaintiff estimates to be at least $105,000. Plaintiff alleges that the additional effort he performed in this regard was requested by defendant’s authorized representatives;
Item ■? — -Judgment for the value of his services realized by defendant in an amount estimated by plaintiff is to be at least $100,000; and
Item 4 — Judgment for $15,000 for attorney’s fees and costs.

Defendant did not file an answer to said complaint but instead filed the Motion For Partial Dismissal at bar.

II.

The basis for defendant’s motion for dismissal of claim Items (or Counts) 2, 3 and 4, supra, is the fact that plaintiff never presented said claims, properly certified, to the contracting officer for decision. Absent a contracting officer’s final decision on a written and certified claim, there can be no direct access action brought in this court. Milmark Services, Inc. v. United States, 231 Ct.Cl. 954, 956 (order dated Sep. 3, 1982); Paragon Energy Corp. v. United States, 227 Ct.Cl. 176, 181, 645 F.2d 966, 969-970 (1981); Conoc Constr. Corp. v. United States, 3 Cl.Ct. 146, 147 (1983). Plaintiff’s reliance on pre-Contract Disputes Act Board decisions is misplaced. See e.g., River Associates, Inc., CGBCA No. T-166, 65-2 BCA 115,039. This Act now mandates a decision by the contracting officer for direct access jurisdiction to this court. Had plaintiff presented these claim Items to the contracting officer in certified form, as required by the Contract Disputes Act, consideration may have been given to [826]*826a fair and equitable settlement thereof, one of the purposes of the statutory certification requirement. See Warchol Constr. Co. v. United States, 2 Cl.Ct. 384, 391 (1983).2 Further, the dollar information relative to said claim Items 2, 3 and 4 was readily available to plaintiff at the time of the default, or shortly thereafter at the latest.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Clark Mechanical Contractors v. United States
34 Cont. Cas. Fed. 75,283 (Court of Claims, 1987)
Fredenburg v. United States
33 Cont. Cas. Fed. 74,503 (Court of Claims, 1986)
Gunn-Williams v. United States
32 Cont. Cas. Fed. 73,703 (Court of Claims, 1985)
Richard L. Thoen v. The United States
765 F.2d 1110 (Federal Circuit, 1985)
Rider v. United States
32 Cont. Cas. Fed. 73,473 (Court of Claims, 1985)
Loftin v. United States
6 Cl. Ct. 596 (Court of Claims, 1984)
Hulsey v. United States
6 Cl. Ct. 593 (Court of Claims, 1984)
T.J.D. Services, Inc. v. United States
32 Cont. Cas. Fed. 72,871 (Court of Claims, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
32 Cont. Cas. Fed. 72,876, 5 Cl. Ct. 823, 1984 U.S. Claims LEXIS 1319, Counsel Stack Legal Research, https://law.counselstack.com/opinion/thoen-v-united-states-cc-1984.