Chalker & Lund Co. v. United States

107 F. Supp. 734, 123 Ct. Cl. 381, 1952 U.S. Ct. Cl. LEXIS 52
CourtUnited States Court of Claims
DecidedOctober 7, 1952
DocketNo. 47694
StatusPublished
Cited by4 cases

This text of 107 F. Supp. 734 (Chalker & Lund Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Chalker & Lund Co. v. United States, 107 F. Supp. 734, 123 Ct. Cl. 381, 1952 U.S. Ct. Cl. LEXIS 52 (cc 1952).

Opinion

Littleton, Judge,

delivered the opinion of the court:

The plaintiff entered into a contract with the defendant dated March 26, 1943, for the construction of a number of warehouses and a repair building at the Army Air Forces Depot at 36th Street Airport, Miami, Florida. The original specifications in the Government’s invitation to bid required the contractor to “perform all work of clearing, excavating, filling, backfilling, and grading,” required in connection with the construction.

In February 1943, prior to submission of plaintiff's bid, the Government entered into a contract with the Hooper Construction Company, for the necessary filling and rough grading, and accordingly the original specifications in the invitation to plaintiff to bid were amended on March 17, 1943, to eliminate the work of filling and rough grading. Defendant notified plaintiff of the amendment by telegram on March 20, 1943, stating in part: “All earth fill will be placed by others. Building contractor will fine grade fill only.”

The amended specifications included the following:

1A-04. Excavation, -filling and grading. — (a) Rough grading over the building site is covered under another contract, including compaction of the fill, specified as follows:
Buildings having elevated concrete floor slabs on fill, shall have the fill carefully placed to the proper elevation.
* * * The embankments shall be placed in layers not exceeding six inches, each layer to be compacted by puddling, tamping, or rolling to 100 percent of the maximum density at optimum moisture.
(b) Under this contract, the contractor shall complete the grading, as necessary to place the concrete slabs and to construct the foundations, and shall base his quotations upon estimates of the work required to accomplish this, which estimates shall be based upon the contractor’s visual inspection of the grading work actually ac[402]*402complished. No separate payment nor any adjustment of the contract price will be allowed for any grading done under this contract.
1A-05. Section III — Concrete worlc. — (a) All concrete slabs on earth fill shall be 6 in. thickness.

Plaintiff submitted its bid on the contract under the amended specifications on March 24, 1943, and the contract was awarded to plaintiff March 26, 1948. As far as filling and grading were concerned, plaintiff had only to fine grade the fill placed and rough graded by the Hooper Company.

It is from the nature of the material used by Hooper in the fill that the controversy here arises, under plaintiff’s first cause of action. The fill placed by Hooper consisted principally of a materia] technically known as “oolite” containing a high percentage of lime. The material was excavated from under water and was soft when dumped on the fill. When it became dry, however, after about a week, it became quite hard. Plaintiff had planned to perform the fine grading by hand labor, using shovels at first and then leveling the fill at the specified elevation with straight edges aftei1 the screeds for the concrete slab floors were set in place. This is a method commonly used in fine grading a sand fill.

Because of the hardness of the fill material, however, plaintiff was unable to fine grade it with hand labor as planned, and had to bring in a scarifier and power grader to accomplish the work. After the oolite had been scarified and graded, it became necessary for plaintiff to put sand on top to achieve a fine grade exactly 6 inches below the finished floor level, as required by the specifications. As a result of the extra work occasioned by the use of oolite in the fill by the Hooper Company, plaintiff’s costs were considerably above those originally anticipated by plaintiff on this particular item when it submitted its bid to defendant. It is for this difference in costs that plaintiff sues in its first cause of action.

Plaintiff contends in effect that its contract did not contemplate the use of oolite in the fill, and that plaintiff could not reasonably have been expected to anticipate the use of oolite as a fill material. Plaintiff asserts rather that its [403]*403obligation under the contract was to fine grade a sand fill and that the use of oolite instead of sand was a breach of the contract by the Government.

In support of its position plaintiff relies upon the telegram of March 20, 1943, and the amended specifications which referred to an “earth fill.” Plaintiff contends that the term “earth fill” did not include an oolite fill. Plaintiff also points to that part of the amended specifications which required compaction of the fill by puddling, tamping, or rolling. Plaintiff argues that this method of compaction was inappropriate to compaction of oolite but was entirely appropriate to compaction of a sand fill.

Plaintiff further cites that part of the amended specifications which increased from 4 to 6 inches the thickness of the concrete floor slabs to be placed on the fill. In this regard plaintiff argues that an increase in thickness of the floor slab would not normally have been consistent or necessary with the use of a high content limestone fill such as oolite, but was consistent with the use of a softer fill such as sand.

These arguments are advanced to show that plaintiff reasonably construed the contract to contemplate the fill would consist of sand and not an oolite. Whatever the force of these arguments in the absence of other factors, however, they are not persuasive of the validity of plaintiff’s position in the face of certain other specific provisions in plaintiff’s contract.

The invitation to bid contained the following provision:

XII. Investigation oe conditions: Bidders are expected to visit the locality of the work and acquaint themselves with all available information concerning the nature of materials to be excavated from structure excavations and the local conditions bearing on trans-portion [sic], handling and storage of materials. They are also expected to make their own estimates of the facilities needed, difficulties in attending the execution of the proposed contract, including local conditions, availability of labor, water, electric power, roads, uncertainties of weather, and other contingencies. In no event will the Government assume any responsibility whatever for any interpretation, deduction, or conclusions drawn from examination of the site. At the bidder’s [404]*404request, a representative of the Government will point out the site of the proposed operations. Failure to acquaint himself with all available information concerning these conditions will not relieve the successful bidder from responsibility for properly estimating the difficulties and costs of successfully performing the work.

Paragraph 1A-04 of the amended specifications, supra, was equally explicit in charging plaintiff with knowledge of the grading work at the site.

Plaintiff did not send a representative, its superintendent, to inspect the site until receipt of the amended specifications. No borrow pit was actually opened when the superintendent visited the project area. The first pit was opened by the Hooper Company on March 23,1943, the day after the superintendent’s visit, and the day before plaintiff’s bid was submitted.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Elastomeric Roofing Associates, Inc. v. United States
26 Cl. Ct. 1106 (Court of Claims, 1992)
Thoen v. United States
32 Cont. Cas. Fed. 72,876 (Court of Claims, 1984)
Hargrave v. United States
130 F. Supp. 598 (Court of Claims, 1955)

Cite This Page — Counsel Stack

Bluebook (online)
107 F. Supp. 734, 123 Ct. Cl. 381, 1952 U.S. Ct. Cl. LEXIS 52, Counsel Stack Legal Research, https://law.counselstack.com/opinion/chalker-lund-co-v-united-states-cc-1952.