Tgs International, Ltd. v. The United States

949 F.2d 402, 1991 U.S. App. LEXIS 31497, 1991 WL 202152
CourtCourt of Appeals for the Federal Circuit
DecidedOctober 8, 1991
Docket90-1440
StatusUnpublished

This text of 949 F.2d 402 (Tgs International, Ltd. v. The United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tgs International, Ltd. v. The United States, 949 F.2d 402, 1991 U.S. App. LEXIS 31497, 1991 WL 202152 (Fed. Cir. 1991).

Opinion

949 F.2d 402

37 Cont.Cas.Fed. (CCH) P 76,188

NOTICE: Federal Circuit Local Rule 47.8(b) states that opinions and orders which are designated as not citable as precedent shall not be employed or cited as precedent. This does not preclude assertion of issues of claim preclusion, issue preclusion, judicial estoppel, law of the case or the like based on a decision of the Court rendered in a nonprecedential opinion or order.
TGS INTERNATIONAL, LTD., Appellant,
v.
The UNITED STATES, Appellee.

No. 90-1440.

United States Court of Appeals, Federal Circuit.

Oct. 8, 1991.

Before RICH, PAULINE NEWMAN and ARCHER, Circuit Judges.

PAULINE NEWMAN, Circuit Judge.

TGS International, Ltd. appeals the decision of the Armed Services Board of Contract Appeals1 affirming in part a contracting officer's decision denying TGS's claims for certain adjustments. We affirm in part, reverse in part, and remand.

OPINION

Appeal is taken under the Contract Disputes Act, 41 U.S.C. §§ 601 et seq. Review of the Board's decision is governed by 41 U.S.C. § 609(b). A decision on a question of fact

shall not be set aside unless the decision is fraudulent, or arbitrary, or capricious, or so grossly erroneous as to necessarily imply bad faith, or if such decision is not supported by substantial evidence.

41 U.S.C. § 609(b). The appellate tribunal must decide questions of law for itself, John T. Brady & Co. v. United States, 693 F.2d 1380, 1384 (Fed.Cir.1982) (no finality attaches to the Board's conclusions of law); although the Board's interpretations of law are carefully considered, Erickson Air Crane Co. of Washington, Inc. v. United States, 731 F.2d 810, 814 (Fed.Cir.1984).

The contract between TGS and the Naval Facilities Engineering Command was for the design and construction of a warehouse and supply project at the Ali Al-Salem Air Base in Kuwait. TGS concentrates this appeal on four areas that it states were subject to government-caused (generally the Kuwait government) delays that affected TGS's costs and time of performance: (1) delivery of two man-lifts known as Demag Pickers; (2) delivery of caulking; (3) customs' delays of electrical equipment and materials; and (4) delays in providing full electric power. Increased labor costs are claimed under the War Risks clause. TGS emphasizes that in this tightly audited contract there was no flexibility to accommodate contingencies, and that its increased costs of performance merit equitable and legal adjustment.

I. Delay Damages

The contract provided that the Kuwait government "shall deliver" certain listed property "at the times and locations stated [in the schedule]", and that "if not so delivered ... the Contracting Officer shall ... if the facts warrant such action, equitably adjust any affected provisions ... pursuant to the procedures of the 'Changes' clause." Although the government (the United States is representing all government interests in this litigation) argues that the government can not be liable under this clause because specific delivery dates were not included in the schedule, when delivery dates are not specified the delivery must be within a reasonable time in view of the circumstances of the contract. See Commerce Int'l Co. v. United States, 338 F.2d 81, 87 (Ct.Cl.1964) (government's obligation measured "by the reasonable expectations of the parties in the special circumstances in which they contracted").

1. The Demag Pickers

The Board acknowledged the delay in delivery of two Demag Pickers, for reasons outside of TGS's control. TGS argues that the late delivery of the two Pickers affected the cost of performing the rewarehousing in Building 18-2. The Board found that "TGS's job progress was not impacted", due to concurrent delays that were the responsibility of TGS and because the building was accepted with the pickers as a punch list item. This finding, which depended in part on the evaluation of evidence including the credibility of witnesses, will not here be disturbed. See Gyromat Corp. v. Champion Spark Plug Co., 735 F.2d 549, 552 (Fed.Cir.1984) (credibility of witnesses is left to trier of fact). We affirm the Board's decision on this issue.

2. Caulking

Due to a series of mishaps and errors, none caused by TGS, caulking material to seal the Butler Stone panels, initially ordered on June 19, 1984, did not arrive until April 4, 1985. TGS states that the delay in receipt of the caulking material necessitated the extra step of cleaning out sand and dirt that wind storms had blown into the cracks, delayed the acceptance of the building, and caused other inefficiencies such as the need to twice erect scaffolding.

The Board found that "the confusing state of the present record prevents us from assigning fault for this delay", and also that the issue was moot for lack of impact upon TGS's work effort. The Board erred in weighing the issue of fault against TGS, for whether or not the reasons could be precisely identified, it was clear that the delivery delays (for example, the disappearance of the first shipment) were out of TGS's control. However, the Board's ruling that TGS did not establish impact must be sustained, for there was substantial evidence of concurrent delay attributable to TGS in other areas. The general rule regarding concurrent delay is that:

Where both parties contribute to the delay "neither can recover damage, unless there is in the proof a clear apportionment of the delay and the expense attributable to each party."

Blinderman Constr. Co. v. United States, 695 F.2d 552, 559 (Fed.Cir.1982) (quoting Coath & Goss, Inc. v. United States, 101 Ct.Cl. 702, 714-15 (1944)). The Board found that the project had suffered significant delays caused by TGS, manifested particularly in the structural steel shipments. This finding is supported by substantial evidence and must be sustained thus defeating recovery by TGS of the asserted additional cost of performance. However, in accordance with Blinderman, liquidated damages for this period of delay shall be remitted.

3. Electrical Materials

TGS states that certain critical air shipments of electrical equipment and materials were unreasonably delayed by Kuwait customs authorities, thereby delaying completion. Also involved were prolonged periods of shipping and delivery and customs delay in the switchgear, magnesium backfill, and some other items.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
949 F.2d 402, 1991 U.S. App. LEXIS 31497, 1991 WL 202152, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tgs-international-ltd-v-the-united-states-cafc-1991.