Skanska Usa Building, Inc. v. United States

CourtUnited States Court of Federal Claims
DecidedMarch 21, 2013
Docket07-143C
StatusUnpublished

This text of Skanska Usa Building, Inc. v. United States (Skanska Usa Building, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Skanska Usa Building, Inc. v. United States, (uscfc 2013).

Opinion

In the United States Court of Federal Claims No. 07-143 C (Filed: March 21, 2013)

************************************* SKANSKA USA BUILDING, INC., * * Plaintiff, * * v. * * THE UNITED STATES, * * Defendant. * *************************************

OPINION AND ORDER

Before the court are the parties’ cross-motions for summary judgment and renewed cross- motions for summary judgment. In this action, plaintiff seeks to recoup the additional costs it incurred to dispose of certain excavated material upon the discovery of lead contamination in that material during contract performance. According to plaintiff, its costs to dispose of the lead- contaminated material were greater than the costs that it reasonably expected to incur at the time it submitted its bid. Defendant, on the other hand, contends that the costs to dispose of the lead- contaminated material were included in the total contract price. For the reasons set forth below, the court grants in part and denies in part both parties’ motions for summary judgment.

I. BACKGROUND

On March 31, 2003, the United States Army Corps of Engineers (“Corps”) awarded contract number DACA67-03-C-0203, FY03 Whole Barracks Renewal, Fort Lewis, WA, to Skanska USA Building, Inc. (“Skanska”).1 App. 1-2. The contract concerned the construction of

1 The court derives the facts in this section from the Declaration of Wes Johnson in Support of Plaintiff’s Motion for Partial Summary Judgment on Liability (“Johnson Decl.”); the exhibit attached to Mr. Johnson’s declaration (“Johnson Ex.”); the Declaration of Dave Berglund in Support of Plaintiff’s Motion for Partial Summary Judgment on Liability (“Berglund Decl.”); the Declaration of Terry R. Marston in Support of Plaintiff’s Motion for Partial Summary Judgment on Liability (“Marston Decl.”); the exhibits attached to Mr. Marston’s declaration (“Marston Ex.”); the appendix to Defendant’s Motion for Summary Judgment (“App.”); the exhibit attached to Defendant’s Reply in Support of Its Motion for Partial Summary Judgment on Liability (“Def.’s Ex.”); and the exhibit attached to the Supplemental Declaration of Terry R. Marston in Support of Plaintiff’s Motion for Partial Summary Judgment on Liability (“Marston nine buildings at North Fort Lewis. Marston Ex. 11 at 4. Skanska retained Nacon Inc. (“Nacon”) to serve as a subcontractor to perform some of the work required by the contract. Id. at 5. Nacon, in turn, retained Active Construction, Inc. (“Active”) to perform one of those areas of work–the earthwork.2 Id. at 7; Marston Ex. 12 at 4. The earthwork generally consisted of the excavation, transportation, and placement of soil and other material. See Marston Ex. 3 at 2, 4.

In preparing its proposal to perform the earthwork portion of the contract, Active’s lead estimator, Dave Berglund,3 reviewed both the contract documents and the reports from a site visit. Berglund Decl. ¶ 8. Mr. Berglund found that neither the contract documents nor the site visit reports indicated that the soil on the project site was contaminated. Id. ¶¶ 9-11. Further, Mr. Berglund’s review of the contract documents led him to understand that “any soils that were not needed on the project would have to be disposed away from Ft. Lewis,” id. ¶ 20, and that the contractor had the right to retain the salvage value of the surplus soil, id. ¶¶ 14-16. Mr. Berglund ultimately estimated that Active would likely need to dispose of “several thousand” cubic yards of surplus soil. Id. ¶ 21. Although the cost of hauling and disposing that amount of surplus soil was normally high, id. ¶ 22, Mr. Berglund knew “that there was a market for clean fill material (soil) through which” Active could recover any hauling and disposal costs, id. ¶ 23. Accordingly, because he believed the contract permitted Active to “retain any savings it could obtain in the course of disposing of any surplus soil [Active was] required to remove from the site,” id. ¶ 22, he did not include any amounts for this expense in Active’s proposal, id. ¶¶ 22, 24.

Through the course of the project, the contractors accumulated a stockpile of approximately 15,000 cubic yards of material. See id. ¶ 25; Marston Ex. 1 at 1-2. In Request for Information number 318 dated September 26, 2003, Skanska posed the following question to the Corps:

Due to a surplus in satisfactory soils on the project, approximately 15,000 cubic yards, Active is requesting permission to place a portion of this material in the low area next to the revised location of the North irrigation vault per FY03 RFI #25. . . . Active is also requesting that [it] be allowed to remove the remaining material from the project site.

Please note that this work will be done at no cost to the Government.

Supp’l Ex.”). 2 Active was a civil construction firm that had been doing business in the Fort Lewis region for forty-one years. Berglund Decl. ¶ 4. 3 Mr. Berglund had seventeen years of experience working in civil construction in the Fort Lewis region. Berglund Decl. ¶ 5.

-2- Marston Ex. 1 at 1. On October 1, 2003, Jim Packard, the Corps’ project engineer,4 Marston Ex. 4 at 1, responded: “Fort Lewis has no problem with us depositing surplus satisfactory soils in the low area . . . . Coordinated with Larry Mc Vay of Public Works 1 Oct 03,” Marston Ex. 1 at 1. Skanska followed-up Mr. Packard’s response with Request for Information number 318R, which contained the same question and answer exchange as well as an additional inquiry:

Post Note: In response to conversation between Jason Hynes and Doug Mc[N]iesh with Skanska and Jim Packard and Tom Wilkin with the [Corps] on 10/3/03,5 Active has noted that approximately 5,000 cubic yards of soil will be spread near the North irrigation vault. . . . Active is requesting to remove 10,000 cubic yards of soil from the Post. Please confirm that this is acceptable.

Id. at 2 (footnote added). Mr. Packard provided the following response on October 7, 2003: “Post Note: Confirmed. Regrade elevated area to grade to existing catch basin and/or add rings to adjust height of same. Continue erosion control around catch basin.” Id.

In accordance with the Corps’ apparent permission to dispose of the surplus soil off of Fort Lewis,6 Active made arrangements with ESE Corporation on March 3, 2004, to haul away the soil at no cost to Active. Berglund Decl. ¶ 25; Johnson Decl. ¶ 5; Johnson Ex.; App. 36. ESE Corporation planned to use the soil on its own project, but conditioned its agreement with Active on soil sampling certifying that the soil was not contaminated. Johnson Decl. ¶¶ 4, 6; Johnson Ex.

4 Mr. Packard described himself as the Corps’ “voice to the contractor for day-to-day work,” but as lacking the authority to “direct changes to the contract . . . .” Marston Ex. 8 at 9. He further explained that the administrative contracting officer had the authority to issue change orders for work priced below $100,000 and that all other changes were within the authority of the contracting officer. Id. at 10. 5 Mr. Wilkin was the assistant project engineer. See Marston Decl. ¶ 10. 6 The court writes “apparent” because deposition testimony from November 2007 reflects some dispute within the Corps regarding the meaning of Mr. Packard’s response to the amended request for information. Compare Marston Ex. 7 at 6-7 (indicating the view of the contracting officer, Nancy Gary, that the Corps had authorized Active to remove the surplus soil from Fort Lewis), and Marston Ex. 9 at 4, 7-8 (indicating Mr. Wilkin’s view that the Corps had confirmed the acceptability of Active removing the surplus soil from Fort Lewis), with App. 70-72 (indicating Mr. Packard’s view that the requests for information merely reflected the Corps’ written confirmation of prior oral agreements concerning the placement of some surplus soil near the irrigation vault).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
International Data Products Corp. v. United States
492 F.3d 1317 (Federal Circuit, 2007)
Teg-Paradigm Environmental, Inc. v. United States
465 F.3d 1329 (Federal Circuit, 2006)
Maxima Corporation v. The United States
847 F.2d 1549 (Federal Circuit, 1988)
H.B. Mac, Inc. v. United States
153 F.3d 1338 (Federal Circuit, 1998)
Ford Motor Company v. United States
157 F.3d 849 (Federal Circuit, 1998)
Varilease Technology Group, Inc. v. United States
289 F.3d 795 (Federal Circuit, 2002)
Nvt Technologies, Inc. v. United States
370 F.3d 1153 (Federal Circuit, 2004)
Egyptian Goddess, Inc. v. Swisa, Inc.
543 F.3d 665 (Federal Circuit, 2008)
Miller Elevator Co. v. United States
39 Cont. Cas. Fed. 76,635 (Federal Claims, 1994)
Mansfield v. United States
71 Fed. Cl. 687 (Federal Claims, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
Skanska Usa Building, Inc. v. United States, Counsel Stack Legal Research, https://law.counselstack.com/opinion/skanska-usa-building-inc-v-united-states-uscfc-2013.