Jemison & Partners, Inc.

CourtArmed Services Board of Contract Appeals
DecidedDecember 5, 2022
DocketASBCA No. 62928
StatusPublished

This text of Jemison & Partners, Inc. (Jemison & Partners, Inc.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jemison & Partners, Inc., (asbca 2022).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS Appeal of - ) ) Jemison & Partners, Inc. ) ASBCA No. 62928 ) Under Contract No. W912P8-19-C-0018 )

APPEARANCE FOR THE APPELLANT: W. Lee Kohler, Esq. Kohler Construction Law, APLC Metairie, LA

APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq. Engineer Chief Trial Attorney William G. Meiners, Esq. Engineer Trial Attorney U.S. Army Engineer District, New Orleans

OPINION BY ADMINISTRATIVE JUDGE O’CONNELL

This is a dispute about topsoil, or, more specifically, a dispute about whether appellant would be paid for the actual quantities of soil placed, or simply a lump sum. Appellant seeks $53,104.80. The parties waived a hearing and submitted the appeal on the record under Board Rule 11. The Board denies the appeal.

FINDINGS OF FACT

1. The parties entered into the above-captioned contract for greenspace restoration on February 15, 2019. The work included the replacement of topsoil and the planting of sod and trees along the median of Jefferson Avenue in Orleans Parish, Louisiana at a price of $747,298.57. (R4, tab 9 at 1, 3-5, 39, 44) 1

2. The Corps issued the solicitation on November 16, 2018 (R4, tab 4 at 1). The bid schedule for the solicitation listed an “estimated quantity” of 2,355 cubic yards (CY) of topsoil and requested unit price bids, which would result in an “estimated amount” for that contract line item number (CLIN 0002). Note 1 to the bid schedule provided that:

The Contractor shall verify all quantities on the plan; quantities are provided as an aid to bidders only.

1 Rule 4 citations are to the .pdf page number in the electronic file. Quantity takeoff mistakes made by the Contractor shall be no cause for additional costs to the Government.

(R4, tab 4 at 8) (emphasis in original) The bid schedule, with Jemison’s bid numbers, was included in the contract but the word “estimated” was omitted from the column heading so that “Estimated Quantity” became “QTY” and “Estimated Amount” became “Total Amount.” Note 1, however, was included in the contract (R4, tab 9 at 41).

3. The Standard Form 1449 Continuation Sheet in the solicitation (and the contract) identified CLIN 0002 as “FFP” or firm-fixed price (R4, tab 4 at 3; tab 9 at 3). The Board finds that a reasonably prudent bidder would have understood from reading the Continuation Sheet in conjunction with the Bid Schedule that the price per CY was fixed but the quantity of topsoil was an estimate.

4. The Payment Procedures section of the solicitation, at Section 1.4, Payments to the Contractor, required the submission of invoices and “quantity backup data by the [c]ontractor,” and provided that upon initial site work acceptance Jemison would be paid “100% contract cost for topsoil” (R4, tab 4 at 15). This provision was included in the contract (R4, tab 9 at 48).

5. The Excavation and Fill section of the solicitation at Part 4, Measurement and Payment, provided:

Measurement for work required under this section shall be an in place topsoil cubic yard measurement. The topsoil quantities are provided as an aid to bidders only. The contractor shall take measurements subtracting rootball volume at each area requiring excavation and soil replacement. . .

(R4, tab 4 at 34, 43) This provision was included in the contract (R4, tab 9 at 76).

6. Jemison submitted various questions to the Corps during negotiation of the contract. The Corps answered a question from Jemison related to the topsoil in an amendment to the solicitation issued on January 28, 2019:

Q1. . . . [C]an we retain the same estimated quantities for top soil and add a qualification in the revised proposal that the actual quantities utilized will be verified by the USACE in the field? It is our understanding the USACE carefully confirms material quantities (such as top soil) in the field as work progresses. We understand that the

2 USACE will only pay for verified materials used in the project.

A1. . . . Measurement for this work shall be an in place top soil cubic yard measurement verified by the government. The topsoil quantities are provided as an aid to the bidder. The actual topsoil quantities used cannot exceed the government’s estimated quantities without a contract modification.

(R4, tab 7 at 2) The question and answer were included in the contract (R4, tab 9 at 15).

7. The Board finds based on Jemison’s use of the phrases “[i]t is our understanding the USACE carefully confirms material quantities (such as top soil),” and “[w]e understand that the USACE will only pay for verified materials used in the project,” that Jemison understood that the Corps intended to measure in-place quantities and pay only for the topsoil placed.

8. Jemison submitted a final proposal on February 6, 2019. The final proposal included an “Estimated Quantity” for CLIN 0002 of 2,355 CY, at a unit price of $84, for an “Estimated Amount” of $197,820. Jemison added a note that stated:

The top soil estimate assumes the maximum cubic yards for the purpose of this bid proposal. In reality, the landscaping contractor does not anticipate using this volume of top soil and understands the top soil will be field verified by the USACE. . . .

(R4, tab 8 at 2)

9. The Board finds based on Jemison’s statement that the topsoil would be “field verified” that it continued to understand that payment would be for actual verified quantities. The Board further finds that Jemison or its subcontractor had conducted a takeoff of the amount of topsoil to be placed and had determined that the estimate in the solicitation was high.

10. The contract incorporated Federal Acquisition Regulation (FAR) 52.212-4, COMMERCIAL TERMS AND CONDITIONS – COMMERCIAL ITEMS (OCT 2018) (R4, tab 9 at 27). This clause contains the following terms relating to invoice and payment:

(g) Invoice.

3 (1) The Contractor shall submit an original invoice . . . to the address designated in the contract to receive invoices. An invoice must include—

...

(iv) Description, quantity, unit of measure, unit price and extended price of the items delivered;

(i) Payment—

(1) Items accepted. Payment shall be made for items accepted by the Government that have been delivered to the delivery destinations set forth in this contract.

FAR 52.212-4(g) & (i) (emphasis added)

11. Jemison began performance; all was well through the first two pay requests. In the first pay request for the period through April 30, 2019, Jemison requested payment for 452.78 CY of topsoil at $84/CY for a total of $38,033.52, which the Corps approved (R4, tab 11 at 2, 5).

12. In the second payment request for the period from May 1 to August 12, 2019, Jemison requested payment for an additional 1,206.61 CY of topsoil at $84/CY for a total of $101,355.24, which the Corps also approved (R4, tab 13 at 2, 8).

13. With this second payment request, Jemison included an updated planting log (see R4, tab 13 at 1). Consistent with the direction in the Measurement and Payment clause that “[t]he contractor shall take measurements subtracting rootball volume at each area requiring excavation and soil replacement,” the planting log showed an excavation quantity, a deduction for the rootball of the tree(s), and the resulting topsoil quantity (finding 5). For example, the first entry in the log, at station 1442, shows an excavation of 11.11 CY, minus a rootball of 0.125, resulting in a (rounded) topsoil quantity of 10.99 CY. 2 After 15 pages of such calculations, the planting log showed a topsoil quantity of 1,659.39 CY, which is the sum of the

2 The planting log submitted with the first payment request included the excavation and topsoil quantities, from which the rootball deduction can be calculated, but it did not explicitly state the rootball numbers (R4, tab 12).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Teg-Paradigm Environmental, Inc. v. United States
465 F.3d 1329 (Federal Circuit, 2006)
Metropolitan Area Transit, Inc. v. Nicholson
463 F.3d 1256 (Federal Circuit, 2006)
Blinderman Construction Co., Inc. v. The United States
695 F.2d 552 (Federal Circuit, 1982)
Fidelity Construction Company v. The United States
700 F.2d 1379 (Federal Circuit, 1983)
Edward R. Marden Corporation v. United States
803 F.2d 701 (Federal Circuit, 1986)
Blough v. United States
35 Cont. Cas. Fed. 75,675 (Court of Claims, 1989)
Hirsch v. United States
104 Ct. Cl. 45 (Court of Claims, 1945)

Cite This Page — Counsel Stack

Bluebook (online)
Jemison & Partners, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/jemison-partners-inc-asbca-2022.