Hawaiian Dredging Construction Company, Inc. v. United States

Court of Appeals for the Federal Circuit·Decided February 19, 2025·No. 23-1909·Unpublished

Opinion

NOTE: This disposition is nonprecedential.

United States Court of Appeals for the Federal Circuit

HAWAIIAN DREDGING CONSTRUCTION COMPANY, INC., Plaintiff-Appellant

v.

UNITED STATES, Defendant-Appellee

2023-1909

Appeal from the United States Court of Federal Claims in No. 1:22-cv-00339-CNL, Judge Carolyn N. Lerner.

Decided: February 19, 2025

MICHAEL ZISA, Peckar & Abramson, P.C., Washington, DC, argued for plaintiff-appellant.

RUSSELL JAMES UPTON, Commercial Litigation Branch, Civil Division, United States Department of Justice, Washington , DC, argued for defendant-appellee. Also represented by BRIAN M. BOYNTON, MARTIN F. HOCKEY, JR., PATRICIA M. MCCARTHY.

2 HAWAIIAN DREDGING CONSTRUCTION COMPANY, INC. v. US

Before DYK, CLEVENGER, and PROST, Circuit Judges.

PROST, Circuit Judge.

Hawaiian Dredging Construction Company (“HDCC”)

appeals a decision from the United States Court of Federal Claims (“CFC”) granting the government’s Rule 12(b)(6) of the Rules of the CFC (“RCFC”) motion to dismiss HDCC’s complaint for failure to state a claim upon which relief can be granted. See Hawaiian Dredging Constr. Co., Inc v. United States, No. 22-339, 2023 WL 1979542 (Fed. Cl. Feb. 14, 2023) (“Opinion”). For the reasons that follow, we agree with the CFC’s conclusion that HDCC has not pled sufficient facts to demonstrate excusable delay regarding its retaining wall construction, but disagree that the alleged government delays regarding the Rights of Way (“ROWs”) delivery and utility relocation related claims, as well as HDCC’s repayment claim, are ripe for granting the government’s motion to dismiss under RCFC 12(b)(6). We also conclude that HDCC’s claim that the final ROWs delivered by the government differed from the ROWs as stated in the request for proposals should not have been dismissed. We thus affirm in part, reverse in part, and remand for further proceedings.

BACKGROUND

The United States Department of Transportation, acting through the Federal Highway Administration, Central Federal Lands Highway Division (“the agency”), selected HDCC as a general contractor for the Lahaina Bypass 1B- 2 design-build construction project in Lahaina, Maui, Hawaii (“the Project”). The Project was to relocate the terminus of the Lahaina Bypass, which included roadway extensions, overpass, culvert construction, and the installation of road and bridge safety features. On June 3, 2016, the agency awarded HDCC a firm fixed-price contract to complete the Project and issued a notice to proceed (“NTP”) on June 29, 2016, to begin work.

HAWAIIAN DREDGING CONSTRUCTION COMPANY, INC. v. US 3

While HDCC’s contract work was substantially completed by July 24, 2018, on July 17, 2020, HDCC filed a Contract Disputes Act (“CDA”) claim requesting an “equitable adjustment for various delays and increased costs during its [c]ontract performance.” Opinion, 2023 WL 1979542, at *3. HDCC alleged that it required final ROWs from landowners near the highway, relocation of overhead utilities, and construction permits; and the government’s “failure to secure the ROWs in a timely manner,” and differences between the final ROWs and the ROWs proposed in the request for proposals (“RFP”), caused HDCC to suffer construction delays and increased costs. Id. HDCC also alleged that it experienced excusable delays due to government changes and additions to the contract work relating to the retaining wall construction.

On March 30, 2021, the contracting officer (“CO”) issued its final decision denying HDCC’s CDA claim. J.A. 53–146. On March 29, 2022, HDCC filed its complaint at the CFC, followed by an amended complaint, seeking $6,576,968 in damages and specific costs, 190 compensable and excusable days of delay, and 482 days of excusable delay .

The government moved to dismiss the amended complaint under RCFC 12(b)(6) for failure to state a claim upon which relief may be granted because “HDCC bore the risk of increased costs” under the terms of the contract. J.A. 1622. The CFC found that HDCC “failed to plausibly allege that there were [g]overnment directed changes to the [c]ontract” because “[w]hat HDCC interprets as changes are, in fact, obstacles that arose during contract performance which deviated from assumptions HDCC held at the time of its bid.” Opinion, 2023 WL 1979542, at *10. The CFC concluded that the amended complaint does not state a claim upon which relief may be granted and granted the government’s motion to dismiss without prejudice. Id. at *11.

4 HAWAIIAN DREDGING CONSTRUCTION COMPANY, INC. v. US

HDCC timely appealed. We have jurisdiction under 28 U.S.C. § 1295(a)(3).

DISCUSSION

“We review the Court of Federal Claims’ legal conclusions de novo and its factual findings for clear error.” Shell Oil Co. v. United States, 896 F.3d 1299, 1306 (Fed. Cir. 2018). Contract interpretation is a question of law that we review de novo. Pac. Gas & Elec. Co. v. United States, 536 F.3d 1282, 1284–85 (Fed. Cir. 2008) (citing Winstar Corp. v. United States, 64 F.3d 1531, 1540 (Fed. Cir. 1995) (en banc), aff’d, 518 U.S. 839 (1996)). “We review a grant of a motion to dismiss for failure to state a claim de novo. To withstand a motion to dismiss under Rule 12(b)(6) of the RCFC, a complaint must contain ‘enough facts to state a claim to relief that is plausible on its face.’” Frankel v. United States, 842 F.3d 1246, 1249 (Fed. Cir. 2016) (quoting Bell Atl. Corp. v. Twombly, 550 U.S. 544, 570 (2007)). “In deciding a motion to dismiss, a court is required to accept as true all factual allegations pleaded.” Id.

On appeal, HDCC argues that the CFC erred in (1) dismissing HDCC’s amended complaint under RCFC 12(b)(6), (2) dismissing a portion of HDCC’s claims that were not subject to the motion to dismiss, and (3) denying its motion for reconsideration of and/or relief from the order of dismissal and its motion for leave to amend. We address each argument in turn.

I

HDCC alleges that because it “experienced numerous impacts and delays that were caused by the [g]overnment,” it may seek to recover time and costs associated with government impacts and delays. Appellant’s Br. 5. Specifically , HDCC argues that the CFC erred in granting the government’s motion to dismiss because the CFC did not accept all of HDCC’s well pled factual allegations as true in the light most favorable to HDCC, including that the

HAWAIIAN DREDGING CONSTRUCTION COMPANY, INC. v. US 5

government caused project schedule delays which prevented HDCC from timely completing the contract with regard to (a) work requiring ROWs, (b) utility relocation, and (c) retaining wall construction. J.A. 29–32.

A

Turning to the work requiring ROWs, HDCC argues that the government “failed to timely provide the final ROW for the Project,” and “when the [g]overnment finally provided the final ROW four months after issuing the NTP, it was materially and unforeseeably different from the ROW that was included in the RFP and upon which HDCC had based its bid and developed its design.” Appellant’s Br. 13. Such “failure to timely secure and provide the final ROW,” according to HDCC, “constituted a constructive change because it forced HDCC to perform additional work and caused delays to HDCC’s performance.” Id. at 23.

The government argues that “HDCC failed to point to any provision of the [c]ontract requiring the agency to timely secure the final ROWs by any particular date certain , and also failed to identify any changes to ROWs.” Appellee ’s Br. 31–32. Additionally, the contract incorporated Federal Acquisition Regulation (“FAR”) 52.236-7, which states:

The Contractor shall, without additional expense to the Government, be responsible for obtaining any necessary licenses and permits, and for complying with any Federal, State, and municipal laws, codes, and regulations applicable to the performance of the work.

Free access — add to your briefcase to read the full text and ask questions with AI

Hawaiian Dredging Construction Company, Inc. v. United States, (Fed. Cir. 2025).

Hawaiian Dredging Construction Company, Inc. v. United States (Hawaiian Dredging Construction Company, Inc. v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

United States v. Winstar Corp.
518 U.S. 839 (Supreme Court, 1996)
Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Pacific Gas & Electric Co. v. United States
536 F.3d 1282 (Federal Circuit, 2008)
Teg-Paradigm Environmental, Inc. v. United States
465 F.3d 1329 (Federal Circuit, 2006)
C. Sanchez and Son, Incorporated v. United States
6 F.3d 1539 (Federal Circuit, 1993)
Coast Federal Bank, Fsb v. United States
323 F.3d 1035 (Federal Circuit, 2003)
bell/heery v. United States
739 F.3d 1324 (Federal Circuit, 2014)
Frankel v. United States
842 F.3d 1246 (Federal Circuit, 2016)
Shell Oil Company v. United States
896 F.3d 1299 (Federal Circuit, 2018)
Winstar Corp. v. United States
64 F.3d 1531 (Federal Circuit, 1995)