Northrop Grumman Systems Corporation v. United States

CourtUnited States Court of Federal Claims
DecidedJuly 13, 2022
Docket12-286
StatusPublished

This text of Northrop Grumman Systems Corporation v. United States (Northrop Grumman Systems Corporation v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Northrop Grumman Systems Corporation v. United States, (uscfc 2022).

Opinion

No. 12-286C (Originally filed: June 27, 2022) (Re-filed: July 13, 2022) 1

**********************

NORTHROP GRUMMAN SYSTEMS CORPORATION, Contracts; Contract Plaintiff, Disputes Act, 41 U.S.C. §§ 7101-7109 (2018); v. delay; disruption; changes; counterclaim; THE UNITED STATES, expectancy damages; lost savings. Defendant.

John W. Chierichella, Washington, DC, with whom were Anne B. Perry, David S. Gallacher, Christopher M. Loveland, and Townsend L. Bourne, for plaintiff. Maureen Del Duca and Mark Ries, of counsel.

Cameron Cohick, Senior Trial Counsel, United States Department of Justice, Civil Division, Commercial Litigation Branch, Washington, DC, Christopher J. Carney, Senior Litigation Counsel, Sarah E. Harrington, Deputy Assistant Attorney General, Martin F. Hockey, Jr., Acting Director, with whom were Rebecca S. Kruser and Michael D. Snyder, Trial Attorneys, for defendant. Michael F. Kiely, United States Postal Service, Law Department, of counsel.

1 This opinion was originally filed under seal to afford the parties an opportunity to propose any appropriate redactions. The parties have since agreed that none are necessary. The opinion thus appears in full. OPINION

BRUGGINK, Judge.

In 2007, the United States Postal Service (“the Postal Service”) entered into a contract with Northrop Grumman Systems Corporation (“Northrop”) for Northrop to build and deliver 102 Flats Sequencing System machines (“FSS machines”) for a fixed price of $874 million. Following delivery and acceptance of those machines, in 2012, Northrop filed suit under the Contract Disputes Act, 41 U.S.C. §§ 7101-7109 (2018) (“CDA”), claiming that the Postal Service breached the contract by delaying and disrupting Northrop’s performance as well as withholding payments owed. The Postal Service counter-claimed, alleging, inter alia, that plaintiff failed to timely deliver the machines.

The court held trial over eight weeks between February 3, 2020, and March 5, 2021. The parties filed post-trial briefs, and the court held post-trial oral argument on December 8, 2021. We find for the reasons set out herein that neither party is entitled to recover on their principal claims for delay, that plaintiff is entitled to recover its unpaid contract balance, along with three specific additional cost claims, and that the government is entitled to certain offsetting claims.

BACKGROUND

I. Postal Service Automation Leading to the Flats Sequencing System

Over the course of the last two decades, the Postal Service has deployed a variety of automation machines to sort and sequence the mail it delivers to reduce the labor involved prior to delivery. The Postal Service’s goal has been to decrease the time its employees spend on sorting and sequencing mail. The Postal Service delivers many sizes of mail and parcels. Here, we are exclusively concerned with “flats,” which is an intermediate size of mail such as catalogs or flyers.

Among the earlier projects, the Postal Service contracted with Northrop for a machine to develop a simple sorting procedure for use with flat mail, known as the Automated Flat Sorting Machine (“AFSM”). Next, in the early 2000s, the Postal Service sought a machine to sequence flat mail into delivery point sequence. The Postal Service began by contracting with Northrop in 2003 to build such a prototype flats sequencing machine. The prototype machine was a half-sized Flats Sequencing System (“FSS”) machine or a “proof of concept” machine.

2 Northrop satisfactorily built a prototype, and the Postal Service modified the prototype contract in 2006 to direct Northrop to build one pre- production FSS machine (“Pre-Production Contract”). The goal of the Pre- Production Contract was to build a single FSS machine that would sort the mail into delivery point sequence. The machine used many of the same mechanisms and methods that appeared on the later FSS production machines. The design of the FSS machine evolved over time, however, from prototype through pre-production to production. From the prototype to the pre-production machine, Sean Ledford, Northrop’s FSS Program Manager of Engineering, estimated that 75% of the design was mature. 2 The remaining 25% of machine design was not finished until after commencement of the production stage.

Despite only initiating and not completing a contract to produce one model FSS machine, the Postal Service quickly forged ahead with plans for the follow-on contract to produce 100 working FSS machines. The Postal Service’s plan was to roll out several phases of the FSS machine program with multiple purchases of dozens of machines. In the first phase of this project, the same year that Northrop and the Postal Service contracted for one pre-production FSS machine, the Postal Service also sought proposals for a contractor to build and install 100 production machines. Northrop submitted a proposal in July 2006. At this point, the pre-production machine was still undergoing design reviews, and the design was not finalized.

After Northrop made a series of proposal revisions, on February 23, 2007, the Postal Service awarded Northrop an $874 million firm fixed price contract to build and install 100 FSS machines for deployment in postal locations across the country (“FSS Production Contract”). The contract also included a First Article Test FSS machine and a training FSS machine, bringing the total to 102 machines. Along with the machines, the FSS Production Contract called for Northrop to develop and deliver voluminous documentation and various other deliverables to aid the Postal Service in installing, moving, maintaining, and trouble-shooting the machines. In context, the parties entered the FSS Production Contract months before the Pre-Production Machine reached its In-Plant Test, which occurred between August 20, 2007 and September 11, 2007.

In sum, as of February 2007, the Postal Service had contracted to buy 102 FSS machines, the design for which was incomplete and the performance

2 Mr. Ledford’s role in the FSS Program is depicted on the organizational chart in Background Section III.

3 of which was untested. Northrop, for its part, had agreed to design, build, and install those machines, along with a host of other deliverables, for a firm fixed price and before it had completed even one pre-production machine. From the standpoint of hindsight, the parties allowed optimism to triumph over caution. While the parties are to be congratulated on eventually persisting in the face of serious obstacles to the design, production, and delivery of all of the machines, machines which are remarkable to behold in operation, the fact remains that their collective lack of preparedness triggered ten years of litigation. 3

II. Flats Sequencing System Production Machine

In terms of size, one FSS machine would comfortably fill half of a football field. Sean Ledford, Northrop’s engineering manager on the project, explained the process of flats moving through the FSS machine, which consists of a series of inter-connected features—a system of systems. The design as eventually completed included mail being processed through various elements of the FSS. The process begins at the Standalone Mail Preparation (“SAMP”) part of the machine. Mail enters the SAMP at the Automatic Bundle Sorting Unit (“ABSU”), which is basically a hopper. “You put a pallet in, and it tilts it over” and tied bundles of mail fall out. Tr. 2432, 2436 (Ledford). After dumping, the mail moves across a conveyor to prep stations. Postal Service employees cut the bundles open and put the mail in green trays.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
Northrop Grumman Systems Corporation v. United States, Counsel Stack Legal Research, https://law.counselstack.com/opinion/northrop-grumman-systems-corporation-v-united-states-uscfc-2022.