New England Specialty Services, Inc. v. United States

CourtUnited States Court of Federal Claims
DecidedMay 26, 2020
Docket19-643
StatusPublished

This text of New England Specialty Services, Inc. v. United States (New England Specialty Services, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
New England Specialty Services, Inc. v. United States, (uscfc 2020).

Opinion

In the United States Court of Federal Claims No. 19-643C

(Filed: May 26, 2020)

) NEW ENGLAND SPECIALTY ) Contract claim; motion for summary SERVICES, INC., ) judgment; genuine issues of material fact ) Plaintiff, ) ) v. ) ) UNITED STATES, ) ) Defendant. ) )

Scott K. DeMello, Lepizzera & Laprocina Counsellors at Law, Warwick, RI, for plaintiff.

Robert R. Kiepura, Trial Attorney, Commercial Litigation Branch, Civil Division, United States Department of Justice, Washington, D.C., for defendant. With him on the briefs were Joseph H. Hunt, Assistant Attorney General, Civil Division, and Robert E. Kirschman, Jr., Director, and Deborah A. Bynum, Assistant Director, Commercial Litigation Branch, Civil Division, United States Department of Justice, Washington, D.C. Of counsel was Theresa Negron, Deputy District Counsel, New England District, United States Army Corps of Engineers.

OPINION AND ORDER

LETTOW, Senior Judge.

This case presents a dispute over a design-build contract for the construction of a pre- engineered metal building and related site work in Natick, Massachusetts for the United States Army Corps of Engineers. Plaintiff, New England Specialty Services, Inc. (“NESS”), has brought suit against the United States (“the government”), alleging, inter alia, breach of contract and unreasonable delay. Pending before the court is defendant’s motion for summary judgment (“Def.’s Mot.”), ECF No. 13. Plaintiff opposes this motion. See Pl.’s Resp. to Def.’s Mot. (“Pl.’s Resp.”), ECF No. 14. Following the conclusion of briefing, see Def.’s Reply, ECF No. 15, a hearing was held on May 7, 2020, and the parties filed supplemental briefs on May 18, 2020, see ECF Nos. 20, 22. BACKGROUND 1

On September 26, 2015, New England Specialty Services, Inc., was awarded a firm-fixed price contract, Contract No. W912WJ-15-C-0032, to construct a storage warehouse located at the U.S. Army Soldier Systems Center in Natick, Massachusetts. See Def.’s App. at 1-2. 2 The project consisted mainly of two tasks: (1) constructing a pre-engineered metal building and (2) site work which included installation of an electrical duct bank, concrete masonry units, grout, and air curtains. See id. at 3; Compl. ¶ 11, ECF No 1. The contract provided for 425 calendar days within which to complete the project following issuance of the notice of proceed, see Def.’s App. at 1, making the required contract completion date December 3, 2016.

NESS’s first project baseline schedule, including a critical path layout and narrative, projected the completion date of the project to be August 3, 2016. See Pl.’s App. at 342. As the project moved forward, however, numerous issues arose that caused the completion date to be delayed. See, e.g., id. at 344 (noting an initial delay due to a flawed contract specification). The project was not completed until February 16, 2017, 75 days later than the original contract completion date, see Def.’s App. at 874, and 134 working days later than the original NESS schedule completion date of August 3, 2016, id. at 898. At the heart of this dispute is whether it is the government or NESS who is responsible for the delays and who, then, should bear the associated costs.

Relevant to plaintiff’s claims are six bilateral modifications that were issued while project work was ongoing, which adjusted the scope of work under the contract. See Def.’s App. at 836- 68. Notably, the required contract completion date was not changed by these modifications. Id. Most relevant to the claims here are Modifications 3, 4, 5, and 6. Modification 3 related to “various structural changes,” id. at 844; Modification 4 related to “electrical ductbank changes,” id. at 847; Modification 5 related to more “electrical changes,” id. at 851; and Modification 6 related to small structural and mechanical changes, see id. at 863-64. Each of these modifications included release language noting that “the contract time is not affected,” “the contract price is increased as stated . . . which reflects all credits due the Government and all debits due the Contractor,” and “this adjustment constitutes compensation in full on behalf of the Contractor and its Subcontractors and Suppliers for all costs and markups directly or indirectly attributable [to] the change ordered [and] for all delays related thereto . . .” See id. at 846, 849, 854, 865.

1 The following recitations do not constitute findings of fact by the court. Instead, the recited factual elements are taken from the complaint and the parties’ briefs and attached appendices. 2 Both plaintiff and defendant attached appendices to their briefs. Both appendices were consecutively paginated. Defendant’s appendix will be cited as “Def.’s App. at [page number]” and plaintiff’s appendix will be cited as “Pl.’s App. at [page number].”

2 NESS submitted a certified claim to the contracting officer on April 25, 2018. See id. at 869-900. In its claim, NESS sought costs for schedule delays, costs for alleged changes in the contract terms, including structural changes to the air curtain, painting of structural beams, an additional support for an overhead door, additional as-built drawings, and preparation of claim costs, as well as a rejection of liquidated damages threatened by the contracting officer’s representative. See id. at 874. The contracting officer issued the final decision on these claims, granting them only in part, on December 21, 2018. See Pl.’s App. at 338-52. 3 Subsequently, NESS filed its complaint in this court seeking $542,105.86 in damages, inclusive of delay costs and direct costs, and the release of its final payment as previously sought in the certified claim. See Compl. at 15.

STANDARDS FOR DECISION

The court shall grant summary judgment “if the movant shows that there is no genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law.” Rule 56(a) of the Rules of the Court of Federal Claims (“RCFC”). A material fact is one that “might affect the outcome of the suit.” Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248 (1986) (interpreting Fed. R. Civ. P. 56). 4 A genuine dispute exists when the finder of fact may reasonably resolve the dispute in favor of either party. Id. at 250.

The movant bears the burden of demonstrating the absence of any genuine disputes of material fact, see Celotex Corp. v. Catrett, 477 U.S. 317, 322 (1986), and shall “cite[] to particular parts of materials in the record, including depositions, documents, electronically stored information, affidavits or declarations, stipulations . . . , admissions, interrogatory answers, or other materials,” RCFC 56(c)(1)(A). The court may consider other materials in the record even if not cited by the parties. RCFC 56(c)(3). “[T]he inferences to be drawn . . . must be viewed in the light most favorable to the party opposing the motion.” Matsushita Elec. Indus. Co. v. Zenith Radio Corp., 475 U.S. 574, 587 (1986) (quoting United States v. Diebold, Inc., 369 U.S. 654, 655 (1962)). If the record taken as a whole “could not lead a rational trier of fact to find for the non-moving party, there is no ‘genuine issue for trial’” and summary judgment is appropriate. Matsushita, 475 U.S. at 587 (quoting First Nat’l Bank of Ariz. v. Cities Serv. Co., 391 U.S.

Related

United States v. Diebold, Inc.
369 U.S. 654 (Supreme Court, 1962)
First Nat. Bank of Ariz. v. Cities Service Co.
391 U.S. 253 (Supreme Court, 1968)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Mega Construction Co. v. United States
39 Cont. Cas. Fed. 76,564 (Federal Claims, 1993)
Jackson Construction Co. v. United States
62 Fed. Cl. 84 (Federal Claims, 2004)
Weaver-Bailey Contractors, Inc. v. United States
37 Cont. Cas. Fed. 76,227 (Court of Claims, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
New England Specialty Services, Inc. v. United States, Counsel Stack Legal Research, https://law.counselstack.com/opinion/new-england-specialty-services-inc-v-united-states-uscfc-2020.