Weaver-Bailey Contractors, Inc. v. United States

37 Cont. Cas. Fed. 76,227, 24 Cl. Ct. 576, 1991 U.S. Claims LEXIS 557, 1991 WL 257802
CourtUnited States Court of Claims
DecidedDecember 2, 1991
DocketNo. 137-87C
StatusPublished
Cited by14 cases

This text of 37 Cont. Cas. Fed. 76,227 (Weaver-Bailey Contractors, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Weaver-Bailey Contractors, Inc. v. United States, 37 Cont. Cas. Fed. 76,227, 24 Cl. Ct. 576, 1991 U.S. Claims LEXIS 557, 1991 WL 257802 (cc 1991).

Opinion

OPINION

SMITH, Chief Judge.

Weaver-Bailey Contractors, Inc., seeks an award of its attorneys’ fees and expenses in the amount of $55,226.10 under the Equal Access to Justice Act (EAJA), 28 U.S.C.A. § 2412 (1988). For the reasons set forth below, the court finds Weaver-Bailey is entitled to recover $41,744.69 under the EAJA.

FACTS

The relevant facts are set forth in an earlier published opinion, Weaver-Bailey Contractors, Inc. v. The United States, 19 Cl.Ct. 474 (1990), and are repeated only to the extent necessary here. In July, 1984, Weaver-Bailey and the government entered into a contract for the improvement of the recreation area surrounding Arcadia Lake in Edmond, Oklahoma. Most of the job consisted of earthwork, such as cutting slopes and filling in low areas. The project was delayed when it was discovered that the United States Corps of Engineers (Corps) significantly underestimated the unclassified excavation1 necessary to complete the earthwork.

The case came before the court as a direct access appeal from the contracting officer’s denial of Weaver-Bailey’s request for an equitable adjustment. The central issue in litigation was which party was responsible for the delay in contract completion. The court found that the government was solely responsible for the delay in performance of the contract due to the Corps’ underestimation of the amount of unclassified excavation for the job. On February 9, 1990, a judgment in the amount of $469,041.00, with interest under the Contract Disputes Act, was entered in favor of Weaver-Bailey.

Defendant filed a Motion for Reconsideration on March 5, 1990, which was denied on April 17, 1990. Defendant then appealed to the United States Court of Appeals for the Federal Circuit. On October 2, 1990, the defendant’s appeal was dismissed. Weaver-Bailey then filed its application for attorney’s fees and other expenses under EAJA.

DISCUSSION

1. SUBSTANTIAL JUSTIFICATION

In order to be eligible for an award of attorney fees, Weaver-Bailey must first show that it was the prevailing party in the litigation and that it meets net worth and employment requirements. These threshold requirements are not in dispute; Weaver-Bailey is a prevailing party within the meaning of EAJA, has a net worth of less than $7,000,000 and employs fewer than 500 people.

[578]*578In addition to these threshold requirements, the government’s position in the litigation must not have been substantially justified. “Substantially justified” does not mean “ ‘justified to a high degree,’ but rather ‘justified in substance or in the main’—that is, justified to a degree that could satisfy a reasonable person____ [The Government’s position must have a] reasonable basis both in law and fact.” Pierce v. Underwood, 487 U.S. 552, 565, 108 S.Ct. 2541, 2550, 101 L.Ed.2d 490 (1988). Moreover, the fact that plaintiff prevailed does not necessarily result in a grant of attorney fees.

“[T]he EAJA was not intended to be an automatic fee-shifting device in cases where the [plaintiff] prevails ... [Substantial justification is to be decided case-by-case on the basis of the record.” Luciano Pisoni Fabbrica Accessori Instrumenti Musicali v. United States, 837 F.2d 465, 467 (Fed.Cir.1988). In the instant case, an examination of the record and review of precedent make it clear that the government’s position was not substantially justified.

The government has the burden of demonstrating substantial justification for its position. Cox Constr. Co. v. United States, 17 Cl.Ct. 29, 32 (1989), citing Gavette v. Office of Personnel Management, 808 F.2d 1456, 1465-66 (Fed.Cir.1986). Placing the burden on the government to prove the reasonableness of its actions “encourages parties to contest action they believe to be unreasonable and thereby serves to refine public policy.” Gavette, 808 F.2d at 1465, quoting H.R.REP. No. 1418 at 18, 1980 U.S.CODE CONG. & AD. NEWS at 4953, 4997. In a sense, an EAJA applicant’s success on the merits presents a prima facie showing of entitlement to attorney fees which shifts the burden to the government to prove substantial justification.

Here, defendant argues that its position was reasonably based in fact and law. The government had two defenses. First, the government maintained that this was not a delay case; and, second, assuming there was a delay, the government was not its sole cause. The basis for the first argument was that Weaver-Bailey projected that it would use the entire time allotted under the contract (until February 13, 1985) to complete performance. In addition, the completion date was extended due to inclement weather and Weaver Bailey completed performance within that extended period. However, Weaver-Bailey argued that it intended to complete performance prior to the original February completion date to avoid doing earthwork during the winter.

A contractor may recover damages for government-caused delay to the contractor’s early completion of performance if the contractor establishes that it could realistically complete the project early. B. Bramble & M. Callahan, Construction Delay Claims § 4.2 (1987). The government introduced evidence, namely two construction progress charts, to dispute Weaver-Bailey’s intent and ability to complete the project early. Weaver-Bailey’s charts projected not an early completion date, but rather a completion date in accordance with the contract.

As evidence of its planned early completion, Weaver-Bailey relied on the testimony of Marion Stephenson, the project manager, who testified that he told Corps personnel of his intent at the pre-work conference. This testimony was contradicted by the Corps personnel who testified that they did not recall Mr. Stephenson ever making such a statement. However, as the court noted,

[t]he proper focus is not whether Weaver-Bailey informed the government, at the inception of the contract, that it intended to complete the project before winter; rather the focus should be on whether Weaver-Bailey would have completed the project early, but for the government-caused delay.

Weaver-Bailey, 19 Cl.Ct. at 479 (emphasis in the original). See also Metropolitan Paving Co. v. United States, 325 F.2d 241, 163 Ct.Cl. 420, 423 (1963) (Whether the parties planned an early completion makes little difference; important inquiry is whether the government’s actions prevent[579]*579ed the contractor from early completion). The court found that Weaver-Bailey would have completed the project early, but for the Corps’ underestimation of the amount of required unclassified excavation. Id.

Defendant now argues that the court’s finding that Weaver-Bailey established early completion rested on credibility findings of the witnesses and evidence. Therefore, the court is not precluded from finding here that the government’s position in this respect was substantially justified. See United Constr. Co., Inc. v. United States, 11 Cl.Ct.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Q Integrated Companies, LLC v. United States
133 Fed. Cl. 479 (Federal Claims, 2017)
Metropolitan Van & Storage, Inc. v. United States
101 Fed. Cl. 173 (Federal Claims, 2011)
United Partition Systems, Inc. v. United States
95 Fed. Cl. 42 (Federal Claims, 2010)
Infinite Information Solutions, LLC v. United States
94 Fed. Cl. 740 (Federal Claims, 2010)
Dalles Irrigation District v. United States
91 Fed. Cl. 689 (Federal Claims, 2010)
ACE Constructors, Inc. v. United States
81 Fed. Cl. 161 (Federal Claims, 2008)
Geo-Seis Helicopters, Inc. v. United States
79 Fed. Cl. 74 (Federal Claims, 2007)
Jackson Construction Co. v. United States
62 Fed. Cl. 84 (Federal Claims, 2004)
Lion Raisins, Inc. v. United States
57 Fed. Cl. 505 (Federal Claims, 2003)
R.C. Construction Co. v. United States
42 Cont. Cas. Fed. 77,389 (Federal Claims, 1998)
Prowest Diversified, Inc. v. United States
42 Cont. Cas. Fed. 77,204 (Federal Claims, 1997)
PCI/RCI v. United States
37 Fed. Cl. 785 (Federal Claims, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
37 Cont. Cas. Fed. 76,227, 24 Cl. Ct. 576, 1991 U.S. Claims LEXIS 557, 1991 WL 257802, Counsel Stack Legal Research, https://law.counselstack.com/opinion/weaver-bailey-contractors-inc-v-united-states-cc-1991.