PCI/RCI v. United States

37 Fed. Cl. 785, 1997 U.S. Claims LEXIS 97, 1997 WL 251739
CourtUnited States Court of Federal Claims
DecidedMay 14, 1997
DocketNo. 96-575C
StatusPublished
Cited by24 cases

This text of 37 Fed. Cl. 785 (PCI/RCI v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
PCI/RCI v. United States, 37 Fed. Cl. 785, 1997 U.S. Claims LEXIS 97, 1997 WL 251739 (uscfc 1997).

Opinion

ORDER

MILLER, Judge.

This case is before the court on plaintiffs application for attorneys’ fees and expenses pursuant to the Equal Access to Justice Act (the “EAJA”), 28 U.S.C. § 2412 (1994). The court must decide whether defendant’s position in this dispute was substantially justified.

[787]*787PACTS

The facts relevant to this pre-award bid protest, in which plaintiff sought injunctive relief restraining the Government from awarding a contract for a building project to any bidder other than plaintiff, are set forth in PCI/RCI, A Joint Venture v. United States, 36 Fed. Cl. 761 (1996), and are discussed in summary fashion.

PCI/RCI, a Joint Venture (“PCI/RCF or “plaintiff’), consisting of Roers’ Construction, Inc. (“RCI”), and Professional Contractors, Inc. (“PCI”), submitted a bid, bid bond, and certificate of procurement integrity signed by James Roers “Partner” or “Managing Partner” for a project known as the Modernization of the Federal Building/Post Of-fiee/Courthouse, Bismarck, North Dakota, Project No. IND96016. After determining that plaintiff was the apparent low bidder, the General Services Administration (“GSA”) inquired into whether plaintiff was in fact a bona fide affiliation and, if so, whether Mr. Roers’ signature alone was sufficient to bind the joint venture.

Following several unsuccessful efforts to satisfy GSA’s inquiries, plaintiffs bid was deemed non-responsive. Preaward Contracting Officer Ann N. Fleekenstein informed plaintiff by letter dated August 23, 1996, that “there was nothing in the agreement giving James P. Roers the authority to bind the joint venture or PCI.” Ms. Flecken-stein based her decision, in part, on Federal Acquisition Regulation (“FAR”) § 4.102(d), 41 C.F.R. § 4.102(d) (1996), which requires each participant in a joint venture to sign the contract. After reconsideration Ms. Fleeken-stein, by letter dated August 26, 1996, further opined that “[e]ach participant in a joint venture is required to sign the bid and furnish evidence that one has the authority to bind the other.”

Plaintiff initiated a pre-award bid protest action seeking injunctive relief to prevent GSA from awarding the contract to any other bidder. In evaluating plaintiffs claim, the court recognized that a breach of an implied contract only “ ‘occurs ... if the contracting agency acts in an arbitrary and capricious, i.e., irrational or unreasonable, manner in rejecting the bid.’ ” PCI/RCI, 36 Fed. Cl. at 767 (quoting NKF Eng’g Inc. v. United States, 805 F.2d 372, 375 (Fed.Cir.1986)). To prevail in the underlying litigation, plaintiff was required to demonstrate, by a preponderance of the evidence, that the agency’s actions 1) were without a rational or reasonable basis, or 2) violated an applicable procurement statute or regulation. See id. (citing CACI Field Servs., Inc. v. United States, 854 F.2d 464, 466 (Fed.Cir.1988) (per curiam)).

Despite the significant hurdles facing plaintiff, the court granted its request for injunctive relief. Consistent with the Federal Circuit’s decision in Sadelmi Joint Venture v. Dalton, 5 F.3d 510 (Fed.Cir.1993), the court applied the fundamental principle of joint venture law that participants in a bona fide joint venture are permitted to apportion their respective responsibilities as they see fit. Noting that the contracting officer erroneously applied FAR § 4.102(d), thereby establishing an invalid requirement with which plaintiff was unable to comply, the court found that the contracting officer’s decision requiring two signatures to bind the joint venture was either irrational or unreasonable. After prevailing in the litigation phase, plaintiff filed this action pursuant to the EAJA, seeking $18,016.00 in attorneys’ fees and $3,419.57 for other expenses.

DISCUSSION

“The EAJA provides a specific waiver of sovereign immunity to enable persons who prevail in certain suits brought against the government to an award of attorney fees incurred in challenging the government’s action in court.” Chiu v. United States, 948 F.2d 711, 714 (Fed.Cir.1991). As a waiver of sovereign immunity, the EAJA must be construed strictly. Ruckelshaus v. Sierra Club, 463 U.S. 680, 685, 103 S.Ct. 3274, 3277-78, 77 L.Ed.2d 938 (1983). Eligibility for attorneys’ fees requires “1) that the claimant be a ‘prevailing party’; 2) that the Government position was not ‘substantially justified’; 3) that no special circumstances make an award unjust; and 4) that any fee application be submitted ... within 30 days of final judgment ... and be supported by an itemized statement.” Commissioner, Immi[788]*788gration & Naturalization Serv. v. Jean, 496 U.S. 154, 158, 110 S.Ct. 2316, 2319, 110 L.Ed.2d 134 (1990) (quoting 28 U.S.C. 2412(d)(1)(A)); see Doty v. United States, 71 F.3d 384, 385 (Fed.Cir.1995). The Government bears the burden of proving that its position was substantially justified. Gavette v. OPM, 808 F.2d 1456, 1465-66 (Fed.Cir. 1986) (en banc) (quoting H.R.Rep. No. 1418, 96th Cong., 2d Sess. 18, reprinted in 1980 U.S.C.C.A.N. 4984, 4997). Moreover, the Government must show that its actions were substantially justified throughout the entire dispute, not just the litigation phase. Id. at 1467. In determining whether a fee award is merited, the court will “make a judgment call” determining whether the Government’s position is substantially justified. Chiu, 948 F.2d at 715.

1. Entitlement

Plaintiff has based its motion, in part, on 28 U.S.C. § 2412(d)(1)(A), which provides that

[ejxeept as otherwise specifically provided by statute, a court shall award to a prevailing party other than the United States fees and other expenses ... incurred by that party in any civil action (other than cases sounding in tort), including proceedings for judicial review of agency action, brought by or against the United States in any court having jurisdiction of that action, unless the court finds that the position of the United States was substantially justified or that special circumstances make an award unjust.

Defendant concedes that plaintiffs petition was timely filed, that plaintiff meets the statutory eligibility requirements set forth in 28 U.S.C. § 2412(d)(2)(B)1, and that plaintiff is a prevailing party. See Def's Br. filed Mar. 17,1997, at 2.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Keirton USA, Inc. v. United States
2023 CIT 47 (Court of International Trade, 2023)
Small v. United States
130 Fed. Cl. 88 (Federal Claims, 2016)
Metropolitan Van & Storage, Inc. v. United States
101 Fed. Cl. 173 (Federal Claims, 2011)
Greenhill v. United States
96 Fed. Cl. 771 (Federal Claims, 2011)
United Partition Systems, Inc. v. United States
95 Fed. Cl. 42 (Federal Claims, 2010)
Universal Fidelity LP v. United States
70 Fed. Cl. 310 (Federal Claims, 2006)
Filtration Development Co., LLC v. United States
63 Fed. Cl. 612 (Federal Claims, 2005)
Lion Raisins, Inc. v. United States
57 Fed. Cl. 505 (Federal Claims, 2003)
Hopi Tribe v. United States
55 Fed. Cl. 81 (Federal Claims, 2002)
Preseault V. United States
52 Fed. Cl. 667 (Federal Claims, 2002)
Baldi Bros. Constructors v. United States
52 Fed. Cl. 78 (Federal Claims, 2002)
Brickwood Contractors, Inc. v. United States
49 Fed. Cl. 148 (Federal Claims, 2001)
Gutz v. United States
45 Fed. Cl. 291 (Federal Claims, 1999)
Massie v. United States
45 Fed. Cl. 213 (Federal Claims, 1999)
Gonzalez v. United States
44 Fed. Cl. 764 (Federal Claims, 1999)
California Marine Cleaning, Inc. v. United States
43 Fed. Cl. 724 (Federal Claims, 1999)
R.C. Construction Co. v. United States
42 Cont. Cas. Fed. 77,389 (Federal Claims, 1998)
Concept Automation, Inc. v. United States
42 Cont. Cas. Fed. 77,348 (Federal Claims, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
37 Fed. Cl. 785, 1997 U.S. Claims LEXIS 97, 1997 WL 251739, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pcirci-v-united-states-uscfc-1997.