Brickwood Contractors, Inc. v. United States

49 Fed. Cl. 148, 2001 U.S. Claims LEXIS 58, 2001 WL 355702
CourtUnited States Court of Federal Claims
DecidedApril 9, 2001
DocketNo. 99-388C
StatusPublished
Cited by5 cases

This text of 49 Fed. Cl. 148 (Brickwood Contractors, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brickwood Contractors, Inc. v. United States, 49 Fed. Cl. 148, 2001 U.S. Claims LEXIS 58, 2001 WL 355702 (uscfc 2001).

Opinion

ORDER

HORN, Judge.

This matter comes before the court on the application of Brickwood Contractors, Inc. (Brickwood) for attorneys’ fees and other expenses under the Equal Access to Justice Act (EAJA), 28 U.S.C. § 2412 (1994 & Supp. IV 1998). Plaintiff argues that it is entitled to an award of attorneys’ fees and expenses under EAJA because (1) plaintiffs bid protest prevented the Navy from converting an invitation for Bids (IFB) to a Request for Proposals (RFP), thereby making the plaintiff the prevailing party in the matter; and (2) the government could not have met the regulatory requirements for such a conversion from an IFB to an RFP under Federal Acquisition Regulation (FAR) 14.404-1, for which reason the United States was not substantially justified in its actions. Plaintiff meets the eligibility criteria under the EAJA and seeks $11,134.22 in fees and expenses incurred in pursuing the bid protest and the instant application. After careful consideration of the record before the court and the applicable law, the court finds that the defendant is liable to the plaintiff for EAJA fees and expenses.

FINDINGS OF FACT

On February 9, 1999, the Department of the Navy issued IFB No. N62477-97-B-0083, Repair Elevated Water Storage Tanks, Naval Air Station, Patuxent River, Maryland. On March 24, 1999, the Navy issued Amendment 0003, which added three options to the original IFB and solicited bids for each of these options. The Amendment 0003 options included removing contaminated paint, performing wipe samples, testing the wipe samples, and disposing of all contaminated and uncontaminated waste. Amendment 0003 also added an Evaluation of Options Clause which provided:

Except when it is determined in accordance with FAR 17.206(b) not to be in the Government’s best interests, the Government will evaluate offers for award purposes by adding the total price for all options to the total price for the basic requirement. Evaluation of option(s) will not obligate the Government to exercise the option(s).

On March 30, 1999, the Navy issued Amendment 0004, which among other changes, added PCB (Polychlorinated Biphenyl) contamination testing to the base requirements. Amendment 0004 explained the criteria for exercising the options by stating:

[I]f the above testing reveals that the exterior and/or interior paint coatings do contain PCB levels equal to or greater than 50 PPM, the elevated water storage tank debris will be considered a hazardous waste. In that event, the Government will award Options 1, 2, and/or 3 as the test results warrant.

[150]*150On April 6, 1999, five bids, including that of the plaintiff, were received and publicly opened. Based upon the total price (base bid plus options), the Navy identified plaintiff as the apparent low bidder. Due to significant disparities in the bids, however, the Navy requested a bid analysis to determine if the bids were unbalanced. Alpha Corporation, an independent consulting firm, issued a report on April 14,1999, which stated:

1. There appears to be a considerable difference in the Bidders’ understanding of the scope of work involved with the bid options.... As we all know, the interpretation of environmental regulatory requirements is both complex and variable. While the two low bidders interpreted the bid options properly, the other three low bidders appear to have misinterpreted the bid option requirements.
2. Because of the limited number of bidders, resulting from the limited number of appropriate tank manufacturers, statistical analysis of the distribution of bids is inconclusive. We feel that the even distribution of base bids within the bid result range (96% to 155% of the Government estimate) is common and appropriate.

Pursuant to Amendment 0004, the base specifications would have required the contractor to test for PCB contamination. However, in late April 1999, the Navy conducted tests on the water towers to determine if the options would ever need to be exercised. On April 29,1999, the Navy concluded that there was no evidence of PCB contamination. Therefore on May 5, 1999, the Navy issued a Determination and Findings for Evaluating Bids Exclusive of Options, announcing that the bids on the options would be excluded from the final price evaluation because they were no longer needed. If the options had been evaluated along with the base bids, plaintiff would have had the low bid. If the options had not .been evaluated, plaintiff would have been displaced by two other bidders who had lower base bids.

On June 15,1999, the Navy issued Amendment 0005 to the solicitation, which did not cancel,1 but extended, the solicitation by stating: “By amendment, this invitation for Bids (IFB) will be converted to a Request for Proposal (RFP) by the authority of Federal Acquisition Regulation (FAR) Part 14.404-1.” Because the government determined that the tanks contained no contaminated paint and that the options would never be exercised, Amendment 0005 also deleted the Evaluation of Options Clause and eliminated the requirements regarding PCBs.

On June 18, 1999, plaintiff filed a bid protest in the United States Court of Federal Claims alleging that “[t]he Navy’s attempt to convert an IFB to an RFP, however, is not authorized by FAR or any other law or regulation.” Plaintiff requested the court to enter judgment “enjoining the Navy from converting the IFB to an RFP,” and “directing that the Navy proceed with the award of the contract to Brickwood.”

On July 16, 1999, after plaintiff filed its lawsuit, the defendant issued Amendment 0009, by which the government did cancel the solicitation (N62477-97-R-0083), with the intention of offering a new IFB, this time without options and without a requirement for PCB testing. The Navy issued a Determination and Findings for Cancellation of Solicitation on July 16, 1999, stating that the “otherwise inadequate or ambiguous specifications for this project warrant cancellation and re-solicitation.” Defendant filed a motion to dismiss in this court, arguing that “[bjecause the cancellation renders the plaintiffs claim moot, the Court lacks jurisdiction and should dismiss this action.” This court dismissed plaintiffs protest on July 22, 1999, without reaching the merits of the case.

The next day, on July 23, 1999, plaintiff filed a second bid protest, this time contesting the cancellation of the IFB. The plaintiff requested the court to “[djeclare that the cancellation of the IFB was improper and enjoin further action by the Navy to resolicit [151]*151the services under a new IFB” and “[d]eclare that Brickwood is entitled to award of the contract under the procurement at issue in this action.” The plaintiff alleged that the Navy’s cancellation of the IFB had violated the FAR, constituted a breach of the implied obligation to treat each bid fairly and honestly, and initiated an improper auction. After reviewing the plaintiffs complaint and the applicable regulations, the court informed the plaintiff that it did not believe “that the Navy ha[d] acted arbitrarily or capriciously in canceling the bid and moving to award the contract through the issuance of a new solicitation.” The plaintiff voluntarily dismissed its second bid protest on September 27, 1999.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Universal Fidelity LP v. United States
70 Fed. Cl. 310 (Federal Claims, 2006)
Clarence W. Gosnell, Inc. v. Hensley
846 A.2d 469 (Court of Special Appeals of Maryland, 2004)
Brickwood Contractors, Inc. v. United States
288 F.3d 1371 (Federal Circuit, 2002)
Brickwood Contractors, Inc. v. United States
49 Fed. Cl. 738 (Federal Claims, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
49 Fed. Cl. 148, 2001 U.S. Claims LEXIS 58, 2001 WL 355702, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brickwood-contractors-inc-v-united-states-uscfc-2001.